HomeMy WebLinkAboutTuskawilla Borrow Pits-1992 RESPONSE TO QUESTIONS AND
RECOMMENDATIONS FOR BORROW PITS
TUSCAWILLA UNITS 14C & 15
A. RECOMMENDATIONS FROM CITY ENGINEER DATED MARCH 2 , 1992
1 . THE BORROW PITS, (EXCAVATION) IS TO BE CONSTRUCTED IN ACCORDANCE
WITH THE APPROVED ENGINEERING AND DOCUMENTS SUBMITTED ON FEBRUARY
28 , 1992 WITH REVISIONS DATED MARCH 2 , 1992 .
RESPONSE: Agreed. The construction will be supervised and
monitored on a regular basis by Michael D. Sims,
Geotechnical Engineer, for compliance with the
approved documents and monitoring of groundwater
effects. The City will be provided with copies of
such reports in connection with these activities.
2 . A PERFORMANCE BOND SHALL BE POSTED TO COVER THE PROPER COMPLETION
OF BORROW PITS IN ACCORDANCE WITH THE APPROVED ENGINEERING DESIGN.
RESPONSE: Agreed. A performance bond or a bond in the
aggregate amount of $905,000 has been requested by
the City Engineer and will be posted to insure
proper construction and reclamation according to
permit conditions and City codes.
3 . A PERFORMANCE BOND IS TO BE PROVIDED TO COVER ANY DAMAGE TO SENECA
BOULEVARD WHERE THE "BRIDGE CROSSING" IS TO BE PLACED.
RESPONSE: Agreed. $7, 000 is included in the performance
bond, with a specific provision to cover any
damage to Seneca Boulevard. Sullivan Materials,
Inc. ("Applicant") agrees to repair any damage
that may occur and restore the road to the
conditions existing prior to the excavation work.
4 . A CONSTRUCTION FENCE IS TO BE IN PLACE AROUND THE AREA WHERE
EXCAVATION IS ON-GOING.
RESPONSE: Agreed. A four (4) foot high barbed-wire fence
will be constructed and maintained (in conjunction
with existing fencing) during the entire operation
and will be removed upon completion of final
sloping of lake banks.
5. NO RESIDUAL MATERIAL WILL BE LEFT IN MOUNDS OR IN ANY OTHER
UNSIGHTLY MANNER.
RESPONSE: Agreed. Applicant will remove any residual
materials upon completion of work, will use best
efforts to maintain a neat and orderly work area.
RE11124T00011RTRTDG03.181 9 . o 3 a
P203184
6 . UPON COMPLETION OF EACH PHASE OF THE EXCAVATION, THE AREA WILL BE
STABILIZED WITH SOD.
RESPONSE: Agreed. As each individual lake is completed,
Applicant will grade, seed and mulch the
sideslopes and plant native vegetation in
accordance with permit requirements. Applicant
will not wait until the very end of the project to
finish the shorelines, but will engage in
continuous reclamation as the project progresses.
7 . THE SIDESLOPES OF THE EXCAVATIONS (BORROW PITS) WILL BE STABILIZED
AGAINST EROSION AND AVOID SLOPE MATERIAL SLIDING INTO THE PITS.
RESPONSE: Agreed. The sideslopes will be stabilized by
seeding, mulching and the planting of native
vegetation on the sideslopes. In addition,
Applicant has agreed to build sideslopes at a 4-
to-1 slope in accordance with the City Engineer' s
recommendation.
8 . MAINTENANCE OF THESE BORROW PITS SHOULD BE DETERMINED AND ASSIGNED
TO A SPECIFIC ENTITY.
RESPONSE: Agreed. See Item #19.
9 . ALL APPROPRIATE STATE AND FEDERAL PERMITS MUST BE ACQUIRED FROM
THE APPROPRIATE AGENCIES AND COPIES PROVIDED TO THE CITY PRIOR TO
COMMENCEMENT OF WORK.
RESPONSE: Agreed. The Florida Department of Environmental
Regulation has extensively reviewed all
engineering and drawings and has agreed to issue
permits on Tuesday, March 24, 1992. The St. Johns
River Water Management District has reviewed all
documentation and studies. No work will commence
until the developer has obtained the requisite
permits and the City has received copies. It is
specifically understood that approval is
conditioned upon St. Johns River Water Management
District and Florida Department of Environmental
Regulation permit issuance.
10. TRAFFIC CONTROL WILL HAVE TO BE PROVIDED DURING THE COURSE OF THE
EXCAVATION ACTIVITY.
RESPONSE: Agreed. There will be no hauling activities on
any public roads except for the crossings at
Seneca Boulevard and Winter Springs Boulevard and
within the Expressway R.O.W. at 434. Contractor
will provide necessary traffic control in
accordance with the direction of the City.
RE11:2<T0001ULTRIDG1,.18: _ 9 a_ 0 '� o L
.10318- -
11. NO CONSTRUCTION VEHICLES ARE TO TRAVEL THE CITY ROADS, SUCH AS
WINTER SPRINGS BOULEVARD, SENECA BOULEVARD EXCEPT FOR THE "ASPHALT
BRIDGE CROSSING" , VISTAWILLA DRIVE AND THE RAILROAD CROSSING
EXCEPT VISTAWILLA DRIVE EXTENSION WHICH REMAINS PRIVATELY OWNED.
RESPONSE: Agreed. Trucks hauling the fill materials will be
strictly "off-road" type. Except for the stated
crossings, these vehicles will not be on the City
roads.
12 . THE ROADS SUCH AS WINTER SPRINGS BOULEVARD, SENECA BOULEVARD AND
VISTAWILLA AT THE RAILROAD CROSSING ARE TO BE VIDEOED PRIOR TO
COMMENCEMENT OF WORK.
RESPONSE: Agreed. All roads will be video taped prior to
commencement of construction activity. If damage
should occur, it will be the responsibility of the
Applicant to repair.
13 . THE WINTER SPRINGS DEVELOPMENT J.V. AND/OR SULLIVAN MATERIALS INC.
IS TO T.V. THE SEWER LINES ON SENECA BOULEVARD AT THE "ASPHALT
BRIDGE CROSSING" BEFORE THE WORK BEGINS AND AFTER THE WORK IS
COMPLETED.
RESPONSE: Agreed. Sewer lines at Seneca will be video taped
prior to commencement of construction activity.
If damage should occur, it will be the
responsibility of the Applicant to repair.
14 . THE WATER LINES ON VISTAWILLA DRIVE EXTENSION ARE TO BE PRESSURE
TESTED AND BACTERIOLOGICALS TAKEN AFTER WORK IS COMPLETED.
RESPONSE: Agreed. Pressure testing and bacteriologicals
will be performed after work is completed.
15. THE STORM WATER PIPES ARE TO BE TELEVISED AND VISTAWILLA DRIVE
EXTENSION ON SENECA BOULEVARD BEFORE WORK BEGINS AND AFTER WORK IS
COMPLETED.
RESPONSE: Agreed.
16 . IF THE CONTRACT BETWEEN SULLIVAN MATERIALS INC. AND HUBBARD
CONSTRUCTION IS NOT CONSUMMATED FOR THE BORROW PIT EXCAVATIONS IN
TUSCAWILLA UNITS 14-C AND 15, THIS PERMIT IS TO BECOME NULL AND
VOID.
RESPONSE: Agreed. Applicant will not be allowed to commence
the project until a contract is executed with the
Expressway contractor (Hubbard) . All approvals of
the City shall be null and void if an agreement is
not reached with the Expressway contractor.
Q a 0 3 o
RE..:247000]IRTRIDCOI.18:
_,_I
B. ADDITIONAL RECOMMENDATIONS FROM CITY ENGINEER DATED MARCH 9, 1992
17 . HOURS OF OPERATION (TO BE DETERMINED) .
DAYS OF OPERATION (TO BE DETERMINED) .
RESPONSE: 7: 00 AM - 6: 00 PM, Monday through Saturday for
excavation and delivery of material. There will
be pumps operating 24 hours per day only during
the dewatering phase of the project. Any
exceptions to this schedule will require city
approval.
18 . ALL MATERIAL EXCAVATED MUST BE USED EXCLUSIVELY FOR THE EXPRESSWAY
CONSTRUCTION.
RESPONSE: Agreed. An established precondition of permit is
an agreement with the Expressway contractor for
delivery of materials exclusively for Expressway.
Some of the material may be used on-site as would
be the case in most developments.
19 . THERE IS TO BE POSTED A MAINTENANCE BOND FOR EACH LAKE (POND)
AFTER CONSTRUCTION IS COMPLETED FOR A PERIOD OF THREE YEARS FOR
20% OF THE TOTAL COST OF CONSTRUCTING THE LAKES (PONDS) .
RESPONSE: Parcel 15 - Winter Springs Development Joint
Venture intends to form a maintenance association
comprised of the commercial and residential sites
of Tract 15 in conjunction with the development of
this Tract. The association will collect
assessments and provide for continued maintenance
of the lakes as a condition of the development
order. Applicant will post a maintenance bond
with the City of Winter Springs in the amount of
$97,800. This amount is based on bids and actual
budgets for maintenance of similar lakes
calculated as follows:
Mowing $13,990/year x 3 years = $41,970
Planting Maintenance $18,610/year x 3 years =
$55,830
Parcel 14C - Applicant will post a maintenance
bond to the City of Winter Springs in an amount of
$33,150 to insure the proper maintenance of the
lakes for a period of five (5) years. The amount
is based on $6, 630 per year for shoreline mowing
and maintenance of shoreline vegetation. Should
the City or other entity desire to assume
maintenance responsibility, Applicant will pay
direct costs to the City or such entity.
5ao � d �
RE.i 247A0001ARTRJDG03.18_
910315.4 n
20. MOVE THE CHELSEA WOODS ENTRANCE TO THE INTERSECTION OF SENECA
BOULEVARD AND WINTER SPRINGS BOULEVARD.
RESPONSE: Agreed. Applicant will expend up to $10,000 to
construct a new entrance for Chelsea Woods at the
intersection of Seneca and Winter Springs
Boulevards. In addition to the budget amount for
construction, Applicant will provide an easement
at each corner to provide land for the entrance
and water and electric stub-outs to each corner.
The Chelsea Woods homeowners agree to perpetually
maintain the new entrance at their cost
immediately upon completion of the entrance.
C. ADDITIONAL ISSUES AND OUESTIONS
1. IS THERE A POTENTIAL THREAT OF BREACHING THE PROTECTIVE LAYER
(HAWTHORNE FORMATION) AND CAUSING ARTESIAN FLOW AND/OR GROUNDWATER
CONTAMINATION?
Michael D. Sims, in conjunction with FDER and the SJRWMD, has
examined this issue and determined that the Hawthorne
Formation is satisfactorily dense and in excess of 40 feet in
thickness in Tracts 14C and 15. This was determined by
extending one deeper boring at each site to the top of the
limestones which comprise the Floridan aquifer. The top of
the Floridan aquifer was encountered at depths of 82 and 96
feet at Tracts 14C and 15, respectively. It has been
concluded by the SJRWMD staff (based on the additional boring
data) that there is no concern with respect to any potential
penetration of the Hawthorn Formation. It is extremely
unlikely, but if a potential problem occurred, the procedure
used to cap artesian wells would be used to remedy the
situation.
2 . WILL THE DEWATERING CONDUCTED DURING THE EXCAVATION CREATE A
LOWERING OF THE WATER TABLE FOR ADJACENT PROPERTIES RESULTING IN
PROBLEMS WITH WELLS AND LANDSCAPING?
This issue has been specifically addressed and calculated in
the geotechnical study. Groundwater will be continuously
recirculated on site to above ground holding ponds where the
water will percolate back into the ground table. No water
will be discharged off-site. Monitoring wells will be placed
on the Casscells, property and other properties deemed
necessary and routine readings will be reported with a copy
sent to the City. If a temporary drop should occur, the
contractor will immediately construct a recharge berm to
correct the problem. Upon the completion of each excavation,
the dewatering ceases and the groundwater resumes its normal
seasonal level.
RE.::247:000 I ARRSDGO?.18
203:5.
3 . WILL THE FIVE (5) LOTS CREATED ON THE WEST SIDE OF SENECA
BOULEVARD CONFORM TO THE EXISTING CHELSEA WOODS SUBDIVISION?
Yes, Applicant agrees to adopt the Chelsea Woods current standards
which will apply to the five (5) lots. In addition, Applicant
agrees to establish haul routes from the lake on the north side of
Parcel SAC (to the Beltway) which will not negatively impact any
specimen trees. Applicant agrees in future development to keep
the wooded character of the portion of Parcel 14C that lies east
of Seneca Boulevard.
9 a 030,2
RE'\1:247\0001\RTRIDGOZ.15:
..0315 c 0