HomeMy WebLinkAbout2015 01 12 Consent 302 Starlight Baptist Church Site AcceptanceCOMMISSION AGENDA
ITEM 302
January 12, 2015
Regular Meeting
REQUEST:
Informational
Consent
X
Public Hearings
Regular
KS
City Manager
KL
Department
The Public Works Department requesting the City Commission: 1) validate the Staff
recommendation finding the Starlight Baptist Church sitework to be built in substantial
accordance with the Final Engineering plans, subject to satisfactory completion of the
remaining open project closeout list items; and 2) accept the public sidewalk for ownership
and maintenance.
SYNOPSIS:
Sitework for the Starlight Baptist Church Sanctuary Building is in progress and expected to
be complete before the end of January 2015. This agenda item provides the site acceptance
necessary before any certificates of occupancy can be issued by the building official, and
also accepts the public infrastructure for ownership and maintenance, subject to completion
of the remaining open project closeout items.
CONSIDERATIONS:
APPLICABLE CODE:
Section 9 -178. Required Improvements to be completed prior to building on lots;
exceptions.
(c) Where the building official has an authoritative method of assurance that the
improvements will be completed in accordance with approved plans, such as
withholding occupancy, the building official may issue building permits upon
advising the developer that all or partial occupancy will be restricted until
satisfactory completion of the improvements has be accomplished.
Consent 302 PAGE 1 OF 3 - January 12, 2015
(d) ... Certificates of occupancy will not be issued until all improvements are
accepted by the city commission.
The Starlight Baptist Church is located at the northwest corner of Hayes Road and East
Bahama Road. The final phase of the church's expansion program consists of
construction of a 565 -seat Sanctuary Building totaling 18,158 square feet in area.
Sitework for the project includes grading, drainage facilities, parking (paved and
unpaved), landscaping, and public sidewalks along the property's Hayes Road and
Bahama Road street frontages. The Final Engineering Plans were approved by the City
Commission on October 28, 2013. Project construction commenced in January 2014.
This agenda item is for the conditional acceptance of the site improvements. The sitework
is in progress and to date has been constructed in substantial compliance with the Final
Engineering plans approved by the City Commission. Exhibit A is the project closeout list
showing the open items as of December 24, 2014. All items on the project closeout
list must be complete subject to Staff approval prior to issuance of any certificates of
occupancy.
The Starlight Baptist Church sitework is expected to be complete by January 18, 2015, in
time for the church's scheduled opening in late January. Staff is recommending this
conditional site acceptance in order to allow the Starlight Baptist Church to open as soon as
possible after all required conditions are met. The public infrastructure being conveyed to
the City for ownership and maintenance consists of a public sidewalk along Hayes Road
and Bahama Road.
FISCAL IMPACT:
There is no fiscal impact associated with this site acceptance.
COMMUNICATION EFFORTS:
This Agenda Item has been electronically forwarded to the Mayor and City Commission,
City Manager, City Attorney /Staff, and is available on the City's Website, LaserFiche, and
the City's Server. Additionally, portions of this Agenda Item are typed verbatim on the
respective Meeting Agenda which has also been electronically forwarded to the individuals
noted above, and which is also available on the City's Website, LaserFiche, and the City's
Server; has been sent to applicable City Staff, Media/Press Representatives who have
requested Agendas /Agenda Item information, Homeowner's Associations/Representatives
on file with the City, and all individuals who have requested such information. This
information has also been posted outside City Hall, posted inside City Hall with additional
copies available for the General Public, and posted at five (5) different locations around the
City. Furthermore, this information is also available to any individual requestors. City Staff
is always willing to discuss this Agenda Item or any Agenda Item with any interested
individuals.
RECOMMENDATION:
Staff recommends that the City Commission: 1) validate the Staff recommendation finding
the Starlight Baptist Church sitework to be built in substantial accordance with the Final
Engineering plans, subject to satisfactory completion of the remaining open project closeout
Consent 302 PAGE 2 OF 3 - January 12, 2015
list items as noted on Exhibit A prior to issuance of any Certificates of Occupancy; and 2)
accept the public infrastructure for ownership and maintenance.
ATTACHMENTS:
1. Exhibit A - Starlight Baptist Church Project Closeout List (1 page)
Consent 302 PAGE 3 OF 3 - January 12, 2015
EXHIBIT A
City of Winter Springs
Project Closeout List for City Commission Final Site Acceptance
Starlight Baptist Church — Sanctuary Building
1. Completion of all Sitework Construction and Pass Final Site Inspection
2. Provide Engineer of Record's Certification Letter to the City, certifying that all sitework
has been completed in accordance with the approved plans
3. Complete set of record drawings accepted (PDF copy only, provided by engineer -of-
record, based on an as -built survey)
4. 2 -Year Maintenance Bond, Letter of Credit, or Cash Deposit Received (10% of the value
of the improvements in the City right -of -way that will be owned and maintained by the
City — sidewalk)
5. Bill of Sale Received for Infrastructure being turned over to the City for ownership and
maintenance (sidewalk)
6. Approvals from all City Departments
7. Letter from Engineer to SJRWMD Certifying Improvements ( SJRWMD standard
certification form)