REQUEST:
The Public Works Department requesting the City Commission: 1) validate the Staff
recommendation finding the Seven Oaks subdivision sitework to be built in substantial
accordance with the Final Engineering plans, subject to satisfactory completion of the
remaining open project closeout list items; and 2) accept the public infrastructure for
ownership and maintenance.
SYNOPSIS:
Sitework for Seven Oaks is substantially complete and has been conditionally approved by
the applicable City Departments. This agenda item provides the site acceptance necessary
before any certificates of occupancy can be issued by the building official for any non-
model units. This agenda item also accepts the public infrastructure for ownership and
maintenance.
CONSIDERATIONS:
APPLICABLE CODE:
Section 9-178. Required Improvements to be completed prior to building on lots;
exceptions.
(c) Where the building official has an authoritative method of assurance that the
improvements will be completed in accordance with approved plans, such as
withholding occupancy, the building official may issue building permits upon
advising the developer that all or partial occupancy will be restricted until satisfactory
completion of the improvements has be accomplished.
Consent 303 PAGE 1 OF 3 - May 12, 2014
(d) … Certificates of occupancy will not be issued until all improvements are
accepted by the city commission.
Seven Oaks is a 138-unit single family development by Meritage Homes on a 35-acre site
located on the south side of Shepard Road, north of Florida Avenue, and east of Boat
Lake.
The Final Engineering Plans were approved by the City Commission at the August 26,
2013 City Commission meeting. Sitework commenced in September 2013 and building
construction commenced in late 2013. A plat was approved by the City Commission at
the November 18, 2013 City Commission meeting and was recorded on December 6,
2013.
This agenda item is for the conditional acceptance of the site improvements. The sitework
has been constructed in substantial compliance with the Final Engineering plans approved
by the City Commission, except as noted on the attached project closeout list, Exhibit A.
All items on the project closeout list must be complete subject to Staff approval prior to
issuance of any certificates of occupancy for any non-model units.
The public infrastructure being conveyed to the City for ownership and
maintenance includes: roadways, curb, gutter, sidewalks, signage, striping, stormwater
improvements, water, sewer, and reclaimed water improvements.
FISCAL IMPACT:
There is no fiscal impact associated with this site acceptance.
COMMUNICATION EFFORTS:
This Agenda Item has been electronically forwarded to the Mayor and City Commission,
City Manager, City Attorney/Staff, and is available on the City’s Website, LaserFiche, and
the City’s Server. Additionally, portions of this Agenda Item are typed verbatim on the
respective Meeting Agenda which has also been electronically forwarded to the individuals
noted above, and which is also available on the City’s Website, LaserFiche, and the City’s
Server; has been sent to applicable City Staff, Media/Press Representatives who have
requested Agendas/Agenda Item information, Homeowner’s Associations/Representatives
on file with the City, and all individuals who have requested such information. This
information has also been posted outside City Hall, posted inside City Hall with additional
copies available for the General Public, and posted at five (5) different locations around the
City. Furthermore, this information is also available to any individual requestors. City Staff
is always willing to discuss this Agenda Item or any Agenda Item with any interested
individuals.
Consent 303 PAGE 2 OF 3 - May 12, 2014
RECOMMENDATION:
Staff recommends that the City Commission: 1) validate the Staff recommendation finding
the Seven Oaks sitework to be built in substantial accordance with the Final Engineering
plans, subject to satisfactory completion of the remaining open project closeout list items as
noted on Exhibit A prior to issuance of any Certificates of Occupancy; and 2) accept the
public infrastructure for ownership and maintenance.
ATTACHMENTS:
1. Exhibit A - Seven Oaks Project Closeout List (1 page)
Consent 303 PAGE 3 OF 3 - May 12, 2014
EXHIBITA
CityofWinterSprings
ProjectCloseoutListforCityCommissionFinalSiteAcceptance
SevenOaks
May2,2014
1.CompletionwithfinalinspectionofallSiteconstructionworkasshownontheapproved
FinalEngineeringplans,includinglandscapingandhardscaping
2.EngineerofRecord'sCertificationLettertotheCity
3.Completesetofrecorddrawingsaccepted(hardcopyanddigitalfile)
4.2YearMaintenanceBond,LetterofCredit,orCashDepositReceived(10%ofthevalue
oftheimprovementstobeownedandmaintainedbytheCity)
5.BillofSaleReceivedforInfrastructurebeingturnedovertotheCityforownershipand
maintenance
6.ApprovalsfromallCityDepartments
7.LetterfromEngineertoSJRWMDCertifyingImprovements(SJRWMDstandard
certificationform)