REQUEST:
The Public Works Department Requesting the City Commission validate the Staff
recommendation finding the Winter Springs Village Phase 1 sitework to be built
in substantial accordance with the Final Engineering plans and to accept the public
infrastructure for ownership and maintenance, subject to satisfactory completion of
the remaining open punchlist items
SYNOPSIS:
Sitework for Winter Springs Village Phase 1 is substantially complete and has been
conditionally approved by the applicable City Departments. This agenda item provides the
site acceptance necessary before any certificates of occupancy can be issued by the building
official.
CONSIDERATIONS:
APPLICABLE CODE:
Section 9-178. Required Improvements to be completed prior to building on lots;
exceptions.
(c) Where the building official has an authoritative method of assurance that the
improvements will be completed in accordance with approved plans, such as withholding
occupancy, the building official may issue building permits upon advising the developer
that all or partial occupancy will be restricted until satisfactory completion of the
improvements has be accomplished.
(d) … Certificates of occupancy will not be issued until all improvements are accepted by
Consent 204 PAGE 1 OF 3 - March 26, 2012
the city commission.
Winter Springs Village is a new 202 single-family unit subdivision by Meritage Homes
located on a 40-acre site in the Winter Springs Town Center. The site is located along the
east side of Tuskawilla Road, south of St. Johns Landing.
Final Engineering and a Developer's Agreement for Winter Springs Village were
conditionally approved by the City Commission on March 28, 2011. The project consists
of two phases, with 99 of the 202 units in Phase 1 and the remainder in Phase 2. A plat for
Phase 1 was approved by the City Commission on September 12, 2011 and recorded on
October 4, 2011.
This agenda item is for the conditional site acceptance of the Phase 1 site improvements.
The Winter Springs Village Phase 1 sitework has been constructed in substantial
accordance with the Final Engineering plans approved by the City Commission on March
28, 2011, except as noted on the attached punchlist, Exhibit A. In addition, All
Development Agreement requirements applicable to the sitework have been completed.
Meritage Homes has provided the required two-year maintenance letter of credit for the
public infrastructure being turned over to the City for ownership and maintenance, in the
amount of $197,623.31. This public infrastructure includes:
a.Roadway infrastructure (asphalt pavement, base, curb, gutter, etc.) for all public roads
including the segment of Michael Blake Boulevard from Tuskawilla Road to the
Cross-Seminole Trail
b.The onsite water distribution system including the mains, valves, and hydrants
between the points of connection and the point of service (meters) at each lot.
c.Public sidewalks along all public right-of-ways and public sidewalk easements
d.Signage and striping in the right-of-way
e.Sanitary sewer system including the lift station and force main from the lift station to
the point of connection near S.R. 434
f.Stormwater infrastructure in the right-of-way, at the three retention ponds, and the
drainage easement containing the pond outfall piping and structures
g.Irrigation main lines and related appurtenances within the right-of-way
The Developer's Agreement includes provisions for City reimbursement to Meritage Homes
of certain eligible infrastructure expenses after completion and acceptance by the City. This
agenda item is not requesting City Commission approval for any reimbursements. This
agenda item is only for the approval of the infrastructure. A future agenda item requesting
City Commission authorization for the reimbursements will be submitted after Meritage
Homes has provided the necessary documentation supporting the requested reimbursements
in accordance with the Developer's Agreement.
FISCAL IMPACT:
There is no fiscal impact associated with this site acceptance.
COMMUNICATION EFFORTS:
This Agenda Item has been electronically forwarded to the Mayor and City Commission,
City Manager, City Attorney/Staff, and is available on the City’s Website, LaserFiche, and
the City’s Server. Additionally, portions of this Agenda Item are typed verbatim on the
Consent 204 PAGE 2 OF 3 - March 26, 2012
respective Meeting Agenda which has also been electronically forwarded to the individuals
noted above, and which is also available on the City’s Website, LaserFiche, and the City’s
Server; has been sent to applicable City Staff, Media/Press Representatives who have
requested Agendas/Agenda Item information, Homeowner’s Associations/Representatives
on file with the City, and all individuals who have requested such information. This
information has also been posted outside City Hall, posted inside City Hall with additional
copies available for the General Public, and posted at five (5) different locations around the
City. Furthermore, this information is also available to any individual requestors. City Staff
is always willing to discuss this Agenda Item or any Agenda Item with any interested
individuals.
RECOMMENDATION:
Staff recommends that the City Commission validate the Staff recommendation finding the
Winter Springs Village Phase 1 sitework to be built in substantial accordance with the
approved Final Engineering plans, subject to completion of all open punchlist items as
noted on Exhibit A prior to issuance of any Certificates of Occupancy, and to accept the
public infrastructure for ownership and maintenance.
ATTACHMENTS:
1. Exhibit A - Winter Springs Village Site Punchlist (1 page)
Consent 204 PAGE 3 OF 3 - March 26, 2012
I 95
( Rik
EXHIBIT A
Winter Springs Village Punchlist
March 16, 2012
1. Complete the installation of all common area landscaping that will not be impacted by future
home construction, including the entire Tuskawilla Road frontage and the green courtyard space
in front of lots 146 -150 and 129 -132. This must be completed and accepted prior to any
Certificate's of Occupancy.
2. Completion and restoration of ponds 1, 2, and 3:
a. Repair washouts and erosion
b. Replace dead sod
c. Regrade side slopes as needed to a uniform 5:1 or 2:1
d. Sod all bare areas (except 2:1 side slope area below the breakpoint elevation)
e. Install littoral zone plantings and other landscaping per the plans
f. Fill and sod over the exposed portions of the outfall pipe (Pond 2)
g. Install PVC orifices in accordance with the typical detail on sheet 22
3. Install overlook at Pond 1.
4. Repair areas of asphalt unraveling at various locations; the City reserves the option within the
two -year maintenance period to require any unacceptable asphalt areas to be removed and
replaced.
5. Convert the temporary fire hydrant with the bag on it on Tuskawilla Road to a permanent
hydrant.
6. Install a permanent (decorative) stop sign at the trail crossing on MBB southbound (it is
understood that this is on order and the sign will be installed upon arrival).
7. Complete the backfilling and installation of erosion protection at the Pond 1/3 discharge bubble -
up structure.
8. Install streetlights along the public streets in Phase 1. It is understood that this work is
underway by Progress Energy.