HomeMy WebLinkAbout2010 07 12 Informational 100 Status of Current Planning Projects COMMISSION AGENDA
CONSENT
INFORMATIONAL X
ITEM 100 PUBLIC HEARING
REGULAR
July 12, 2010
Meeting
MGR. I /DEPT I_J
pot. uthorization /
REQUEST: Community Development Department is advising the City Commission of the
status of various current planning projects.
SYNOPSIS: The city Commission has been asked to be kept informed of all projects at all
stages of development in the City. This agenda item is an update to the Commission on the
status of current planning projects and any events /changes since the last City Commission
meeting.
CONSIDERATIONS:
Those projects listed below are those with some consistent activity, although not every project
has additional activity for every update report. For a project maps and information on the
school generation rates in the City, please go to the http: // www.winterspringsfl.org /item100.
The number to the left of the project name in this report corresponds to the number on the City
Map showing the location of the project. Items listed below that have changed since the last
updates are shown in bold type.
• (1) SJRWMD (formerly Minter) Site - Staff review was held on August 25, 2008. The
site plan was reviewed at the September 3, 2008 P &Z Board meeting and the
conditional use was reviewed at the September 4, 2008 BOA meeting. Both site plan
and first reading for the rezoning were approved at the September 22, 2008
Commission meeting. The Conditional Use Permit and second reading/adoption of the
rezoning (Ord. No. 2008 -12) were held at the October 13, 2008 City Commission
meeting. Public Works provided an informational up -date of the status of the Solary
Canal Stormwater Treatment Area project to the Commission at its March 23, 2009
meeting. A pre -bid was held April 16, 2009 with bids due April 29, 2009. The low
bidder was Briar Corporation at $1.23 million. Briar Corporation backed out of the
process because they were unwilling to hold their price for 90 days. An update project
was provided at the December 14, 2009 City Commission meeting. A contract was
awarded to the 2 lowest bidder, Wal -Rose. Staff met with Wal -rose on March 31,
2010. Construction commenced on Monday, April 19, 2010. Construction is
scheduled for completion in December 2010.
July 12, 2010
Information 100
Page 2 of 12
• (3A) Mann Site (Ladybird Academy) — Preliminary engineering plans for the 7,500
S.F. Ladybird Academy Daycare received a unanimous vote for approval at the
October 7, 2008 P &Z Board meeting and was approved, subject to conditions, at the
October 27, 2008 City Commission meeting. The Applicant submitted for final
engineering approval on April 6, 2009. The revised engineering plans and aesthetic
package were reviewed at the June 16, 2009 staff review. The applicant's preliminary
building plans have been reviewed for sufficiency. The final engineering/site plan and
aesthetic revisions were approved at the August 10, 2009 Commission, along with a
Development Agreement/Notice of Zoning Restriction modification. A pre -
construction meeting was held on October 15, 2009. The properties to the north will be
designated as recipient site for trees donated in fulfillment of arbor permit obligations.
Site work is on -going and the building permit was issued on January 4, 2010. Vertical
construction is progressing. Construction of the SR 434 modifications is complete but
must be inspected and accepted by FDOT. The building shell construction is
complete and the interior build -out is underway.
• (6) Jetta Point Park — The $9.5 million slated for construction of the Jetta Point Park
project was re- appropriated in the Seminole County budget to help cover general fund
shortfalls for the 08 -09 fiscal year. Seminole County staff contacted City staff to
schedule a pre - application meeting for Tuesday, December 2, 2008. Staff held
discussion with the project designer on November 14, 2008 to review setback and
buffering issues for the park. Staff conducted a pre- application meeting with the
project's designers on December 2, 2008 to review the conceptual park master plan and
provide direction to the County and its design team. The meeting included
representatives of both the City of Oviedo and LYNX. Another meeting between
PBS &J staff and City staff was conducted December 10 to further address outstanding
issues. The County Leisure Services staff met on January 6, 2009 to review the 60%
design plans with the project engineer. Urban Beautification/Arbor staff met with the
design team on -site on May 19, 2006 to discuss tree quantification procedures and
mitigation options. Staff has been contacted relative to the submittal of both the
geotechnical report and the traffic study for the park. Staff received an aesthetic review
package for the park on July 30, 2009 and addressed it with the applicant at the August
18, 2009 staff review. The complete site plan application package was received on
August 21 and was addressed at staff review on September 15. Staff has reviewed and,
at the September 1, 2009 staff review, provided comments to representatives of the
adjacent Vistawilla site, regarding access to the park through the Vistawilla site. Staff
and PBS &J held a conference call on October 1 to address final comments and to craft
a schedule for public hearings, P &Z and Commission meetings for the aesthetic review,
site plan/final engineering, and developer's agreement. Staff had expected a re-
submittal from the project engineer in late November of December 2009. Staff met
with the applicant during the week of December 7, 2009 to discuss the City's littoral
planting requirements for the retention ponds. Staff was advised by the consultant that
a resubmittal should be forthcoming in January 2010. The consultant has submitted the
Florida Department of Environmental Protection (FDEP) water and sewer permits
applications to the City. According to the Seminole County Leisure Services
Department, construction should begin in late fall or early winter, 2010. Final
engineering and aesthetic review plans were reviewed at staff review on March 30,
July 12, 2010
Information 100
Page 3 of 12
2010. At a special April 28, 2010 meeting, the Planning & Zoning Board
recommended the final engineering/site plan be approved subject to a development
agreement. The applicant held a community meeting with the neighbors for more than
an hour, at City Hall, immediately before the P &Z meeting. At the May 10, 2010 City
Commission meeting, 15 citizens voiced concerns about the proposed park. The City
Manager has sent a letter to the County Manager regarding the proposed park and the
citizens' concerns. The County Manager responded in a letter addressing the citizens'
concerns. A group of concerned citizens opposed to the park at this location addressed
the City Commission during the public input portion of the May 24 and June 14, 2010
Commission meetings, as well as at an unrelated June 21, 2010 workshop. The
County Commission Chair, Bob Dallari, sent the City a letter stating that the
county is looking to locate the park elsewhere and instructing the City to stop
work on the permitting and Comprehensive Plan Land Use Change efforts.
• (8) Oviedo Marketplace —The plan for Section B of Parcel 14, comprised of a 77 unit
condominium project, was submitted on September 25 and was reviewed at the October
21, 2008 staff review. Staff received correspondence on December 1, stating that the
applicant was considering developing 58 residential units and using the southerly 2.5
acres (separated from the rest of the site by wetlands) for self - storage. On August 10,
2009, the Commission agreed with the applicant's request to allow a 100,000 SF
storage facility within the DRI/PUD. At its October 12, 2009 meeting the Commission
approved an implementation agreement authorizing the indoor personal storage and
approved the concept of substituting either 184 independent living units, 318 assisted
living facility beds, or some combination of these on the remaining portion of Parcel
14. Staff met with the applicant on January 28 to address development of the storage
facility. A site plan for the storage facility was submitted on February 17, 2010 and
was addressed at the March 16 staff review. Staff worked with the City Attorney to
determine a number of issues regarding the site (e.g. master plan, buffer, setbacks, and
signage). The applicant is currently working on the plat for Parcel 14 and anticipates
coming back with the Master Plan.
• (8A) Tuskawilla Greens (Tuscawilla Country Club) — The PUD master plan
amendment, preliminary & final PUD, and site plan were approved (along with a
development agreement and 4th amended settlement agreement) at the September 8,
2008 Commission meeting. Plans for the renovation /modification of the tennis courts
and country club parking area were received on August 1, 2008 and were reviewed at
the August 19, 2008 staff review. The applicant submitted a plan for the borrow pit
along Northern Way for the fill material to be used on this project. The tennis court site
plan received a recommendation of approval at the November 5, 2008 P &Z Board
meeting and was approved, subject to conditions, at the November 24, 2008
Commission meeting. At its December 8, 2008 meeting, the Commission addressed its
condition of approval that the 4 tennis court be provided before the first certificate of
occupancy, amending the condition to allow more than one half of the 60 units to be
occupied before the fourth tennis court is required. A preconstruction meeting was
held on December 10, 2008. The Aesthetic Review was approved at the City
Commission's January 26, 2009 meeting. The final engineering and landscape plans
for the proposed Northern Way Borrow Pit was denied at the February 9, 2009 meeting
July 12, 2010
Information 100
Page 4 of 12
because of the well to supply the pond. The revision, without the well or the pond
liner, was approved at the February 23, 2009 Commission. The aesthetic review
modification to remove the faux chimneys was approved at the July 13 Commission
meeting. The applicant then submitted engineering drawings for the proposed second
borrow area located along Northern Way, just westward of the first borrow area. At the
August 24 meeting it was announced that the applicant has withdrawn plans for this
excavation from consideration. The City's Building Official met with the applicant on
October 1, 2009 to discuss the permit and impact fees for this project. The site
superintendent met with staff regarding provision of the fourth tennis court. At its
January 25, 2010 meeting, the Commission considered a request from the country club
to modify the completion date for the fourth tennis court. The Commission voted 5 -0
that once country club pays the City the $12,500 it is owed for the TLBD final
contribution; the City Attorney will start negotiating alternatives (the $12,500 was
subsequently received).
•
• (10) Sonesta Pointe (AKA Winter Springs Town Homes, Sonoma Pointe, or Calusa
Cay) — Preliminary plans for approximately 436 town -homes on 40 acres within the
Town Center were received from Engle Homes on July 2, 2004, and were approved as
a concept plan at its August 9, 2004, meeting and refined it at its September 27, 2004
meeting. The City Attorney noted that the concept plan, as proposed, would require a
development agreement or special exception or both. The 40 acres had been acquired
without platting. The applicant has hired a new design team and met with staff on May
31 and July 8, 2005 to summarize outstanding issues. On August 29, 2005, staff
received an aesthetic review package. The state required a letter from the City's Local
Planning Agency, stating that crossing the Cross - Seminole Trail with underground
utility lines is consistent with the City's Comprehensive Plan (approved at the
December 6, 2005 LPA/P &Z meeting). The aesthetic review was approved at the
August 28, 2006 Commission meeting. A final engineering plan was resubmitted on
September 20, 2006 and was reviewed at the October 3, 2006 staff review. A request
for an early work permit was heard at the September 25, 2006 meeting, but a decision
was deferred until more information is provided regarding specimen tree preservation.
The applicant withdrew the early work permit request. The applicant resubmitted for
an early work permit and provided the additional information requested by the
Commission. This permit was approved by the Commission at the Novemberl3, 2006
City Commission meeting. The final engineering plans and the Development
Agreement were approved at the December 11, 2006, Commission meeting, but the
development agreement was not executed or recorded. A revised concept plan
featuring 289 total units, incorporating 114 single family detached units with 72 duplex
units, 103 townhomes, 2 -car garages, and 260 on- street parking spaces ( the 260 is
excluding the Tuskawilla Road on- street parking) was approved at the May 14, 2007
Commission meeting. The Sonesta team met with staff on June 27, 2007, addressing
lowering the overall site elevation and lowering some units to less than the prescribed
2' minimum elevation above the adjacent sidewalk. A revised aesthetic review
package was approved at the August 13, 2007 Commission meeting. Final engineering
plans were received on August 20, 2007 and were addressed at a special September 11,
2007 staff review. Staff reviewed an electronic revision to the plans and advised the
applicant of the necessary procedures to finalize the plan changes. Staff and Dover
July 12, 2010
Information 100
Page 5 of 12
Kohl & Partners reviewed and provided preliminary comments to the applicant's
informal concept plan for the site that includes various single - family detached units,
including front - loaded garages. At its April 28, 2008 meeting, the Commission
approved a site development permit for limited clearing on the property in those areas
permitted for wetland mitigation The concept plan was addressed at the May 18, 2010
staff review meeting and received conditional approval at the June 14, 2010
Commission meeting. Renewal of the early work permit was approved at the May 24,
2010 City Commission meeting and staff is awaiting an executed copy of the
agreement as well as satisfaction of the requirements to pull an arbor permit. Meetings
were conducted on June 22, 2010 and June 25, 2010 to discuss the early work
permit, modifications of the concept plan to eliminate the existing deviations, and
the landscape plan details.
• (11) JDC Calhoun I. City records indicate the following businesses are locating or
have located in the JDC Calhoun Town Center:
• City staff has compiled an ownership map for Phase I of the Town Center. This
map has been made available electronically for reference purposes. Staff is
arranging a meeting with the new management company to discuss landscape and
hardscape maintenance, irrigation system repair and maintenance as well as overall
site maintenance. Staff met with two of the management/leasing companies on
December 8, 2009 to discuss the current status of the Town center /lease
amounts /recent tenant losses, and plans for moving the Town Center forward. Staff
received an e -mail list from the tenant meeting and has updated the tenants on all
relevant information regarding the management and final ownership of the various
sections of the Town Center. Staff was working with Transwestern (management
company) to locate Verizon Wireless Services at the western end of Building 11,
but Verizon withdrew. Staff had a meeting on January 19, 2010 with a
representative of Business Capital Solutions Group regarding marketing of the
Town Center. This representative is also contacting the management companies for
the Town Center properties. Staff understands that the transfer occurred on March
16, 2010. Mosaic Restaurant has opened in the former Beef O'Brady's location.
The Hidden Harbor Seafood and Lobster Feast is scheduled to open in early July in
the former Gian Carlo's location. Staff had a meeting with representatives of
Kee Wee Entertainment on July 2, 2010 to discuss initial plans for a family
entertainment complex and restaurant in Building #1 of the Town Center.
• (13) Town Center Phase II - Staff met with IBEW and 5 th / 3rd Bank representatives on
August 28, 2008 to discuss a possible lot split and the location of a branch bank on a
parcel located along the north side of SR 434, just east of the McDonald's. Staff met
Atwell -Hicks Development Consultants representatives on September 24, 2008 to
discuss lot split, infrastructure, and site design issues associated with the proposed
bank. A lay -out sketch was provided to staff on October 3, 2008. This sketch and
cursory staff comments have been forwarded to Dover Kohl and Partners for further
review. Staff met again with representatives of 5 /3 Bank and the IBEW to look at
proposals for the site design. Another proposal was sent via e-mail to staff and has
been reviewed by staff. Comments were sent to the applicant on December 30, 2008.
July 12, 2010
Information 100
Page 6 of 12
The FDOT has denied the turn lane request of the 5` /3 `d Bank team. City staff met
with the development team on February 2, 2009 to discuss the left turn lane issue.
Additional discussions with FDOT will be scheduled regarding the turn lane and
possible access from Tuskawilla Road, behind the McDonald's site. Staff met with
representatives of Lochrane Engineering and the IBEW's attorney on March 12, 2009
to discuss details of the Phase II Implementation Agreement. Staff and the City
Attorney met with representatives of the IBEW on December 7, 2009 about possible
modifications to the Implementation Agreement. Agenda Item 601 on the January 25,
2010 City Commission meeting addressed the proposed changes to the Phase 2
Implementation Agreement. The Commission voted to table the item and take it to a
special meeting which on February 11, 2010 at 6 PM. At the Special Commission
meeting on February 11, 2010, the Commission voted to negotiate a new
implementation agreement with the IBEW, preserving certain items contained in the
current agreement and allowing the IBEW more flexibility to market the property for
new development. Any new proposals must adhere to the Town Center Code and will
be subject to review and approval of the City Commission. Staff met in April with
developer representatives interested in placing three businesses on the northeast corner
of SR 434 and Tuskawilla Road. Staff had another meeting with this developer in May
2010 to attempt to modify the site plan to meet the Town Center Code requirements.
• (13 A)Town Parke Apartments — The 10.32 acre site is located on the south side of
SR 434, between the Mobile station and the pedestrian bridge. A conceptual site plan
for 201 (was 204) residential apartment units (1 -4 BR) with 413 (was 388) parking
spaces was submitted to the City on March 3, 2009 and was addressed at staff review
on March 19. The City Arborist and the applicant's landscape architect conducted a
site inspection for March 4, 2009. Revised plans were submitted on March 27 and
were addressed at staff review on April 7, 2009. Further revised plans were received
on April 10 and were approved as a concept review by the Commission on April 27,
2009. The concept approval was re -heard at a May 18, 2009 special meeting and was
approved subject to a negotiated Development Agreement with specific stipulations.
Further discussion ensued at the special May 26, 2009 Commission meeting regarding
crime statistics for high density housing areas. Staff has had no recent communications
with the applicant for this development. The Chronicle Jan. 28 -Feb. 3, 2010) stated
that a lawsuit between Atlantic Housing Partners and the City of Oviedo, regarding
language in a development agreement which required owner- occupied residential units,
at site at SR 434 and Chapman Road, was dismissed by U.S. District Judge Anne
Conway. The applicant's engineer met with staff on March 1, 2010, to address how to
proceed. Staff is responding to various questions from the applicant's consultants at
this time. Staff met with the applicant's landscape architects, Foster Conant, on April
20. Staff has requested a draft of the proposed development agreement language and
has also requested the status of the economic fiscal impact report as required by the
City's Comprehensive Plan. Staff is continuing to field questions from the applicant's
consultants on design - related matters. Staff has forwarded the Comprehensive Plan
language that requires an economic fiscal impact report to the project engineer. No
information relative to the draft development agreement language has been received as
of April 30, 2010. Combined preliminary and final engineering plans were submitted
on May 05, 2010 and were addressed at the May 25 staff review. Aesthetic review
July 12, 2010
Information 100
Page 7 of 12
plans were addressed at the June 8 staff review. Staff met with the architect on June
30, 2010 to discuss building architecture.
• (14 Magnolia Park — Staff met with the design team on April 14, 2009 to provide
initial comments on the trail land swap, site, and building design, for the amphitheater
with its changing rooms and rest rooms, in preparation for formal submittals. Staff met
with the consultants on May 14, 2009 to discuss the landscaping, lighting, and sound
components of the design. Additional discussions were held on May 29, 2009
regarding the lighting and sound designs. Staff has received the 60% plans on July 31,
2009 and addressed these plans at the September 1, 2009 staff review. Aesthetic
Review of this project was conducted as part of the October 6, 2009 staff review
meeting. Staff is awaiting the resubmittal of the aesthetic review documents in
response to the October 6, 2009 review. Final staff reviews of the aesthetics and final
engineering were held on December 8, 2009. Staff awaits the final engineering and
aesthetic plan re- submittal for the City Commission. Also, the trail swap is being
delayed because the State wants to bundle the Magnolia Park Trailhead and the Bart
Phillips trail right -of -way dedication along SR 419 together. Staff is working to resolve
these items. The final engineering /site plan and aesthetic review received Commission
approval at the March 22, 2010 Commission. The Lien Satisfaction Agreement has
been executed by the both Bart Phillips and the City and will be forwarded to the City
Attorney for recordation and processing for the purpose of moving forward on the
various dedications for right -of -way and the swapping of trail right -of -way with the
Magnolia Park Amphitheater site. Discussions are underway between Mr. Phillips, the
CSX railroad, Seminole County, and the State Office of Greenways and Trails
regarding the CSX railroad crossing and the trail property swap. Seminole County is
working with CSX Railroad on the swap and City Staff is meeting with the County on
their request for some survey work. Seminole County is making application for an
easement to cross the CSX railroad with the Cross Seminole Trial.
• (19) Grandeville at Town Center (f/k/a Villa Grande &. Grandville) — Staff is working
with the applicant to finalize revisions to the permit plans and to finalize the address
assignments for the units. A pre - construction meeting and permit issuance should be
forthcoming in the next few weeks. Staff met with the applicant on September 29,
2008 to finalize the methodology for building valuation to be used in assessing the
appropriate building permit fees. The applicant reports renegotiating materials prices
(in light of recent price declines) in preparation for submitting for a construction permit
to do the site /civil construction and obtaining building permits. The applicant met
again with staff on December 23, 2008 and announced that, due to the international
financial crisis, they were suspending the project indefinitely. The applicant has asked
for contact information for another developer who approached the City with a proposal
for an "independent living" facility for seniors. Staff met with the applicant on
February 27 and again on April 16, 2009 to discuss options for modifying the proposal
to 144 age- restricted apartments utilizing a site plan similar to the one previously
approved. Further discussions relative to the final design and economic development
incentives for this project were scheduled for June 9, 2009, but were re- scheduled for
June 16, 2009. The applicant is currently working on financing for this project and the
City is continuing consideration of potential economic development incentives. Staff is
July 12, 2010
Information 100
Page 8 of 12
working with the applicant to finalize the financial package and to finish the write up to
be used in marketing the project. Staff provided a letter on September 28, 2009
detailing the existing project status. This letter will be used as part of the financial
package for the project. Staff met with the project representative on October 19, 2009
to discuss the schedule for consideration/approval of the project modifications as
related to the conversion of the project to age- restricted apartments. Staff met with the
applicant on January 26, 2010 once again to address applicable City and county impact
fees. Staff has also provided local demographic and recent activity information on the
Town Center to assist the developer with their HUD application. The applicant has
maintained contact with staff regarding the project. As of May 14, 2010, the developer
has stated that HUD is running 90 -120 days late with their invitations. The developer
expects to hear from HUD within the next 50 -75 days and has indicated that they will
need expedited services from the City once this invitation is received.
• (20) Wagner's Curve Office/Retail (Pinch - A - Penny) — The aesthetic review and final
engineering/site plan were approved, subject to working out details, at the September
22, 2008 Commission meeting. Staff is awaiting submittal of a draft development
agreement. At its February 9, 2009 meeting, the Commission addressed the applicant's
request to reevaluate the Town Center Code. Per the Commission's direction, staff met
with the applicant to review the proposed changes to the building. Staff received the
revised design on March 3, 2009. Staff provided correspondence to the applicant's
representative on March 31, 2009, stating a number of concerns. At the October 26,
2009 Commission meeting, the applicant requested the Commission consider changes
to the Town Center Code to accommodate this site. Staff met with the applicant on
October 29, 2009 to discuss options for implementation of this project and possible
code modifications. Staff is working on possible text amendments for the Town Center
District to address small, irregularly- shaped lots and a possible "transition area" for the
periphery of the Town Center District. A workshop for consideration of possible text
amendments was held on June 21, 2010. Staff met with a representatives of the
Pinch -A -Penny project on June 24, 2010 to discuss ways to modify the
development proposal on the small site in light of the results of the Commission
Workshop held on June 21, 2010.
• Wagner's Curve (9 acre crescent - shaped parcel west of the Pinch -A Penny site) —
Staff has met with representatives proposing the relocation of an existing charter school
in Seminole County to this parcel. Concept plans for a charter school were submitted
April 28, 2010 and was the topic of a work session with the applicant, Victor Dover,
and staff on May 14, 2010. The designation of this parcel as a civic site, subject to
conditions, occurred at the June 14, 2010 Commission meeting. The conceptual plan
was approved with conditions at the June 28, 2010 Commission, along with the
first public hearing for the special exception.
• (21) HSP Office (1.6 acre Wagner's Curve Commercial site) — The final engineering
and aesthetic review were approved at the December 8, 2008 City Commission meeting
(the development agreement and subdivision plan — with subsequent plat - are still out-
standing issues). On November 17, 2009 and again on January 13, 2010, staff met with
representatives of The Primrose School to discuss a proposed concept plan for this
July 12, 2010
Information 100
Page 9 of 12
property. The owner has indicated that there are on -going discussions with the realtor
of the Primrose Academy and they are actively working toward a sale of the property to
the Primrose Academy. A new proposal has been discussed concerning another day
care academy for this site. No details have been provided as of May 14, 2010.
• (23) Brighthouse — The Brighthouse site plan for renovation of the 0.23 acre site on S.
Moss Road has progressed thru staff review and is scheduled for a special April 28,
2010 Planning & Zoning Board meeting. The site plan, aesthetic review, and special
permit were approved at the May 10, 2010 Commission meeting. Plan review for the
building construction is underway as of May 31, 2010.
• (25) Bart Phillips/ 419 Auto & Metal — On September 8, 2008, the Commission
adopted Ord. No. 2008 -11, which provided a restricted C -2 zoning for the 2 parcels
containing approximately 9.04 acres along SR 434. A revised aesthetic review package
for the perimeter wall was received December 19, 2008 and was approved at the
January 26, 2009 City Commission meeting. Vacation of the Ginger Lane and part of
the Old Sanford - Oviedo Road rights -of -way was approved at the February 9, 2009 City
Commission meeting. Staff met with the applicant's team on March 2, 2009 to discuss
the wall permit. A meeting was held with staff and the City Attorney on March 12,
2009 to discuss the Restrictive Rezoning and the Non - conforming use. Staff is
processing the building permit application for the wall for approval, subject to
conditions (e.g. recordation of easements and rezoning to either C -2 or restricted C -2).
The applicant has made application to rezone the C -1 property along SR 419 to a non-
restricted C -2 zoning in place of the restricted C -2 previously approved by the City
Commission. The new rezoning request received a recommendation for approval at the
June 3, 2009 Planning and Zoning Board meeting and Ordinance No. 2009 -10 had first
reading at the June 22, 2009 Commission meeting. Second and final reading for the
rezoning of the property along SR 419 was approved on July 13, 2009. The Building
permit for the first phase of the screen wall along the property's eastern boundary was
issued on September 28, 2009. Staff has received a request for a waiver of the front
setback along S.R. 419, behind the screen wall. A waiver for the front setback along
SR 419, behind the 10 -foot wall was approved by the City Commission on February 8,
2010. The City Attorney and staff took an ordinance to the Planning and Zoning Board
in February 2010 with proposed text amendments regarding permitted uses in the City's
I -1 Zoning District. The applicant has indicated that, in addition to the "secondary
metals recycling" operations in the proposed text amendment, he also wants the
allowance to do "recycling of non - hazardous materials ". This addition was discussed
during the Planning & Zoning Board meeting in February. First reading of the text
amendment for the I -1 zoning district the City Commission was approved at the
Commission's February 22, 2010 meeting. The applicant is in the process of
submitting a request for relief of the fines imposed by the Code Enforcement Board.
Once the Code Board makes a recommendation and an agreement between 419 Metals
and the City are finalized, this item will come back to the City Commission for second
reading. The Code Enforcement Board recommended approval of the reduction of fine
request at a special meeting on March 30, 2010. Second reading of Ordinance 2010 -03
amending the list of permitted uses in the I -1 District and the City Commission's
consideration of the Code Enforcement Lien Satisfaction Agreement received
July 12, 2010
Information 100
Page 10 of 12
Commission approval at the April 12, 2010 City Commission meeting. On April 28,
2010, Mr. Philips paid $500 necessary to satisfy the lien and submitted the executed
Lien Satisfaction document. The Lien Satisfaction Agreement was recorded on May
10, 2010. City staff is working with the County on the trail swap.
• (25A) Altomere Estates — On November 26, 2007, the Florida Engineering Group, on
behalf of Dr. Altomere, submitted a preliminary engineering /subdivision plan for
dividing the northern 17+ acres of the Dr. Moseley's replat into 7 residential lots
(ranging in size from 1.16 to 1.71 acres), roadway, 2 storm -water ponds, and a
previously dedicated conservation area. The plans were discussed at the December 18
staff review. On February 12, 2008, staff met with Dr. Altomare and his design
engineer to address major subdivision issues (lot size, floodplain, and emergency
access). Revised plans were submitted on December 24, 2008 and were reviewed at the
February 3, 2009 staff review meeting. Staff met on April 2, 2009 with the City
Attorney to determine how best to address the lot size compatibility issue. The
subdivision variance requests were heard at a special May 21, 2009 BOA meeting, to
address lot size and maximum cul -de -sac length variances. The applicant met on
May28 with the neighbors in Dunmar, to ascertain their concerns. The variances were
addressed at a public hearing at the June 8, 2009 Commission meeting and postponed
until the emergency access issue is resolved. Access documentation from the applicant
was sent to the City Attorney on October 21, 2009 for his review and comments. Staff
met with the City Attorney on January 14, 2010 to discuss the emergency access
location for this property. Staff is working with the Fire Marshal and the developer to
finalize an acceptable emergency access for this project.
• (26) Starlight Baptist Church — Staff met with the applicant on September 18, 2008 to
discuss building construction phasing. The applicant met with the Building Official on
October 14, 2008 to discuss modifications to the building plans necessary to implement
the phasing plan. A pre - construction conference was scheduled for December 2, 2008,
but was cancelled. The architect has worked with the Building Official on a number of
building design issues. The applicant has inquired about the initial phasing of the
project. The first portion of the construction would involve the enclosing of the
existing open basketball court building to serve as an interim meeting place during
construction of the new sanctuary. The contractor and site engineer have renewed
efforts to coordinate limited site work and enclosure of the covered basketball court
with staff. A very limited plan was addressed at the October 20, 2009 staff review.
Staff met with the consultant for this project on January 14, 2010. They are proposing
to enclose the basketball court for an overflow facility as phase 1 of the development.
Staff is working with the developer on Development Agreement language requiring
sidewalks on Bahama when the City paves that Road. The consultant indicated that the
Church may be in a position to begin the construction on the first part of the new
sanctuary by the summer of 2010. Staff is working with the applicant on the aesthetic
review for the first phase of development. A limited (scaled back) site plan revision,
comprised primarily of enclosing the 5,000 SF covered area, providing a more secluded
bus parking area, a dumpster enclosure, water and sewer connections, and sidewalks
along the adjacent ROWs was received and was addressed at the March 2 staff review.
The aesthetic review and final engineering for Phase I of the project were approved at
July 12, 2010
Information 100
Page 11 of 12
the April 26, 2010 Commission. A preconstruction conference was held on April 27,
2010. As of June 7, 2010, building plans are under review by the building department.
The building department has completed their review of the construction plans and
comments have been sent to the contractor for response.
• (27) Hayes Road Plaza —The City Attorney reported to the Commission on September
8, 2008 that the owner had conveyed property for the turn lane at the corner of SR 434
and Hayes Road. The plans are ready for issuance and the applicant is attempting to
secure the finance package. The owner has been notified in writing that the building
permit is ready to be issued, but, on December 19, 2008, applied for a conditional use
for a 24 -hour convenience store without gas pumps. This request was heard by the
Board of Adjustment on January 15, 2009 and was approved for the convenience store
without gas pumps at the January 26, 2009 Commission meeting. Staff met with the
applicant's team on February 10, 2009 to address aesthetic features for the 7 -11
convenience store. City staff has approved the revised traffic study. The Building
Official has been working with the owner to prevent the building permit application
from expiring, as the applicant continues to seek financing. The project representative
contacted City Staff on October 19, 2009 to let us know that they are almost finished
with modification of the architectural plans to comply with the 2007 Florida Building
Code. Updated construction plans were delivered for review on October 29, 2009.
These plans are currently under review by the building division. A contract has been
awarded for the turn lane on east -bound SR 434 and construction should begin after the
first of the year. At its December 14, 2009 meeting, the Commission directed the City
Engineer to address access options for this and the adjacent commercial site (to the
west) to the January 11, 2010 Commission meeting. Construction on the east -bound
SR 434 turn lane has been initiated, with most of the current work centering on utility
relocations. At its February 22, 2010 meeting, the Commission was informed by the
owner that he expects to receive financing and commence construction within about 45
days. On March 10, the owner told staff he anticipates 3 weeks until financing.
• (28) Park Manor Academy — Having obtained a conditional use and a waiver from the
building setback requirements, the applicant has submitted a combined preliminary and
final engineering plan submittal for the proposed 3,459 SF day care /pre - school facility
with 13 parking spaces, located at the SE end of Excelsior Parkway. The project was
addressed at the May 5, 2009 staff review. A plan resubmittal was received July 17,
2009 and has been reviewed by applicable staff. Staff awaits revised plans from the
design engineer. A response to staff's comments was received on December 30, 2009.
The final engineering /site plan (along with aesthetic review) was approved at the
February 22, 2010 Commission. A preconstruction conference was held and site work
commenced on March 25, 2010. Building plans have not been submitted as of July
2, 2010.
• (36) Lakeside Plaza — A conceptual site plan for 2 buildings comprising 64,614 S.F. of
combined office and retail space on an approximately 7 Y2 acre site abutting and
including part of Lake Talmo, was reviewed at the October 16, 2007 staff review. A
revision was reviewed at the December 10, 2007 staff review; another revision was
reviewed at the March 18, 2008 staff review. The concept plan was approved at the
July 12, 2010
Information 100
Page 12 of 12
May 27, 2008 Commission. The applicant prepared diagrams of the proposed
cantilevered deck, for discussion with staff regarding the restaurant and the minor
buffer encroachment. Final engineering plans were submitted on January 9, 2009 and
were reviewed at the February 3, 2009 staff review meeting. An aesthetic review
package was addressed at the April 21, 2009 staff review. A revised traffic analysis
was approved by staff on July 16, 2009. Staff has addressed the final engineering/site
plans and aesthetic review material at the August 18, 2009 staff review. At the same
meeting, 17 -92 CRA Program Manager John Metsopoulos addressed the applicant and
staff regarding potential CRA funding for this project. Staff provided information on
an alternative point of connection to the public sewer system in the Harbor Winds
Development.
FISCAL IMPACT: There is no fiscal impact associated with this agenda item.
COMMUNICATION EFFORTS: No communication efforts beyond the advertising of the
Commission agenda are necessary in conjunction with this agenda item.
RECOMMENDATION: The City Commission is being asked to review and accept the
information in this agenda item.
ATTACHMENTS: