CITY COMMISSION AGENDA | JUNE 8, 2026 REGULAR MEETING
TITLE
Wetland Park Outfall Improvements at the Cross Seminole Trail and Michael Blake
Boulevard - Change Order No. 3
SUMMARY
The overall project scope of work for this proposal includes professional services to
supplement the previous work efforts and authorizations summarized below:
O riginal P roposal – F inal Design and Permi*ng Services issued on J anuary 11,
2023.
C hange O rder #1 – A ddi3onal Final D esign and Permi*ng S ervices S ubmi4ed on
October 17, 2023.
C hange O rder #2 – A ddi3onal Final D esign and Permi*ng S ervices S ubmi4ed on
February 24, 2025.
O n S eptember 5, 2024, Pegasus E ngineering submi4ed an applica3on to the St. Johns
R iver Water M anagement D istrict (S J R W M D ) for an “I ndividual and C onceptual
A pproval E nvironmental Resource Permit, a S tate 404 P rogram Permit, and
Authorization to Use State-Owned Submerged Lands”.
D istrict staff issued a Request for A ddi3onal Informa3on (R A I ) for A pplica3on N o.
22437-9 on October 3, 2024.
B etween D ecember 27, 2024 and June 19, 2025, the applicant submi4ed five
requests for 90-day time extensions.
A request to officially withdraw the applica3on was submi4ed on S eptember 15, 2025
and approved by D istrict staff on O ctober 6, 2025. T he proposed drainage
improvements between Tuskawilla Road and Wetland Park were revised following
mul3ple coordina3on mee3ngs with S eminole C ounty representa3ves. As part of this
effort, the horizontal alignment was shiGed westward to reduce jurisdic3onal impacts
within Wetland Park. A ddi3onally, design modifica3ons were also dictated by a
S eminole County ordinance prohibi3ng u3li3es from running parallel to mul3-use trails,
limiting the alignment to orthogonal crossings only.
O n February 10, 2026, Pegasus E ngineering submi4ed a new applica3on to the S t. Johns
River Water Management District (SJRWMD) for an “Individual and Conceptual Approval
Environmental Resource Permit, a State 404 P rogram Permit, and A uthoriza3on to Use
State-Owned Submerged Lands”.
424
D istrict staff issued a Request for A ddi3onal Informa3on (R A I ) for A pplica3on N o.
22437-10 on March 10, 2026.
The D istrict ’s pending R A I le4er, provided within E xhibit “D ”, includes a total of 16
comments encompassing both engineering and ecological issues.
The current change order includes out of scope work efforts pertaining to: S J R W M D E R P
permi*ng efforts including wetland mi3ga3on; an A pplica3on for U se of S tate O wned
U plands submi4ed to the F lorida D epartment of P rotec3on (F D E P ) B ureau of S tate
Lands – Bureau of Public Land Administration; and Limited Post-Design Services.
FUNDING SOURCE
This is currently budgeted in Third Generation Sales Tax under City Wide Stormwater
Improvements (Wetlands Park). Pegasus Engineers will provide these engineering
services to the City under the terms of the Agreement for Continuing Civil Engineering
Services – Road and Transportation Facilities, Stormwater Engineering and Flood Control
that will be reinstated retroactively for the limited purpose of approving, performing,
and completing this Task Order.
RECOMMENDATION
S taff requests C ity C ommission approval of Wetland Park O uKall Improvements at the
C ross S eminole Trail and M ichael B lake B oulevard - Change Order N o. 3 for modified
professional consultant services in the amount of $89,800.00
425
“Engineering a Higher Standard”
301 West State Road 434, Suite 309, Winter Springs, FL 32708 407-992-9160 Fax 407-358-515
May 21, 2026 P-229701
Mr. Clete Saunier, P.E.
Director of Public Works and Utilities
400 Old Sanford Oviedo Road
Winter Springs, Florida 32708
csaunier@winterspringsfl.org
Re: Wetland Park Outfall Improvements at the
Cross Seminole Trail and Michael Blake Boulevard
Subj: Change Order #3 – Final Design and Permitting Services
Dear Clete:
In follow-up to our previous discussions, we are pleased to submit the following documents
that comprise a change order proposal for the above referenced project pursuant to the
requirements of the City’s Master Agreement for Continuing Engineering Services – Road and
Transportation Facilities, Stormwater Engineering and Flood Control:
Exhibit "A" (Scope of Work);
Exhibit “B” (Manhour and Fee Estimate);
Exhibit "C" (Sub-consultant Proposals); and
Exhibit "D" (Relevant SJRMWD correspondence).
We look forward to finalizing this important assignment for the City of Winter Springs. If you
have any questions regarding the enclosed documents, please contact me at 407-992-9160,
extension 309 (office), 407-247-0003 (cell), or by e-mail at david@pegasusengineering.net.
Sincerely,
PEGASUS ENGINEERING, LLC
David W. Hamstra, P.E., CFM
Stormwater Department Manager
cc: Greg Teague, Pegasus Engineering
426
Mr. Clete Saunier
May 21, 2026
Page 2
Wetland Park Outfall Improvements at the
Cross Seminole Trail and Michael Blake Boulevard
Change Order #3
Final Design and Permitting Services
Approved for Pegasus Engineering, LLC
_______________ _____ Principal May 21, 2026
Fursan Munjed, P.E. Officer’s Title Date
This proposal is hereby accepted and authorization to proceed is hereby given.
(Please return one executed copy of this proposal for our Pegasus Engineering records).
_______________ _____ __________________
Authorized Signature Officer’s Title Date
427
WETLAND PARK OUTFALL IMPROVEMENTS AT THE
CROSS SEMINOLE TRAIL AND MICHAEL BLAKE BOULEVARD
CHANGE ORDER #3 – FINAL DESIGN AND PERMITTING SERVICES
Scope of Work
428
WETLAND PARK OUTFALL IMPROVEMENTS AT THE CROSS SEMINOLE TRAIL AND MICHAEL BLAKE BOULEVARD
CHANGE ORDER #3 – FINAL DESIGN AND PERMITTING SERVICES
A-1 P-229701
The scope of work for this proposal includes professional services to supplement the previous
work efforts and authorizations that are summarized below.
Original Proposal – Final Design and Permitting Services
Purchase Order No. 2023-00000494 issued on January 11, 2023
Change Order #1 – Additional Final Design and Permitting Services
Submitted on October 17, 2023
Change Order #2 – Additional Final Design and Permitting Services
Submitted on February 24, 2025
On September 5, 2024, Pegasus Engineering submitted an application to the St. Johns River
Water Management District (SJRWMD) for an “Individual and Conceptual Approval
Environmental Resource Permit, a State 404 Program Permit, and Authorization to Use State-
Owned Submerged Lands”.
District staff issued a Request for Additional Information (RAI) for Application No.
22437-9 on October 3, 2024.
Between December 27, 2024 and June 19, 2025, the applicant submitted five requests
for 90-day time extensions.
A request to officially withdraw the application was submitted on September 15, 2025
and approved by District staff on October 6, 2025.
The proposed drainage improvements between Tuskawilla Road and Wetland Park were
revised following multiple coordination meetings with Seminole County representatives. As
part of this effort, the horizontal alignment was shifted westward to reduce jurisdictional
impacts within Wetland Park. Additionally, design modifications were also dictated by a
Seminole County ordinance prohibiting utilities from running parallel to multi-use trails, limiting
the alignment to orthogonal crossings only.
429
WETLAND PARK OUTFALL IMPROVEMENTS AT THE CROSS SEMINOLE TRAIL AND MICHAEL BLAKE BOULEVARD
CHANGE ORDER #3 – FINAL DESIGN AND PERMITTING SERVICES
A-2 P-229701
On February 10, 2026, Pegasus Engineering submitted a new application to the St. Johns River
Water Management District (SJRWMD) for an “Individual and Conceptual Approval
Environmental Resource Permit, a State 404 Program Permit, and Authorization to Use State-
Owned Submerged Lands”.
District staff issued a Request for Additional Information (RAI) for Application No.
22437-10 on March 10, 2026.
The District’s pending RAI letter, provided within Exhibit “D”, includes a total of 16
comments encompassing both engineering and ecological issues.
The current change order includes out of scope work efforts pertaining to: SJRWMD ERP
permitting efforts including wetland mitigation; an Application for Use of State Owned Uplands
submitted to the Florida Department of Protection (FDEP) Bureau of State Lands – Bureau of
Public Land Administration; and Limited Post-Design Services.
Pegasus Engineering, LLC (Consultant), shall provide the engineering services as itemized on the
Manhour and Fee Estimate provided as Exhibit “B”. It should be noted that this change order
includes only new task assignments, expanded task assignments and sub-consultant services
that are intended to supplement the previous authorization.
Referring to the information provided within Exhibit “C”, the scope of work for this change
order will require additional sub-consultant services as discussed below.
Survey Sub-consultant ................................................................................ Reserve Geospatial
1. Legal sketches and descriptions were not a part of any of the previous authorizations.
Two (2) easement documents were needed to accompany the FDEP application for use
of State Owned Uplands.
2. A survey allowance has been included and will be utilized only if the ecological sub-
consultant (GAI) establishes seasonal high water (SHW) levels by setting survey nails
during additional field meetings with SJRWMD representatives.
Ecological Sub-consultant ....................................................................... GAI Consultants (GAI)
1. Although a previous change order included preparation of an Ecological Assessment
Report (EAR) for Wetland Park along with limited permitting assistance, the current
change order expands the scope to address the pending SJRWMD RAI comments,
including additional work efforts specific to wetland impacts and mitigation.
430
WETLAND PARK OUTFALL IMPROVEMENTS AT THE CROSS SEMINOLE TRAIL AND MICHAEL BLAKE BOULEVARD
CHANGE ORDER #3 – FINAL DESIGN AND PERMITTING SERVICES
A-3 P-229701
Structural Sub-consultant ............................................... Florida Bridge & Transportation (FBT)
1. Although a previous change order included structural engineering and design services
for the proposed sheet pile wall, the current change order expands the scope to include
post-design services.
The conditions and assumptions contained within the scope of work for the original proposal
and the previous change orders are also applicable to the current change order proposal but will
not be reiterated herein. The following conditions and assumptions are noted as additional
qualifications to this change order proposal.
1. This proposal does not include the following professional services. In the event that any of
these services are required in the future, it is assumed that an amendment will be
processed to encompass those additional services.
Permit application fees.
Costs for purchasing wetland mitigation credits.
2. Contingency allowances if included in the fee estimate may or may not provide sufficient
monies to complete the intended work in totality. If the assumed budget is insufficient, it is
assumed that an amendment will be processed to encompass those additional services.
Alternatively, and in lieu of a contract amendment, work will only continue until such time
that the budgeted contingency is exhausted.
431
WETLAND PARK OUTFALL IMPROVEMENTS AT THE
CROSS SEMINOLE TRAIL AND MICHAEL BLAKE BOULEVARD
CHANGE ORDER #3 – FINAL DESIGN AND PERMITTING SERVICES
Manhour and
Fee Estimate
432
Task Description (See Note 1 Below)Department Project Sr. Project CADD Admin.
(Effective Date : May 21, 2026)Manager Manager Engineer Technician Assistant
Hourly Rate $177.91 $177.91 $161.46 $95.68 $74.75
A Additional Project Administration 0.0 $0.00
A1 => Prepare and issue the sub-consultant NTP letters and contract agreements 2.0 2.0 4.0 $505.32
A2 => Coordinate with the sub-consultants 2.0 2.0 $355.82
A3 => Perform sufficiency reviews of the preliminary sub-consultant deliverables 4.0 4.0 $711.64
A4 => Up to two (2) additional meetings with City staff or other interested parties 6.0 6.0 $1,067.46
A5 => QA/QC the final project deliverables 8.0 8.0 $1,291.68
A6 => Monthly status reports via invoices 6.0 6.0 12.0 $1,515.96
B Additional Construction Plans 0.0 $0.00
B1 => Cover Sheet 0.0 $0.00
B2 => General Notes 0.0 $0.00
B3 => Drainage Map 0.0 $0.00
B4 => Topographic Survey (by others) 0.0 $0.00
B5 => Topographic Survey (by others) 0.0 $0.00
B6 => Topographic Survey (by others) 0.0 $0.00
B7 => Topographic Survey (by others) 0.0 $0.00
B8 => Topographic Survey (by others) 0.0 $0.00
B9 => Topographic Survey (by others) 0.0 $0.00
B10 => Topographic Survey (by others) 0.0 $0.00
B11 => Overall Project Plan and Key Sheet 0.0 $0.00
B12 => Plan and Profiles - Cross Seminole Trail 0.0 $0.00
B13 => Plan and Profiles - Cross Seminole Trail 0.0 $0.00
B14 => Plan and Profiles - Michael Blake Boulevard 0.0 $0.00
B15 => Plan and Profiles - Michael Blake Boulevard 0.0 $0.00
B16 => Plan and Profiles - Michael Blake Boulevard 0.0 $0.00
B17 => Plan and Profiles - Michael Blake Boulevard 0.0 $0.00
B18 => Cross Section - Cross Seminole Trail 8.0 2.0 12.0 22.0 $2,894.36
B19 => Cross Section - Michael Blake Boulevard 8.0 2.0 12.0 22.0 $2,894.36
B20 => Wetland and Other Surface Water Impacts 6.0 2.0 6.0 14.0 $1,964.46
B21 => Drainage Structure Details - Cross Seminole Trail 0.0 $0.00
B22 => Drainage Structure Details - Cross Seminole Trail 0.0 $0.00
B23 => Drainage Structure Details - Michael Blake Boulevard 0.0 $0.00
B24 => Drainage Structure Details - Michael Blake Boulevard 0.0 $0.00
B25 => Miscellaneous Details 0.0 $0.00
B26 => Temporary Erosion Control Details 0.0 $0.00
B27 => Sheet Pile Structural Engineering Plan (by others) 0.0 $0.00
Task Hours Task Fees
Red text was used to indicate the new
and/or additional plan sheets that were
not included in the original authorization
or previous change orders.
Wetland Park Outfall Improvements at the Cross Seminole Trail and Michael Blake Boulevard Final Design and Permitting Services
Page 1 P-229701 433
Task Description (See Note 1 Below)Department Project Sr. Project CADD Admin.
(Effective Date : May 21, 2026)Manager Manager Engineer Technician Assistant
Hourly Rate $177.91 $177.91 $161.46 $95.68 $74.75
Task Hours Task Fees
Wetland Park Outfall Improvements at the Cross Seminole Trail and Michael Blake Boulevard Final Design and Permitting Services
C Additional SJRWMD Permitting - Environmental Resource Permit (ERP) Application 0.0 $0.00
C1 => Prepare and submit an ERP application to the SJRWMD 16.0 6.0 4.0 26.0 $4,198.04
C2 => Address RAI comments from the SJRWMD (assume one round) 2.0 16.0 6.0 4.0 4.0 32.0 $4,852.86
D FDEP Permitting - Application for Use of State Owned Uplands 0.0 $0.00
D1 => Coordinate with County staff regarding the Cross Seminole Trail 2.0 4.0 2.0 8.0 $1,390.38
D2 => Prepare a "draft" Written Statement from the Managing Agency (Seminole County) 2.0 2.0 $355.82
D3 => Delineate the proposed easements and prepare figures 4.0 2.0 6.0 12.0 $1,608.64
D4 => Coordinate with the survey sub-consultant (legal sketches and descriptions) 2.0 2.0 $355.82
D5 => Coordinate with City staff regarding a City Commission Resolution 2.0 2.0 $355.82
D6 => Fill out the application and prepare a supporting narrative 8.0 4.0 12.0 $2,069.12
D7 => Update the construction plans to show the new upland easements 3.0 6.0 9.0 $1,107.81
D8 => Coordinate with FDEP representatives 6.0 3.0 9.0 $1,551.84
D9 => Prepare responses to one (1) Request for Additional Information (RAI) 2.0 8.0 4.0 4.0 2.0 20.0 $2,957.16
E Bid Documents 0.0 $0.00
E1 => Finalize the construction cost estimate 6.0 2.0 8.0 $1,390.38
E2 => Prepare a bid schedule 2.0 2.0 $355.82
E3 => Prepare Special Provisions, Supplemental Specifications, and Special Bid Items 24.0 6.0 4.0 34.0 $5,537.60
E4 => Meet with City staff to discuss comments for the bid documents 2.0 2.0 $355.82
E5 => Prepare and transmit final bid documents 8.0 4.0 8.0 20.0 $2,834.56
F Limited Post-Design Services 0.0 $0.00
F1 => Prepare for and attend the pre-construction meeting 3.0 3.0 $533.73
F2 => Review and process shop drawings 0.0 $0.00
- Temporary erosion control plan and pollution control details 2.0 2.0 $355.82
- Precast drainage structures 8.0 2.0 10.0 $1,746.20
- Precast drainage pipes 2.0 2.0 $355.82
- Concrete mix designs 4.0 4.0 $711.64
- Superpave asphalt 2.0 2.0 $355.82
- Sheet pile (by others) 2.0 2.0 $355.82
F3 => Review and process up to three (3) shop drawing resubmittals 6.0 6.0 $1,067.46
F4 => Address the Contractor's RFIs during construction 2.0 16.0 6.0 6.0 30.0 $4,745.22
F5 => Prepare for and attend up to four (4) on-site meetings during construction 4.0 4.0 $711.64
F6 => Review and approve the Contractor's payment applications 12.0 4.0 16.0 $2,780.76
F7 => Review and approve up to two (2) change order submittals 8.0 2.0 10.0 $1,746.20
F8 => Conduct up to four (4) engineering inspections to monitor construction progress 8.0 8.0 $1,423.28
F9 => Prepare for and participate in the substantial completion inspection and provide "punch-list" 4.0 2.0 6.0 $1,067.46
F10 => Prepare for and participate in the final inspection 2.0 2.0 $355.82
F11 => Review the signed and sealed as-built survey 3.0 3.0 $533.73
Page 2 P-229701 434
Task Description (See Note 1 Below)Department Project Sr. Project CADD Admin.
(Effective Date : May 21, 2026)Manager Manager Engineer Technician Assistant
Hourly Rate $177.91 $177.91 $161.46 $95.68 $74.75
Task Hours Task Fees
Wetland Park Outfall Improvements at the Cross Seminole Trail and Michael Blake Boulevard Final Design and Permitting Services
F12 => Prepare record drawings 8.0 2.0 4.0 14.0 $2,128.92
F13 => Assemble a compendium of construction documentation 8.0 2.0 10.0 $1,746.20
F14 => Prepare an Engineer's Certification of Completion 2.0 2.0 $355.82
TOTAL LABOR HOURS 45.0 224.0 71.0 72.0 18.0 430.0 - -
TOTAL LABOR COSTS $8,005.95 $39,851.84 $11,463.66 $6,888.96 $1,345.50 - - $67,555.91
PERCENT BREAKDOWN (HOURS) 10.5% 52.1% 16.5% 16.7% 4.2% 100.0% - -
NOTES:1. Pegasus Labor Fees =
2. Other Direct Costs =
1. Refer to the proposal scope of work for additional discussions and qualifications. 3. Survey Sub-consultant - Reserve Geospatial =
2. Permit application fees are not included. 4. Getoechnical Sub-consultant - N/A =
3. Costs for purchasing wetland mitigation credits are not included. 5. Ecological Sub-consultant - GAI Consultants =
6. Structural Sub-consultant - FBT =
TOTAL FEES =
- -
$15,000.00
$89,800.00
$67,555.91
$148.19
$1,100.00
$5,995.90
Page 3 P-229701 435
WETLAND PARK OUTFALL IMPROVEMENTS AT THE
CROSS SEMINOLE TRAIL AND MICHAEL BLAKE BOULEVARD
CHANGE ORDER #3 – FINAL DESIGN AND PERMITTING SERVICES
Sub-consultant
Proposals
436
(Reserve Geospatial)
437
Page 1 of 2
CLIENT INFORMATION: February 14, 2026
Gregory Teague, PE, CFM
Pegasus Engineering, LLC
301 West State Road 434, Suite 309
Winter Springs, FL 32708
407-992-9160
greg@pegasusengineering.net
PROJECT INFORMATION:
Wetland Park Outfall Improvements
Tuskawilla Road at Cross Seminole Trail
Section 31, Township 20 South, Range 31 East, Seminole County, Florida
SCOPE OF WORK:
Provide surveying service to meet the Standards of Practice as outlined by the Florida Board of Professional Land
Surveyors in Chapter 5J-17 FAC, Section 472.027 of the Florida Statutes, to include the following:
Sketch & Description
1. Prepare new descriptions for two (2) proposed easement areas.
2. Prepare a Sketch of Description for recording in the Public Records of Seminole County.
DELIVERABLES:
Provide signed and sealed documents.
TIMELINE:
Anticipated delivery will be two (2) weeks after notice to proceed authorization and return of signed scope letter.
COMPENSATION:
Our fee for the above-referenced work will be as follows:
Sketch & Description $ 1100.00
PAYMENT:
Payment is due thirty (30) days from the date of the invoice.
438
Gregory Teague, P.E., CFM
Wetland Park Outfall Improvements
February 14, 2026
Page 2 of 2
We appreciate the opportunity to provide these surveying services to you.
Ryan Johnson, PSM
AUTHORIZATION:
If you agree with the terms outlined in this Scope of Work, please have an authorized person sign below and send to
rjohnson@reservegeo.com to serve as official notice to proceed.
I have read and accept the Scope of Work as outlined hereon.
Signature Date
Printed Name Title (if any)
439
(GAI Consultants)
440
GAI CONSULTANTS, Inc.
Change Order for Professional Services
03/2026 GAI_Pegasus_Wetland Park Change Order 001_Scope_and_Agreement_2026.doc
| 1 of 2
Project Number: R250349.00 Change Order Number: 001
Project Name: Wetland Park Outfall Improvements
Project Location (City, County, State): City of Winter Springs, Seminole County, Florida
The terms and conditions of the Agreement for Professional Services, dated April 8, 2025, (hereinafter referred to as
) between Pegasus Engineering, LLC, (h ) and GAI Consultants, Inc.
(GAI ) will govern the performance of the services described in this Change Order Number 001
(hereinafter referred to as CHANGE ORDER ).
Project Description: The Project Owner is proposing drainage improvements along the east side of the Cross Seminole Trail
to re-direct the existing discharge south towards the center of Wetland Park. Drainage improvements are also proposed along
the west side of Michael Blake Boulevard to convey stormwater runoff from the north end of Wetland Park to the existing
south outfall. GAI is providing wetland, listed species, and permitting support to the CLIENT.
Due to changes to the project design, withdrawal of the original permit application, and subsequent re-submittal of permit
applications, additional field work and agency coordination by GAI will be necessary to address regulatory agencies concerns
regarding the project.
GAI Scope of Services: GAI will perform the following services under this CHANGE ORDER.
GAI will conduct an additional field visit to refresh sections of the BDA wetland delineation not previously
reviewed by GAI and regulatory agency staff.
GAI will attempt to set three (3) Seasonal High-Water Elevations within the wetland. The location and elevation of
these points will need to be field-located by the Project Surveyor.
GAI will conduct and additional regulatory site visit with representatives of the St. Johns River Water Management
District (District). Should District staff require the location of flags to be field-adjusted, these new flag points will
need to be field-located by the Project Surveyor.
GAI will respond to District Request for Additional Information and assist the CLIENT with responding to District
RAI questions.
As noted above, changes to the wetland limits and the location and elevation of the SHWE points will need to be
field-located by the Project Surveyor.
Schedule: Pursuant to the provisions of the AGREEMENT between GAI and CLIENT, GAI shall commence work upon
receipt of a copy of this CHANGE ORDER executed by CLIENT. GAI shall endeavor to complete its services under this
CHANGE ORDER within 180 days, subject to excused delays
Compensation: Compensation for services rendered by GAI under this CHANGE ORDER shall be in accordance with the
rates agreed to and incorporated into the AGREEMENT between GAI and CLIENT.
under this CHANGE ORDER is $,.0. A breakdown by task is included on the attached Excel spreadsheet.
Assumptions and Understandings:
following assumptions and understandings:
1) Access to the project site(s) upon which GAI is to conduct its field work will be available to GAI personnel at the time
this CHANGE ORDER is authorized. All exploration locations shall be cleared of buried utilities/piping/structures by
Client.
2) CLIENT CHANGE ORDER at the time this CHANGE
ORDER is authorized.
3) CLIENT
information/topo information, etc. at the time this CHANGE ORDER is authorized. Unless otherwise noted, GAI may
rely upon such information.
4) CLIENT will give GAI prompt notice whenever it observes or otherwise becomes aware of any development that affects
441
GAI CONSULTANTS, Inc.
Change Order for Professional Services
03/2026 GAI_Pegasus_Wetland Park Change Order 001_Scope_and_Agreement_2026.doc
| 2 of 2
5) CLIENT will examine and provide comments and/or decisions with respect to any GAI interim or final deliverables
within a period mutually agreed upon.
6) Any of CLIENT
manner.
7) CHANGE
ORDER within 45 days. If authorization to proceed is not received within 45 days, GAI reserves the right to revise its
compensation.
REQUESTED AND AUTHORIZED BY OFFERED AND AGREED BY
PEGASUS ENGINEEERING, LLC GAI CONSULTANTS, INC.
By By
Printed Name Printed Name George T. Reese
Title Title Vice President
Date Date
Attachments: Breakdown of Compensation Specifications Drawings Other
END OF CHANGE ORDER
442
Manhour Calculations
GAI Consultants, Inc.
618 East South Street, Suite 700
Orlando, Florida 32801
GAI Project No: R250349.00
prepared by: DJ Silverberg
R250349.00-CO-001_MNHR-25C26_r23D26.XLSX
revised 23-Apr-26
PROJECT SENIOR ENVIRON. PROJECT ENVIRON. ENVIRONMENTAL DRAFTING/ SR. PROJECT
TASK PRINCIPAL MANAGER SPECIALIST SPECIALIST SPECIALIST GRAPHICS COORDINATOR CLERICAL TOTALS
Ecological Assessment/Permit Coordination Hrs Rate Cost Hrs Rate Cost Hrs Rate Cost Hrs Rate Cost Hrs Rate Cost Hrs Rate Cost Hrs Rate Cost Hrs Rate Cost Hrs Cost
1.1 Conduct Additional Site Review to Refresh Flags 0 190.00 0.00 0 190.00 0.00 5 190.00 950.00 4 105.00 420.00 0 105.00 0.00 0 105.00 0.00 0 85.00 0.00 0 60.00 0.00 9.0 $1,370.00
1.2 Set Seasonal High Water Elevations 0 190.00 0.00 0 190.00 0.00 4 190.00 760.00 4 105.00 420.00 0 105.00 0.00 0 105.00 0.00 0 85.00 0.00 0 60.00 0.00 8.0 $1,180.00
1.3 Schedule/Conduct Additional Site Review with SJRWMD 0 190.00 0.00 0 190.00 0.00 5 190.00 950.00 3 105.00 315.00 0 105.00 0.00 0 105.00 0.00 0 85.00 0.00 0 60.00 0.00 8.0 $1,265.00
1.4 Prepare Responses to RAIs 0 190.00 0.00 8 190.00 1520.00 0 190.00 0.00 0 105.00 0.00 0 105.00 0.00 2 105.00 210.00 0 85.00 0.00 0 60.00 0.00 10.0 $1,730.00
1.5 Coordination with Client and Owner 0 190.00 0.00 2 190.00 380.00 0 190.00 0.00 0 105.00 0.00 0 105.00 0.00 0 105.00 0.00 0 85.00 0.00 0 60.00 0.00 2.0 $380.00
Subtotal 0 0.00 10 1900.00 14 2660.00 11 1155.00 0 0.00 2 210.00 0 0.00 0 0.00 37.0 $5,925.00
TOTAL 0 0.00 10 1900.00 14 2660.00 11 1155.00 0 0.00 2 210.00 0 0.00 0 0.00 37 $5,925.00
Reimbursables Task 1.1 $5,925.00
Document Reproduction 0.00 0.00 $70.90
Mileage 2 trips to site (42mi. x 2 x 0.725)60.90 60.90 $5,995.90
Tolls 10.00 10.00
Reimbursable totals 70.90 Fees $70.90
Salary $5,925.00
Total $5,995.90
Total Labor Cost
Reimbursable Cost
Total Project Cost
Change Order 001
Wetland Park Outfall Improvements
443
(Florida Bridge & Transportation)
444
Florida Bridge and Transportation, Inc.
Structural Engineers
633 Dartmouth Street * Orlando, FL 32804 * Phone (407) 513-9709 * Fax (407) 513-9712
April 27, 2026
Mr. Greg Teague, P.E.
Pegasus Engineering
301 West SR 434, Suite 309
Winter Springs, FL 32708
RE: Structural Design and Plan Sheet for Sheet Pile Wall
Wetland Park Outfall, City of Winter Springs
Proposal for Structural Design Services
FBT Project Number 23-58.01
Dear Greg:
Florida Bridge and Transportation, Inc. (FBT) is pleased to submit this proposal to PEGASUS
for engineering services for the above referenced project. The scope of design services for this
work order includes the following:
1) Design and Plan Production: FBT will provide the structural design and plan sheets for
the proposed sheet pile walls per the concept shown in the plan provided by Pegasus. It is
assumed the sheet pile walls will be cantilever walls (not braced or anchored). FBT will
provide design and details for the sheet pile and the concrete coping with railing. The
railing will be a standard railing from FDOT Standard Indexes and no custom
modifications are included. It is assumed the exposed portions of the sheet pile will be
coated with standard coal tar epoxy (black), and special coating systems and colors will
not be required. Wall control drawings will not be provided (wall geometry will be
shown in Pegasus’ plans). The plans and calculations will include one custom design with
details for the “short sheets” which will be required to span across an obstruction such as
a utility or other buried element.
2) Meetings, Specifications and Cost Estimates: FBT will attend one status meeting (if
required) with the City staff and Pegasus. The project specifications will consist of the
FDOT Standard Specifications for Road and Bridge Construction, and supplemental
specifications are not anticipated or included. FBT will provide one estimate of probable
construction cost for the structural items. FBT will assist Pegasus develop a bid schedule
for the structural items.
3) The project deliverables will consist of 100% and signed and sealed “final” plans and
structural calculations. We understand the final deliverables may include 24x36 sheets.
The reprographic cost for FBT’s portion of the project is included in the fee below.
We propose a total lump sum fee of $15,000.00 for all FBT's basic structural engineering
services indicated above. The work will be invoiced monthly on a percent complete basis. If the
work is stopped by PEGASUS or others for any reason before completion, FBT will be
reimbursed for the hours expended up to that point at an average hourly rate of $165 per hour.
445
Greg Teague
April 27, 2026
Sheet 2 of 2
FBT Winter Springs Outfall Sheet Pile Proposal 4-27-26
The scope and fee indicated above does not include the following services:
• Braced or anchored wall design and details
• Reinforcing steel bar list for the concrete coping
• Design and detailing of custom railing (other than standard FDOT railing)
• Development of site plans, permitting, utility coordination, etc.
• Design or analysis of a coating system or corrosion protection
• Post design services
• Development of As-Built or Construction Record Drawings
• Construction inspection or observation of on-going or completed construction
The items indicated above, or any other services not included in the basic scope of design
services described above, may be provided for an additional fee. A supplemental agreement
must be negotiated prior to the additional work being performed by FBT. Additional services
required for this project may be provided based on an addendum to this agreement. Fees for
additional services will be addressed on a case by case basis.
In order for FBT to perform these services, we will need the following information from others:
• Site layout showing overall geometry with top of wall and existing/proposed grades on
low side of wall
• Survey at the walls including elevations, contours and topo
• Geotechnical field work and design recommendations
This proposal will become invalid if not executed within 90 days. We are prepared to commence
the structural design services upon receipt of written notice to proceed.
Very truly yours,
Florida Bridge and Transportation, Inc.
Mark Niedermann, P.E.
Senior Vice President
446
WETLAND PARK OUTFALL IMPROVEMENTS AT THE
CROSS SEMINOLE TRAIL AND MICHAEL BLAKE BOULEVARD
CHANGE ORDER #3 – FINAL DESIGN AND PERMITTING SERVICES
Relevant SJRWMD
Correspondence
447
March 10, 2026
Clete Saunier
City of Winter Springs
400 Old Sanford Oviedo Rd
Winter Springs FL 32708-2617
Sent via email: csaunier@winterspringsfl.org
Re: Wetland Park Outfall Improvements at the Cross Seminole Trail and Michael Blake
Boulevard
Application Number 22437-10
(Please reference the application number on all correspondence.)
Dear Mr. Saunier:
The St. Johns River Water Management District (District) has received your Individual
Environmental Resource Permit application. Upon review of the proposed project, the following
technical information is needed to sufficiently review the application. This information is being
requested under the authority granted to the District by sections 373.413(2) and 373.4131,
Florida Statutes (F.S.), and rules 62-330.054, 62-330.060, 62-330.301 and 62-330.302, Florida
Administrative Code (F.A.C.).
In order to expedite the review of your application, please use the application number
referenced above and respond electronically through e-Permitting at sjrwmd.com/permitting or
submit all requested information to the District.
1. The application fee for a project less than 10 acres with less than 1 acre of work in, on,
or over wetlands or other surface waters is $1190. Please submit the required
application fee online or by check made payable to the St. Johns River Water
Management District. [62-330.071, F.A.C.; 40C-1.603, F.A.C.]
2. It appears a portion of the project is occurring within property owned by the Trustees of
the Internal Improvement Trust Fund (TIITF) of the State of Florida. Please submit
documentation as described under 4.2.3(d), Applicant’s Handbook, Volume I, such as a
recorded deed or easement or a redacted contract that demonstrates the applicant’s real
property interest over all land upon which the proposed activities will be conducted. [62-
330.060(3), F.A.C.]
3. Thank you for providing on your plans the jurisdictional wetland and other surface water
boundaries and all proposed wetland and other surface water impact areas. In addition,
please include on the plans the total acreage of all unimpacted onsite wetlands that
matches the environmental assessment. [62-330.060(2), F.A.C., 62-330.301(1)(d)(f),
F.A.C.; 10.0 – 10.3, A.H. Vol I]
448
Wetland Park Outfall Improvements at the Cross Seminole Trail and Michael Blake Boulevard
March 10, 2026 22437-10
Page 2 of 5
4. Please provide detailed drawings on the construction plans showing typical cross-
section plans of all areas to be developed adjacent to wetlands (lots, roads, and
stormwater ponds, etc.). Please include in the cross sections the wetland limits, upland
buffers, limits of construction (including the back slope of any proposed fill), property
boundary, dimensions, slopes, existing and proposed elevations, locations of any
proposed fencing and signage, and the location of erosion control measures.
Additionally, please provide cross sections of:
a. CS-06 out to the wetland
b. From the road through MB-06 and out to wetland.
[62-330.301, 62-330.302, F.A.C.; Section 10.0, A.H. Vol. I]
5. Please provide further details regarding the current condition of the temporary impact
areas (CST-01) and how the area will be restored and monitored post-restoration to
ensure the system is not degraded by the proposed impacts (before and after
topographic surveys, vegetative monitoring, replanting of forested systems, etc). Please
note, mitigation may be required for the temporal loss of function to forested systems if
they are proposed for temporary impact. If temporary forested impacts are proposed,
please include the location and acreage on the drawings and revise the UMAM and
mitigation plan to account for these impacts. [62-330.301, 62-330.302, F.A.C. and 10.0
A.H.
6. An applicant must provide reasonable assurances that a regulated activity will not cause
adverse secondary impacts to the water resource. Secondary impacts to wetlands and
surface waters from adjacent development will not be considered adverse if upland
buffers are maintained with a minimum width of 15 feet and an average width of 25 feet.
To qualify under 10.2.7 A.H., the upland buffers must be undisturbed except for drainage
structures and provide a conservation easement or other means of ensuring the buffers
will remain undisturbed during construction and use of the facilities. Mitigation will be
required for all secondary impacts that cannot be avoided.
a. Currently, the work being performed on the northern section of Michael Blake
Blvd appears to be less than 15 feet from the flagged wetland line (at flag W1-38
for example). Once the site visit is complete and a final wetland line has been
approved, please demonstrate the project meets the above criteria or apply
secondary impacts as appropriate.
[62-330.301(1)(f), F.A.C.;10.2.7, A.H. Vol I]
7. Please demonstrate that the project, as proposed, will not adversely affect the wetlands
to be preserved. Provide the elevation of the wet season water levels within the wetlands
to be preserved and discuss the methodology used to determine those elevations. An
adverse hydrologic impact to the wetlands will be considered a direct impact and must
meet the criteria for elimination and reduction of impacts and mitigation. [62-
330.301(1)(a)(b)(d), F.A.C.; Section 10.2.2.4, A.H. Vol. I]
8. During the June 11, 2025 site visit, only a portion of the flagged wetland line was
reviewed. Please contact Brian Silverman at Bsilverman@sjrwmd.com to schedule a site
449
Wetland Park Outfall Improvements at the Cross Seminole Trail and Michael Blake Boulevard
March 10, 2026 22437-10
Page 3 of 5
visit to review the remaining flagged wetland boundaries and evaluate the seasonal high
water elevations in the on-site wetlands or other surface waters. Please note that if staff
determines that additional wetlands or other surface waters will be impacted, additional
environmental information may be needed, and the project must meet the review criteria
as described in Section 10.0 of the Applicant’s Handbook (Environmental Criteria). [62-
330.301, F.A.C., 62-330.302, F.A.C.; 10.0 A.H. Vol I]
9. If the wetland or surface boundaries are changed during the site inspection or if new
wetlands are identified, please update the environmental report and the signed and
sealed construction plans to reflect the revised wetland line, the location and acreage of
all wetlands and other surface waters, as well as the location and acreage of all wetland
and other surface water impacts, both direct and secondary. [62-330.060(2), 62-
330.301(1)(d)(f), F.A.C.; Section 10.0 – 10.3, A.H. Vol. I]
10. Mitigation will be required for all direct and secondary wetland impacts. The applicant is
proposing mitigation via the purchase of credits at a mitigation bank. After the wetland
impacts and UMAM scores have been approved, please provide a complete mitigation
plan including the proposed bank, the type of credits proposed, and the number of
credits proposed. Once the mitigation plan is approved, please a provide a letter from
the mitigation banker verifying the number of credits that have been reserved, sold or
transferred to the permit applicant and requesting that the credits be withdrawn from the
bank upon the issuance of the applicant’s District permit. Please do not purchase or
reserve credits before the District approves a mitigation plan. [10.3.1 A.H., Vol. 1 and 62-
330.301 and 62-330.302, F.A.C.] The letter should include:
a. Project Name and Permit/Application Number
b. Number of credits reserved, sold, or transferred
c. Type of credits reserved, sold, or transferred
d. Phase the credits are to be withdrawn from
e. Basin the credits are to be withdrawn from
11. According to Audubon Florida Eagle Watch Nest Map a bald eagle nest (SE096) is
located on site just south of the proposed discharge structures on the Cross Seminole
Trail. Please conduct a survey in accordance with the USFWS Bald Eagle Monitoring
Guidelines to determine the current status of the nest and submit this survey to the
district. Please note that your project may not result in the unauthorized taking of a listed
species and if the nest is occupied/active in the current season, you may be required
modify your activities or the timing of certain activities within 330 ft and 660 feet of the
nest, in accordance with USFWS National Bald Eagle Management Guidelines. Please
demonstrate the project meets the guidelines or provide comments from the appropriate
agencies that there will be no adverse impacts to bald eagles. [10.2.2 and 10.2.7, A.H.
Vol I]
12. Please be advised that a copy of your permit application has been forwarded to the
Florida Fish and Wildlife Conservation Commission (FWC) for review regarding your
project’s potential effects on fish and wildlife, listed species and their habitat. Additional
information or modifications to the plans may be requested following receipt of their
comments. Please note that an applicant must provide reasonable assurances that a
regulated activity will not impact wetland and other surface water functions and cause
adverse impacts to the habitat of fish, wildlife, and listed species or to the abundance
450
Wetland Park Outfall Improvements at the Cross Seminole Trail and Michael Blake Boulevard
March 10, 2026 22437-10
Page 4 of 5
and diversity of fish, wildlife and species having special protection that use upland
habitats for nesting and denning. [10.2.2, 10.2.8, A.H.]
13. Calculations Tables 4 and 5 (pgs. 155 & 156/372) do not appear to include peak stage
or discharge data for the “OUTFALL” node. Please provide data for the system outfall in
the tables. [62-330.060, 62-330.301(1)(a)(b)(c), F.A.C.; Part 3 A.H. Vol II]
14. Calculations Table 4 (Pg. 155/372) appears to indicate that the system stages above
critical elevations at several locations in the proposed conditions. Please clarify and
demonstrate that the proposed project will not result in adverse water quantity or quality
impacts. [62-330.060, 62-330.301(1)(a)(b)(c)I, F.A.C.; Part 3 A.H. Vol II]
15. Calculations Table 7 appears to demonstrate that peak discharge from the outfall in the
proposed condition exceeds previously permitted discharge rates for the mean annual
storm event. Please clarify and demonstrate that the proposed project will not result in
adverse water quantity or quality impacts. [62-330.060, 62-330.301(1)(a)(b)(c)I, F.A.C.;
Part 3 A.H. Vol II]
16. Please demonstrate that the project meets the applicable nutrient performance criteria in
Sections 8 and 9, A.H. Vol. I. [62-330.060, 62-330.301I, F.A.C.; Sections 8, 9, A.H. Vol.
I]
Please note, per District rules, you have 90 days to respond to this RAI letter. An automated
courtesy reminder email will be sent to you on day 80 if you have not yet submitted a formal
response to this RAI letter.
Please be aware, suggestions or other direction provided by District staff are offered to assist
applicants in complying with District rules. However, applicants bear the burden of
demonstrating that their application meets the applicable rule requirements. Although District
staff may provide suggestions to applicants that would allow staff to recommend approval of an
application to the District’s Executive Director or 4elegate, the final decision regarding the
approval of a permit application is up to the District’s Executive Director or 4elegate. If an
application is recommended for substantive denial, the application will be scheduled for
consideration by the District’s Governing Board. Applicants are hereby advised the Governing
Board and the Executive Director or 4elegate are not bound by previous statements or
recommendations of District staff regarding an application.
If the applicant desires to dispute the necessity for any information requested on an application
form or in a letter requesting additional information, he or she may, pursuant to section
373.4141, F.S, and section 5.5.3.6, Environmental Resource Permit Applicant’s Handbook
Volume I (ERP A.H. Volume I) request that District staff process the application without the
requested information. If the applicant is then unsatisfied with the District’s decision regarding
issuance or denial of the application, the applicant may request a section 120.569, F.S. hearing
pursuant to chapter 28-106 and rule 40C-1.1007, F.A.C.
Please be advised that under section 5.5.3.5, ERP A.H. Volume I, the applicant has 90 days
from the date the District makes a timely request for additional information to submit that
information to the District. If an applicant requires more than 90 days to respond, it must notify
the District in writing of the circumstances, at which time the application shall remain in active
status for one additional period of up to 90 days. The District will grant additional extensions for
451
Wetland Park Outfall Improvements at the Cross Seminole Trail and Michael Blake Boulevard
March 10, 2026 22437-10
Page 5 of 5
good cause shown by the applicant. A showing that the applicant is making a diligent effort to
obtain the requested additional information, and that the additional time period is both
reasonable and necessary to supply the information will be considered good cause. In such
case, the District will grant a specified amount of additional time.
If the applicant chooses not to, or is unable to, respond to the request for additional information
within the above time frames, the application will be administratively denied. An administrative
denial is not a determination of the merit of an application and does not preclude the applicant
from reapplying at a later time. However, the applicant will not receive a refund of processing
fees submitted, and the District will not apply those processing fees to a subsequently submitted
permit application or notice. If an applicant cannot provide the information within the applicable
time frames, the applicant may wish to withdraw the application in accordance with section
5.5.3.7, ERP A.H. Volume I. Please note, pursuant to Rule 62-330.020(2), F.A.C., no
construction may begin on the proposed project until a permit is issued by the District.
If you have any questions, please contact Brian Silverman, at (407) 215-1451 or by e-mail:
Bsilverman@sjrwmd.com and Anthony Young, at (407) 215-1470 or by e-mail:
AJYoung@sjrwmd.com .
Sincerely,
Brian Silverman
Regulatory Scientist II
Division of Regulatory Services
Anthony Young
Senior Professional Engineer
Division of Regulatory Services
C: Regulatory File
Gregory Teague; Pegasus Engineering
Sent via Email: greg@pegasusengineering.net
Don J. Silverberg; GAI Consultants
Sent via email: D.Silverberg@gaiconsultants.com
452