HomeMy WebLinkAboutBellomo-Herbert And Company, Inc. Change Order No. 1 Shepard Road Streetscape Contract Documents 2011 03 28 CHANGE ORDER NO. 1 TO TASK ASSIGNMENT NO. 3 SHEPARD ROAD STREETSCAPE CONTRACT DOCUMENTS WINTER SPRINGS, FLORIDA Date: March 18, 2011 I. PURPOSE This is an attachment to Task Assignment 3 between the City of Winter Springs, Florida (Client) and the fimt of Bellomo-Herbert and Company, Inc. (Consultant) and made a part thereof. The purpose of this Change Order is to specify the required additional services of the Consultant. II. GENERAL SCOPE OF WORK The initial scope of this Task Assignment induded providing preliminary and final engineering for the widening of Shepard Road from east of US 17/92 to Wildwood Drive in WinterSprings, Florida. The project indudes modfication of the drainage system from a mixed system of closed and open drainage to a closed system to accommodate pedest�ian facilities. The initial scope of services included the work necessary to acquire a Letter of Exemption from the St. Johns River Water Management District (SJRWMD), After an initial meeting with SJRWMD, it was determined that a Letter of Exemption is not achievable and therefore additional work is necessary to obtain a permit from SJRWMD including permit app[ication fees, permit application and fhe drainage design necessary to achieve a permit. It is anficipated that the drainage design will be comprised of both the analysis necessary to demonstrate to the SJRWMD that post pollutant loading are equal to or better than the existing conditions including phosphorous modeling and the design of BMPs or swales. Further, fhe initiaf scope anticipated coordination with the FDOT for connections to the US 17 -92 right-of-way. However during the preliminary engineering phase it was determined that the Florida Department of Transportation (FDO� has an ongoing project that is directly related to the drainage for Sheppard Road and that additional coordination for drainage wiff be required beyond whatwas anticipated in the initial scope. The following scope of services is intended to describe the necessary tasks associated with the additional goals of the project. A. Final Desiqn and Contract Documents Prepare the addi�onal plan sheets and drainage details to consider the additional drainage elements including: • Summary of Roadway and Drainage Pay Items and General Notes • Swale Cross Section Sheets • Drainage Plan Sheets • Miscellaneous Drainage Details Prepare an Engineer's Estimate of Construction Costs at the 90°r6 and 100°� completion stages. One additional field review is anticipated with FDOT and SJRWMD. Plan Sheets will be submitted at the 90% and 100% completion stages for review bythe Client. Final Project Deliverabfes will be as follows: • 11 "x 17" Plan Sheets • 8'/z"x11" Technical Specifications • Engineer's Estimate of Construction Cost. • Computer files and CADD files in digital format. Bepomo-Herbert 8 Co Inc Sheoard Road — Chanae Order No 1 p��g.3 � B. Drainaqe Analysis The Consuftant wil( provide the necessary drainage analysis including swale design calculations, pre-post pollutant loading analysis and overall drainage calculations necessary to support the SJRWMD permit application. C. Project PermittinQ This task anticipates that this project will require a Standard Environmental Resource Stormwater Permit from SJRWMD. The Consuitant will perform the necessary drainage analysis to obtain the Stormwater Permit for the Shepard Road project. Upon substantial completion of the Plans, the Consultant will prepare the perrnit application package for submission to the SJRWMD. Permit Applica�on fees will be paid for by the Client. D. Suroevin4 Not included. If a swale system on the existing FDOT pond site property is the final design for thls project, additional survey will be required and provided by the Client. This survey is anticipated to be obtained from the FDOT survey completed for the ongoing US 17-92 project. This survey will include topographic survey and right-of-way identificafion incfuding all significant features on the FDOT parcel located near the eastem terminus of the project near Wildwood Drive. E. Environmental Services This supplemental agreement anticipates that any off-site drainage improvements such as the design of a swafe wil) occur an the FDOT Parcel located near the eastern terrninus flf the project and that the FDOT will provide the environmental evaluation for this property. The Consultant will coordinate with the FDOT for the use of their environmental analysis within the Shepard Road permit. Ilf. SCHEDULES AND TINIE CONSTRAINTS The time required to comp(ete the LANDSCAPE ARCHITECT'S services under fhis Change Order shall extend the length of the afarementioned Professional Services Agreement by 60 days. IV. COMPENSAT[ON Total compensation for all services, materials, supplies and any other requirements necessary to complete the Change Orderwork as described herein shall be the lurnp sum of $10,666.00, broken out as follows: • Drainage Analysis $ 3,681.00 • Drainage Plans $ 3,146.00 • Permitting � 3,839.00 TOTAL ADDfTtONAL FEE $10,fi66.00 Bellomo-Herbert & Co.. Inc. Sheoard Road — Chanae Order No. 1 03-18-11 Work Order Task Assignment No. 3 City of Winter Springs, Fla Shepard Road Streetscape Project Master Agreement Contract Date: October 21, 2009 Consultant: Bellomo- Herbert & Company, Inc. 833 Highland Avenue, Suite 201 Orlando, FL 32803 (407) 422 -4845 frank @bellomo - herbert.com Date: March 18, 2011 Attachment(s) to this Work Order: 1. Change Order No.1 Fixed Fee Basis $10,666 Not To Exceed (Ten Thousand Six Hundred and Sixty -Six Dollars) Time For Completion: The services to be provided by the CONSULTANT shall commence upon execution of this WORK ORDER by the parties and shall be completed within the time frame of sixty (60) days of the effective date of this WORK ORDER. Failure to meet the stated completion time requirement may be grounds for termination for default. IN WITNESS WHEREOF, the parties hereto have made and executed the WORK ORDER on the respective dates under each signature: the CITY by signature of the City Manager, and the CONSULTANT by and through its duly authorized corporate officer having the full and complete authority to execute the same. ATTEST: COM TA q‘... .0 • FRANK BELLOMO, PRESIDENT Date: 4 - . t . ATTE T: CITY OF W TER$ INGS Aar ?Z- KEVIN L. SMITH, CITY MANAGER Date: March 30, 2011