REQUEST:
The Community Development Department is advising the City Commission of the status of
various development proj ects within the City.
SYNOPSIS:
The following is a list of development projects that are: 1)proposed, 2) active, 3) inactive or
4) currently under construction within the City of Winter Springs. Items which are listed
below that have progressed since the last update are shown in bold type. Items which have
not and do not appear likely to progress further in the review cycle are periodically removed
from this agenda item.
A list of Economic Development activities Staff is currently undertaking has been provided
at the end of this report.
CONSIDERATIONS:
Proposed development projects
The following is a list of proposed development projects which have received some review
and comments from City Staff. These projects have not been formally submitted for review,
but are only in preliminary discussion stages. At such time as these projects are submitted
for formal review, they will be included on the list of active development projects. If there
has been no activity for an extended period of time, the project will be removed from this
agenda item.
Informational 200 PAGE 1 OF 7- May 11,2015
Lakeside Assisted Living Facilitv (ALF�- On January 29, 2015, staff inet with the potential
developer of a 132 bed ALF with a memory care component and 72 unit independent living
facility that is separate from the ALF. The property is located on the northwest corner of the
intersection of Sara Nicole Lane and SR 434, adjacent to the Laurel Oaks apartment
complex. THe property is zoned G1. The developer indicated to staff they would be
revising preliminary plans in the near future for a second meeting. The applicant's
representative indicated to Staff that a submittal of Final Engineering Plans and an
Aesthetic Review will be submitted in the near future.
Active Development Projects
The following is a list of active development projects that are currently in the development
review process. If there has been no activity for an extended period of time, the project will
be included in the list of inactive development projects and, if there is no further activity for
an extended period of time, the project will be removed from this agenda item.
Big Citv Catering - Staff is in receipt of a building permit application for a commercial
alteration for 1120 Orange Avenue. The building is 19,648 square feet in area and is
proposed to be a destination wedding and banquet facility. The commercial alteration will
allow a change of use for the building from a residential to commercial classification. The
property is zoned Town Center T3 (Suburban Zone) and the proposed use (reception
facilities/meeting rooms) is a permitted use. Staff has advised the applicant to contact the
neighboring properties to discuss their proposal. Staff has not yet reviewed any proposed
site plan or parking layout. The applicant has been instructed to send a letter explaining
the proposed project to the neighboring community. Staff is currently reviewing a site
plan which proposes a parking layout on the property.
Cross Seminole Trail- The Cross Seminole Trail has a missing link from Layer Elementary
to the west end of Old Sanford/Oviedo Road. Seminole County's planned connection will
continue from the current terminus at Layer northerly adj acent to SR 419. It will then turn
under the power easement in unimproved City right-of-way, cross the CSX railroad tracks
and then connect to the existing trail end in the poser easement. Additional property along
SR 419 and Layer Elementary is being donated by Bart Phillips to complete this section of
the trail corridor that is needed. The trail/railroad crossing agreement between Seminole
County and the CSX was finally approved on September 23, 2014 and funds for the
construction of the crossing have been remitted to CSX. The State can now certify that a
viable corridor exists which will allow the appraisals for the donated land to proceed. Once
approved by the Governor and Cabinet in the second quarter of 2015, the real estate
closings should occur in mid 2015. Seminole County has the trail construction plans
complete and they plan on proceeding with construction shortly after the land conveyances
are completed.
Dunkin Donuts - The building plans have been submitted and staff anticipates a pre-
construction meeting in the near future. The building permit is ready to be issued pending
the applicant providing a final proj ect cost valuation to the City. A pre-construction meeting
will be held in the near future. Construction of the project will commence soon thereafter. A
pre-construction meeting was held on March 26, 2015. It is staff s understanding the sale
of the property closed during the week of April 20, 2015. The DA is in the process of
being recorded. The building permit is ready for issuance and has not yet been
Informational 200 PAGE 2 OF 7- May 11,2015
obtained by the applicant.
ICI- Staff has recently processed an application for a rezoning to PUD (Planned Unit
Development), PUD Master Plan, and Development Agreement for the ICI property.
The property is located on the north side of SR 434, across from the Creeks Run
subdivision. The application details the construction of 360 apartments, 20 carriage
houses, and 10 acres of commercial along the SR 434 frontage of the property.
Pursuant to the Code of Ordinances, a community meeting is required to be held prior
to this item being presented to the City Commission for approval. A tentative date of
May 19, 2015 at 6pm has been set for the community meeting.
Magnolia Park— The construction of the Magnolia Park Amphitheater is tied to the Cross
Seminole Trail property conveyances timeline with real estate closings anticipated to be
completed by mid 2015. The City plans on purchasing from the State approximately 0.44
acres of trail right-of-way adjacent to the City property. This adjacent trail right-of-way is
needed because the amphitheater building encroaches into the State's trail right-of-way.
The encroachment will allow maximum utilization of this facility given the constraints of
the site. Staff presented updated cost estimates to the City Commission at their March
23, 2015 meeting and they were directed to identify potential cost saving opportunities
for the Commission to consider that could brings the project within budget.
Construction is anticipated to begin in early 2016 with completion in the summer of
2016. Meetings are ongoing with the architect to identify potential cost saving
revisions to the design.
Northern Oaks - Staff is in receipt of an application for annexation, rezoning, large-scale
future land use amendment and Preliminary Subdivision Plan (PSP) for a 18.67 acre parcel
of land located on the north side of SR 434, approximately 1,000-feet east of SR 417. The
applicant is proposing to rezone the property to R-1 (One-family dwelling district) and
designate of future land use of Low Density Residential in order to develop a 49 unit single-
family residential subdivision on the property. On January 7, 2015, the Planning & Zoning
Board considered the annexation, rezoning and future land use amendments on the property
and recommended approval. The annexation, rezoning, and future land use was presented to
the City Commission at the January 26, 2015 meeting and was approved for transmittal to
the Department of Economic Opportunity. This item will come back before the City
Commission in April 2015. The PSP will be presented at a later date. Staff continues to
work with the developer to formulate the make up of the proposed residential
subdivision.
Nursery Road Warehouse, Phase III- The applicant is requesting approval of a Final
Engineering Plan and Aesthetic Review for a 12,000 square warehouse building within the
Nursery Road warehouse complex, which received Final Engineering Plan approval in
2004. The subject property is approximately 6.6 acres in size and is zoned C-2 (General
Commercial). The warehouse building will be constructed over the existing retention pond
located on the rear (eastern) portion of the subject property. In addition, the applicant is
requesting Aesthetic Review approval for the proposed building. The City Commission
approved Aesthetic Review plans for Building three in 2004, for Building five in 2005 and
for Buildings one and four in 2006. The architectural elevations proposed for this building
are consistent with the previously approved architectural elevations. On March 4, 2015, the
Planning & Zoning Board unanimously approved the Final Engineering Plan and Aesthetic
Review for a recommendation of approval to the City Commission. These items, in addition
to an amendment to a Development Agreement which governs development of the property
Informational 200 PAGE 3 OF 7- May 11,2015
will be presented to the City Commission on March 23, 2015 for final approval. The City
Commission approved the Final Engineering Plan, Aesthetic Review and Modification
to the Development Agreement on March 23, 2015. Building plans are anticipated to
be submitted in the near future.
Plante Propertv (Tuskawilla Pointe� - The development site is located on the east side of
Tuscawilla Road, south of SR 434. The project consists of a mixture of 450 bungalow
and estate lots with a commercial component. The applicant is in the process of preparing a
right-of-way master plan to facilitate the vacation of any unused paper roadway easements
on the southern portion of the property. The developer has requested a 90-day extension of
the Annexation Agreement. The Agreement will expire on May 17, 2015 and the closing
on the subject property is currently set for May 21, 2015. This extension request will be
considered by the City Commission at their April 27, 2015 meeting. The City Commission
approved the extension request at the Apri127, 2015 meeting.
Pollack Shores Apartments - The project is located on the northeast corner of the
intersection of SR 434 and Michael Blake Boulevard in the Town Center. Staff is currently
working with the applicant on the final location and layout of the proj ect. The Concept Plan
and associated Development Agreement is scheduled to be presented to the City
Commission on February 9, 2015. On February 9, 2015 the City Commission approved the
Concept Plan and Developer's Agreement stipulating a maximum of 300 units. Final
Engineering Plans and Aesthetic Review drawings will be submitted in the near
future. Staff has a meeting with the developer on April 23, 2015 to consider the first
version of the final engineering plans. Staff inet with the developer on April 23, 2015 to
discuss issues related to the final design of the project. A revised site plan has been
submitted and is currently under review by staff. Final Engineering Plans and
Aesthetic Review drawings are anticipated to be submitted in the near future.
Southern Oaks (Weaver/Toledo properties� The project is located on the west side of
DeLeon Street, north of SR 434. Of the 95 total units, 52 are located in Winter Springs,
and 43 are located in Oviedo. Final Engineering Plans for the Winter Springs portion of the
development are currently under review. Staff will be setting a meeting date in the near
future to look at the initial submittals for the aesthetic review and development agreement.
The Aesthetic Review was submitted by the applicant. Final Engineering Plans, the
Aesthetic Review and Development Agreement are tentatively scheduled to be
presented to the City Commission for final approval in late June.
Town Center Phase I (�reviouslv referred to as JDC Calhoun I� — AT&T is currently in
process of a tenant buildout of the unit located at the intersection of SR 434 and Cliff Rose
Drive. Inspections of the proj ect are ongoing.
Town Center Phase II — The final Concept Plan for Pollack Shores is currently being
negotiated. On February 9, 2015 the City Commission approved the Concept Plan and
Developer's Agreement for Pollack Shores. (see update under Pollack Shores
Apartments).
Tuscanv Place- A developer has proposed constructing the remainder of the available
units in the Tuscany Place. Tuscany Place is located within the Tuscawilla PUD. The
proposal is for five townhome buildings containing 45 units. Staff has reviewed the
plat and has sent the review comments to the applicant. A resubmittal addressing staff
comments is anticipated soon.
Informational 200 PAGE 4 OF 7- May 11,2015
�nter Springs Retirement Residence - The proposal is for a 4-story, 139 suite Assisted
Living Facility (ALF) located on State Road 434 adjacent to the north side of the Cross
Seminole Trail bridge in the Town Center. On January 22, 2015, the developer held a
community meeting in the City Commission chambers to inform neighboring property
owners about the proposed project. Most of the property is within the corporate limits of
Winter Springs. There is a small portion of property that is part of the old railroad right-of-
way that must be annexed into the City. The developer has submitted an annexation,
rezoning, and future land use amendment application for the 1.8 acre parcel located along
the southern portion of the development site. On March 4, 2015, the Planning & Zoning
Board considered the annexation, rezoning, and future land use amendment for
recommendation of approval to the City Commission. First and Second readings of these
items will be considered by the City Commission on March 23, and April 13 2015.
Additionally, the applicant has submitted an application requesting four Special Exceptions
from the Town Center District Code. An informal Conceptual Plan has been submitted for
illustration purposes with the Special Exception requests. These requests are currently under
staff review and are anticipated to be presented to the Planning & Zoning Board and City
Commission in April 2015. On March 4, 2015, the Planning & Zoning Board unanimously
recommended approval of the annexation, rezoning, and future land use amendment to the
City Commission. First and Second readings of these items will be considered by the City
Commission on March 23, and April 13, 2015. First reading of the annexation, rezoning,
and future land use amendment was approved on March 23, 2015. Second reading of the
annexation, rezoning, and future land use amendment is scheduled for the April 13, 2015
City Commission meeting. The annexation, rezoning, and future land use amendment
were approved on April 13, 2015. Four Special Exception requests were presented to
the Planning & Zoning Board on May 6, 2015. These items are scheduled to be
presented to the City Commission on June 8, 2015.
Inactive Development Projects
The following is a list of inactive development projects that are currently in the
development review process. If there has been no activity for an extended period of time,
the project will be removed from this agenda item.
(None)
Projects currentlp under construction
The following is a list of projects that are currently under construction. At such time a
Certificate of Occupancy has been issued, the project will be removed from the agenda
item.
The RiZE —The project is located next to City Hall. The foundation has been
completed. Permits for all six of the apartment building segments have been issued and
construction continues.
Jesup's Landin�— This project will consist of 171 townhome in 30 buildings units on 17
acres of land located on the south side of Orange Avenue, behind Winter Springs High
School in the Town Center. To date, fifteen (15) buildings have been permitted,
constructed, or completed.
Seven Oaks— Upon completion, this project will consist of 138 single-family units
Informational 200 PAGE 5 OF 7- May 11,2015
located south of Florida Avenue and north of Shepard Road. To date, 63 units have been
permitted, constructed, or completed. A re-plat to address issues with several lots
adjacent to Boat Lake was approved by the City Commission at the January 26, 2015
meeting.
The Greens at Tuscawilla - Upon completion this project will consist of 60 units in 15
buildings located on the south side of Winter Springs Boulevard adjacent to the
Tuscawilla Country Club. To date, eleven (11) buildings have been permitted,
constructed, or completed. The developer has indicated they plan on submitting a re-
plat in the near future to address the shifting of lot lines on lots 9, 10, 11, and 12.
This will allow the finished floor elevation to be closer to the elevation of the lOth
tee box at the Tuscawilla Country Club. Currently, there is about a seven (7)
foot drop from lOth tee to the back of building.
�nding Hollow O�ce Buildings - This project consists of a total of nine (9) single story
office buildings located on the east and west sides of Winding Hollow
Boulevard. Construction of the buildings located on the east side Winding Hollow
Boulevard continues.
Economic Development Activities
(Please be aware that some descriptions will be abbreviated because of confidentiality
agreements)
. Staff continues its efforts to update the property information on eFlorida.
FISCAL IMPACT:
There is no fiscal impact associated with this agenda item.
COMMUNICATION EFFORTS:
This Agenda Item has been electronically forwarded to the Mayor and City Commission,
City Manager, City Attorney/Staff, and is available on the City's Website, LaserFiche, and
the City's Server. Additionally, portions of this Agenda Item are typed verbatim on the
respective Meeting Agenda which has also been electronically forwarded to the individuals
noted above, and which is also available on the City's Website, LaserFiche, and the City's
Server; has been sent to applicable City Staff, Media/Press Representatives who have
requested Agendas/Agenda Item information, Homeowner's Associations/Representatives
on file with the City, and all individuals who have requested such information. This
information has also been posted outside City Hall, posted inside City Hall with additional
copies available for the General Public, and posted at five (5) different locations around the
City. Furthermore, this information is also available to any individual requestors. City Staff
is always willing to discuss this Agenda Item or any Agenda Item with any interested
individuals.
RECOMMENDATION:
Staff requests the Citv Commission receive and review the information provided in this
Informational 200 PAGE 6 OF 7- May 11,2015
Agenda Item.