HomeMy WebLinkAbout2014 12 08 Consent 301 Primrose School Site AcceptanceCOMMISSION AGENDA
ITEM 301
December 08, 2014
Regular Meeting
REQUEST:
Informational
Consent
X
Public Hearings
Regular
KS
City Manager
KL
Department
The Public Works Department requesting the City Commission: 1) validate the Staff
recommendation finding the Primrose School sitework to be built in substantial accordance
with the Final Engineering plans, subject to satisfactory completion of the remaining
open project closeout list items; and 2) accept the public infrastructure for ownership and
maintenance.
SYNOPSIS:
Sitework for the Primrose School is in progress and expected to be complete in early
January 2015. This agenda item provides the site acceptance necessary before any
certificates of occupancy can be issued by the building official, and also accepts the public
infrastructure for ownership and maintenance, subject to completion of the remaining open
project closeout items.
CONSIDERATIONS:
APPLICABLE CODE:
Section 9 -178. Required Improvements to be completed prior to building on lots;
exceptions.
(c) Where the building official has an authoritative method of assurance that the
improvements will be completed in accordance with approved plans, such as
withholding occupancy, the building official may issue building permits upon
advising the developer that all or partial occupancy will be restricted until
satisfactory completion of the improvements has be accomplished.
Consent 301 PAGE 1 OF 3 - December 08, 2014
(d) ... Certificates of occupancy will not be issued until all improvements are
accepted by the city commission.
The Primrose School is a 12,324 square foot daycare facility located on the southwest
corner of S.R. 434 and Heritage Park Street. The Final Engineering Plans were approved
by the City Commission on December 9, 2013. Project construction commenced in June
2014.
This agenda item is for the conditional acceptance of the site improvements. The sitework
is in progress and to date has been constructed in substantial compliance with the Final
Engineering plans approved by the City Commission. Exhibit A is the project closeout list
showing the open items as of December 1, 2014. All items on the project closeout list must
be complete subject to Staff approval prior to issuance of any certificates of occupancy.
The Primrose School sitework is expected to be complete by early January 2015, and the
building may be ready for a certificate of occupancy before the next City Commission
meeting on January 12, 2015. Staff is recommending this conditional site acceptance in
order to allow the Primrose School to open prior to January 12, 2015 if all required
conditions are met. The public infrastructure being conveyed to the City for ownership and
maintenance consists of a water main and related valves and appurtenances.
FISCAL IMPACT:
There is no fiscal impact associated with this site acceptance.
COMMUNICATION EFFORTS:
This Agenda Item has been electronically forwarded to the Mayor and City Commission,
City Manager, City Attorney /Staff, and is available on the City's Website, LaserFiche, and
the City's Server. Additionally, portions of this Agenda Item are typed verbatim on the
respective Meeting Agenda which has also been electronically forwarded to the individuals
noted above, and which is also available on the City's Website, LaserFiche, and the City's
Server; has been sent to applicable City Staff, Media/Press Representatives who have
requested Agendas /Agenda Item information, Homeowner's Associations/Representatives
on file with the City, and all individuals who have requested such information. This
information has also been posted outside City Hall, posted inside City Hall with additional
copies available for the General Public, and posted at five (5) different locations around the
City. Furthermore, this information is also available to any individual requestors. City Staff
is always willing to discuss this Agenda Item or any Agenda Item with any interested
individuals.
RECOMMENDATION:
Staff recommends that the City Commission: 1) validate the Staff recommendation finding
the Primrose School sitework to be built in substantial accordance with the Final
Engineering plans, subject to satisfactory completion of the remaining open project closeout
list items as noted on Exhibit A prior to issuance of any Certificates of Occupancy; and 2)
accept the public infrastructure for ownership and maintenance.
Consent 301 PAGE 2 OF 3 - December 08, 2014
ATTACHMENTS:
1. Exhibit A - Primrose School Project Closeout List (1 page)
Consent 301 PAGE 3 OF 3 - December 08, 2014
EXHIBIT A
City of Winter Springs
Project Closeout List for City Commission Final Site Acceptance
Primrose School
1. Completion of all Sitework Construction and Pass Final Site Inspection
2. Engineer of Record's Certification Letter to the City
3. Complete set of record drawings accepted (PDF copy)
4. FDEP Water Certification
5. 2 -Year Maintenance Bond, Letter of Credit, or Cash Deposit Received (10% of the value
of the improvements to be owned and maintained by the City)
6. Easements Dedicated and Recorded at Seminole County
7. Bill of Sale Received for Infrastructure being turned over to the City for ownership and
maintenance (water main)
8. Approvals from all City Departments
9. Letter from Engineer to SJRWMD Certifying Improvements ( SJRWMD standard
certification form)