REQUEST:
The Public Works Department requesting the City Commission validate the Staff
recommendation finding the Amberly sitework to be built in substantial accordance with the
Final Engineering plans and to accept the public infrastructure for ownership and
maintenance, subject to satisfactory completion of the remaining open punchlist items and
recording of the final plat.
SYNOPSIS:
Sitework for Amberly is substantially complete and has been conditionally approved by the
applicable City Departments. This agenda item provides the site acceptance necessary
before any certificates of occupancy can be issued by the building official.
CONSIDERATIONS:
APPLICABLE CODE:
Section 9 -178. Required Improvements to be completed prior to building on lots;
exceptions.
(c) Where the building official has an authoritative method of assurance that the
improvements will be completed in accordance with approved plans, such as withholding
occupancy, the building official may issue building permits upon advising the developer
that all or partial occupancy will be restricted until satisfactory completion of the
improvements has be accomplished.
(d) ... Certificates of occupancy will not be issued until all improvements are accepted by
the city commission.
Consent 205 PAGE 1 OF 3 -January 28, 2013
Amberly is a new 36 unit single - family subdivision located on Dovera Drive, north of Red
Bug Lake Road, within the Oviedo Marketplace PUD. Final Engineering for Amberly was
approved by the City Commission on July 23, 2012. Sitework construction commenced in
August 2012 and construction of the first model units commenced in December 2012.
A final plat for the Amberly subdivision was approved by the City Commission at the
December 10, 2012 Commission meeting, subject to provision of the required bond, letter
of credit, or cash deposit, which has yet to be provided and thus the plat has not been
recorded.
This agenda item is for the conditional site acceptance of the site improvements.
The Amberly sitework has been constructed in substantial compliance with the Final
Engineering plans approved by the City Commission, except as noted on the attached
punchlist, Exhibit A. In addition, since the plat has not been recorded this site acceptance
must be subject to the recording of the final plat.
The engineer -of- record has provided a certification letter of approval and a complete set of
record drawings. KB Home has provided the required two -year maintenance bond for the
public infrastructure being turned over to the City for ownership and maintenance. This
public infrastructure includes:
• Roadway infrastructure (asphalt pavement, base, curb, gutter, etc.) for all public
streets
• Water distribution system including the mains, valves, and hydrants between the
points of connection and the point of service (meter) to each lot
• Public sidewalks, except those along the immediate frontage of residential units not
yet constructed
• Signage and striping in the right -of -way
• Sanitary sewer system
• Stormwater infrastructure in the right -of -way, pond, and drainage easements
One condition of the City Commission's approval of the Final Engineering plans for
Amberly was a requirement for the Dovera Community Development District (CDD) to
grant the City an easement for emergency access and maintenance of the existing
stormwater system on the CDD property. This easement has been recorded.
FISCAL IMPACT:
There is no fiscal impact associated with this site acceptance.
COMMUNICATION EFFORTS:
This Agenda Item has been electronically forwarded to the Mayor and City Commission,
City Manager, City Attorney /Staff, and is available on the City's Website, LaserFiche, and
the City's Server. Additionally, portions of this Agenda Item are typed verbatim on the
respective Meeting Agenda which has also been electronically forwarded to the individuals
noted above, and which is also available on the City's Website, LaserFiche, and the City's
Server; has been sent to applicable City Staff, Media/Press Representatives who have
requested Agendas /Agenda Item information, Homeowner's Associations /Representatives
on file with the City, and all individuals who have requested such information. This
information has also been posted outside City Hall, posted inside City Hall with additional
Consent 205 PAGE 2 OF 3 -January 28, 2013
copies available for the General Public, and posted at five (5) different locations around the
City. Furthermore, this information is also available to any individual requestors. City Staff
is always willing to discuss this Agenda Item or any Agenda Item with any interested
individuals.
RECOMMENDATION:
Staff recommends that the City Commission validate the Staff recommendation finding
the Amberly sitework to be built in substantial accordance with the approved Final
Engineering plans and accept the public infrastructure for ownership and maintenance,
subject to: 1) completion of all open punchlist items as noted on Exhibit A prior to issuance
of any Certificates of Occupancy; and 2) recording of the final plat.
ATTACHMENTS:
1. Exhibit A - Amberly Site Punchlist (1 page)
Consent 205 PAGE 3 OF 3 -January 28, 2013
EXHIBIT A
Amberly Punchlist for Site Acceptance
January 18, 2013
1. Complete FDEP Sewer Certification (in progress)
2. Complete FDEP Water Certification (in progress)
3. Install all required pond and common area landscaping and pass the final
irrigation inspection
4. Install common area hardscaping (benches, etc.)
5. Restore and sod the disturbed area around the irrigation well
6. Submit test results for asphalt cores and repair surface where cores were
taken
7. Record the final plat before the site can be considered as accepted by the
City