HomeMy WebLinkAbout2012 11 19 Consent 205 Water Storage Tank RepairCOMMISSION AGENDA
ITEM 205
November 19, 2012
Special Meeting
Informational
Consent
X
Public Hearings
Regular
KS
KL
City Manager Department
REQUEST:
Utility Department Requesting Approval to Authorize Crom Engineering & Construction
Services to make repairs to the 0.5 million gallon water storage tank at Water Treatment
Plant (WTP) #2.
SYNOPSIS:
The purpose of this agenda item is to request approval to authorize scheduled repairs in the
amount of $78,050.00 to Crom Engineering & Construction Services of Gainesville, Florida
for the 0.5 million gallon (MG) water storage tank located at WTP #2 on Sheoah Boulevard.
CONSIDERATIONS:
This project is needed to perform major scheduled maintenance to the potable water storage
tank at WTP #2 located at 700 Sheoah Boulevard. Staff had an extensive inspection
performed on all four water storage tanks in the City by Crom Engineering and
Construction Services, Inc (CECS) in 2007. Repairs have been previously completed
on three of the tanks. This scope of work implements the recommendations of the
inspection report and completes the fourth and final tank.
This storage tank was constructed in 1972 by Crom Corporation and has had no interior
structural work done on it since then. There are only two companies in Florida that
construct potable pre- stressed concrete tanks; Crom Corporation out of Gainesville and
Precon Corporation of Newberry. CECS is the repair division of Crom Corporation.
CECS satisfactorily completed similar repairs to the 1.0 MG tank at WTP #1 on Northern
Consent 205 PAGE 1 OF 2 - November 19, 2012
Way in March of 2009 at a cost of $114,900. Precon has refurbished the 0.5 million gallon
tank at WTP #3 in 2011 at a cost of $66,630, and in 2012 refurbished the 0.5 MG tank at
WTP #1 at a cost of $69,000. Staff solicited proposals from both companies to implement
all recommendations contained in the inspection report including a structural certification.
The scope of work includes; replacement of the access manhole, repairs to any exposed
reinforcing wire, sandblasting of the dome and interior walls, recoating with epoxy mortar
and epoxy coating, exterior painting, and repairs to all tank accessories. CECS's bid for
this work is $78,050 and Precon's bid is $77,300. CECS's paint job has been better than
Precon's and that is why staff is recommending CECS for this project.
The work will be scheduled in the December /January time frame which typically is the
lowest water consumption period of the year. The scope will take approximately 60 to 90
days to complete.
FISCAL IMPACT:
Funds are budgeted in the Utility Department line code 3600 -62100 at $105,000 for this
project.
COMMUNICATION EFFORTS:
This Agenda Item has been electronically forwarded to the Mayor and City Commission,
City Manager, City Attorney /Staff, and is available on the City's Website, LaserFiche, and
the City's Server. Additionally, portions of this Agenda Item are typed verbatim on the
respective Meeting Agenda which has also been electronically forwarded to the individuals
noted above, and which is also available on the City's Website, LaserFiche, and the City's
Server; has been sent to applicable City Staff, eAlert /eCitizen Recipients, Media/Press
Representatives who have requested Agendas /Agenda Item information, Homeowner's
Associations/Representatives on file with the City, and all individuals who have requested
such information. This information has also been posted outside City Hall, posted inside
City Hall with additional copies available for the General Public, and posted at five (5)
different locations around the City. Furthermore, this information is also available to any
individual requestors. City Staff is always willing to discuss this Agenda Item or any
Agenda Item with any interested individuals.
RECOMMENDATION:
It is recommended that authorization be granted to award the WTP #2 0.5 MG storage tank
repairs to CECS of Gainesville for $78,050.00 plus a 10% contingency payable from Utility
line code 3600- 62100.
ATTACHMENTS:
A. Crom Engineering and Construction Services (CECS) Proposal
B. Precon Corporation Proposal
Consent 205 PAGE 2 OF 2 - November 19, 2012
EEES
October 12, 2012
Revised October 12, 2012
PROPOSAL 08 -024A
REPAIRS BASED ON INSPECTION
0.5 -MG PRESTRESSED CONCRETE TANK
SHEOAH BLVD. WATER PLANT
WINTER SPRINGS, FL
Crom Engineering and Construction Services (CFCs) proposes to provide labor and
material for the repair of the prestressed concrete tank in accordance with all applicable
codes and standards including OSHA, AWWA, ACI and standard prestressed concrete tank
design.
1. DRAWINGS, SPECIFICATIONS, AND OTHER REQUIRED DATA
Prior to starting work, Crom Engineering and Construction Services will gather all
data required for submittal purposes for the repair to the afore mentioned storage
tank including any available computations, detailed drawings, and specifications.
2. COMMENCEMENT AND COMPLETION
Upon your execution of this proposal, we will be prepared to start work three weeks
after approval of our submittal information; and will undertake to furnish sufficient
labor, materials, and equipment to complete the work within approximately four
weeks working time thereafter.
In the event that we cannot start the job by April 1, 2013 because of delays of any
nature that are caused by the owner or other contractor employed by him or other
circumstances over which we have no control, then the contract price may be re-
negotiated to reflect any increased costs.
3. INSURANCE
We hereby certify that we have Workers' Compensation Insurance, and that we carry
adequate Liability and Property Damage Insurance as well as Builders' Risk
Insurance. A certificate will be furnished by our insuring agency upon request.
CROM ENGINEERING B CONSTRUCTION SERVICES
6801 SW Archer Road • Gainesvi I I e, F I orida 32008.352 -548 -3349 • Fax: 352 -548 -3449
i i i io 17 cif The 1--4D177 o r o 1;0 do r7
08 -024 A - 0.5 -MG Ground Storage Tank October 12, 2012
Sheoah Blvd Water Plant Page 2
4. SERVICES TO BE FURNISHED BY CROM ENGINEERING AND CONSTRUCTION
SERVICES.
We propose to furnish all supervision, labor, material, equipment, scaffold and forms
required to complete the work, except as noted in Paragraph 5. The services to be
furnished by Crom Engineering and Construction Services are specifically:
Repairs Based on Inspection Report
a. Replace the existing aluminum alloy manhole cover with stainless steel cover
and hardware.
b. Remove delaminating coating at manhole frame and recoat with AquataPoxy
A -6 or equal.
c. Repair spalling concrete with exposed corroding steel at the dome hatch by
removing all loose, deteriorated concrete material, sandblasting the corroded
steel and substrate, and patching with a polymer modified cementitious repair
material in conjunction with a bonding epoxy.
d. Replace corroded brackets at interior ladder connection to dome with stainless
steel brackets and hardware. Install TS Rail on interior and exterior ladder.
e. Replace the insect barrier on the underside of the fiberglass dome hatch door.
f. Replace overflow screens.
g.
Recoat underside of dome, interior tank walls and baffle wall.
(1) Sandblast and pressure wash all interior surfaces to remove
delaminating coating.
(2) Remove any exposed mesh and patch as required.
(3) Remove all used abrasive and properly dispose.
(4) Recoat the prepared surfaces with two coats of Tnemec N140 Epoxy.
h. Sandblast and recoat interior piping with two coats Tnemec N140 Epoxy.
i. Pressure wash and paint the tank exterior with two coats of Tnemec Series 6
(two -tone, highlight dome band).
J
Rebuild Liquid Level Indicator assembly
08 -024 A - 0.5 -MG Ground Storage Tank October 12, 2012
Sheoah Blvd Water Plant Page 3
This work shall be performed on the following tank:
• 0.5 -MG Ground Storage Tank — Sheoah Blvd. Water Plant
70' -0" ID x 17' -3" SWD
(Crom Job No. 7222)
5. MATERIALS AND SERVICES FURNISHED BY OTHERS
It is understood that the following services shall be provided by others without
expense to Crom Engineering and Construction Services.
a. Adequate access to the tank site including open storage space for our
vehicles, equipment and materials, conveniently located near the tank to be
repaired.
b. A continuous supply of potable water under minimum pressure for the use of
the CECS crew within 100 feet of the tank site.
c. A continuous supply of electricity during the period of work: one 30 -AMP, 110 -
volt service for the operation of our power tools and accessories, located not
more than 100 feet from the tank. Please be sure that all circuit breakers are
ground -fault protected.
d. Any permit or other governmental fees as may be required for the work.
e. Drainage and disposal of the tank's contents.
f. Disinfection and refilling of the tank's contents.
g. Cleaning the interior of the tank and accessories.
h. Complete lock out and tag out of the subject tank prior to personnel entering
the tank. Owner will be required to provide all materials for this process.
Crom Engineering and Construction Services, Inc. will review the procedures
before entering the tank.
08 -024 A - 0.5 -MG Ground Storage Tank October 12, 2012
Sheoah Blvd Water Plant Page 4
6. BACK CHARGES AND CLAIMS FOR EXTRAS
No claim for extra services rendered or materials furnished will be valid by either
party unless written notice thereof is given during the first ten days of the calendar
month following that in which the claim originated. Crom Engineering and
Construction Services' claims for extras shall carry 30% for overhead and 10% for
profit.
7. DELAYS
It is agreed that we shall be permitted to prosecute our work without interruption. If
delayed at any time for a period of 24 hours or more by an act or neglect of the
owner, his representative, or other contractor employed by him, or by reason of any
changes ordered in the work, we shall be reimbursed for our actual additional
expense caused by such delay, including loss of use of our equipment, plus 30% for
overhead.
8. LABOR
This proposal is predicated on open -shop labor conditions, using our own personnel.
If we are required to employ persons of an affiliation desirable to the owner or other
contractor employed by him or the general contractor thereby resulting in increased
costs to us, the contract price shall be adjusted accordingly. Such requirement shall
not provide that Crom Engineering and Construction Services sign a contract with
any labor organization. In the event of a labor stoppage, we shall not be in default or
be deemed responsible for delay of the progress of this contract or damage to the
owner or the contractor so long as Crom Engineering and Construction Services has
sufficient qualified employees available to perform the work.
9. QUOTATION
We are prepared to carry out this work in accordance with the foregoing for the lump
sum price of:
Repairs Based on Inspection and additions per Owners request (Scope of
work items a-j): $78,050.00
08 -024 A - 0.5 -MG Ground Storage Tank October 12, 2012
Sheoah Blvd Water Plant Page 5
Final payment, including any retention, shall be made within 30 days from the time
work is completed or the billing is received, and is to be received by us in our
accounting office at 250 SW 36th Terrace, Gainesville, Florida 32607. Final payment
shall not be held up because of delays in testing. Owner shall pay CECS interest at
12% per annum on any overdue amounts.
10. CONSULTATION AND LIMITATIONS
If the Owner wishes to have CECS to perform any additional repairs or remediation of
the tank or accessories, it shall authorize such work in writing and pay CECS its
standard charges for such work.
It is agreed that CECS shall not be responsible for any consequential, special or
delay damages.
It is agreed that the venue for any litigation under this Agreement shall be in Alachua
County, Florida.
If CECS engages an attorney for the collection of the amounts due from the Owner,
the Owner shall pay CECS its reasonable attorney's fees and costs through any
appeal.
11. GUARANTEE
CECS will guarantee its workmanship and materials on its work covered in this
Proposal for a period of one year after completion of its work. Prior to leaving the
location, CECS personnel will perform a walk through with the responsible party
overseeing our work for the Owner or Contractor. In case any defects in CECS'
workmanship or materials appear within the one -year period after completion of
CECS' work, CECS shall promptly make repairs at its own expense upon written
notice by the Owner or Contractor that such defects have been found. CECS'
guaranty is limited to defects in CECS' workmanship and materials and CECS is not
responsible for ordinary wear and tear or for damage resulting from negligent or
inappropriate use.
08 -024 A - 0.5 -MG Ground Storage Tank October 12, 2012
Sheoah Blvd Water Plant Page 6
12. ACCEPTANCE
This proposal is offered for your acceptance within 45 days from the proposal date.
We reserve the right after that period to amend our bid to reflect our changing
construction schedules and materials and labor rate changes. The return to this
company of a copy of this proposal with your acceptance endorsed thereon within the
time aforesaid will constitute a contract between us. This proposal shall be made a
part of any subcontract agreement or purchase order.
Sincerely,
CROM ENGINEERING & CONSTRUCTION SERVICES
_Ns/
Clint Jenkins Jeff D. Malpass, P.E.
Project Manager
/asg
ACCEPTED:
PRINT:
TITLE:
DATE:
President
PRECON
Prestressed Concrete Tanks
Mr. Steve Baggs
City of Winter Springs
1126 East State Road 434
Winter Springs, FL 32708
(407) 327 -8992
sbaggs@winterspringsfl.org
PROPOSAL
Subject: City of Winter Springs, FL
0.5 MG Ground Storage Tank
Sheoah Boulevard Water Plant
Description:
PRECON CORPORATION
115 S.W. 140th Terrace
Newberry, Florida 32669
Fax 3324199
(352) 332 -1200
September 25, 2012
1. MATERIALS AND SERVICES To BE FURNISHED BY PRECON CORPORATION
Precon proposes to furnish all labor, material, equipment, scaffolding, forms and
supervision required to complete the repairs in accord with the request of the City of
Winter Springs and Precon Corporation's standard prestressed concrete tank design.
The services to be furnished by Precon Corporation are specifically:
a. Sandblast the dome and top 3' of walls
b. Paint the underside of the dome with epoxy paint
e. Sandblast and paint interior inlet pipe
. Repair and seal dome hatch
e. Replace overflow screen
f. Replace aluminum manhole cover with stainless steel cover and recoat
manhole frame with epoxy.
Rescreen existing aerator
Restring LLI with stainless steel cable
g.
h.
Additional items
a. Add 1/8" mortar to the underside of the donne surface
b. Paint exterior of tank in 2 tone paint job with 2 coats
c. Sandblast and paint remaining 14.33' of interior walls
Price: $ 47,800.00
Price: $ 6,2 0.00
Price: $ 8,400.00
Price: $ 14,900.00
2. SERVICES FURNISHED Y OTHERS
a. Water for construction
b. Electricity for Construction
3. COMMENCEIVIENT AND COMPLETION
We are p reared to furnish sufficient labor, materials and equipment to complete the
work within approximately 5 weeks after a mutually agreeable start date.
4. SHOP DRAWINGS A lC DESIGN DATA
City of Winter Springs -2- September 26, 2012
.5 MG Ground Storage Tank
Sheoah Boulevard Water Plant
We will submit all data required for approval prior to starting work.
6. BOND
The cost of a payment- performance - maintenance bond, issued for a one -year period, is
to be added to the bid price if required. The price for this bond is $12OO per 1,000.00.
If utilizing sub - guard, any bonds required will be added to the tank price.
7. SAFETY
This proposal is based on performing the work in accordance with Precon Corporation's
Safety Program, which meets or exceeds CFR 1926 OSHA Standards. If any
additional safety requirements are placed upon us, such as additional site training or
safety equipment, the cost for such additional requirements plus overhead shall be
reimbursed to us.
8. INSURANCE
Precon will furnish an insurance certificate showing coverage of liability, property and
worker's compensation insurance upon request. Our insurance will be carried in accord
with the general condition requirements. An additional amount will be added to our
subcontract price if there are any extra requirements. Builder's Risk insurance will be
carried in accord with general conditions requirements.
9. ARBITRATION
Any dispute or claim between us shall be settled by arbitration in accord with the
American Arbitration Association rules relating to the construction industry. The
arbitrator's decision may be entered in any court having jurisdiction.
10. ACCEPTANCE
This proposal is offered for your acceptance within days. This proposal is based on
the conditions of the AlA Standard Form of Agreement Between Contractor and
Subcontractor, and it shall be made part of any subcontract.
Accepted:
Offered: Precon Corporation
By: By:
Adrian C. Moore, BA
Title: _ Title: Assistant Project Manager
Date: