HomeMy WebLinkAbout2026 04 13 Consent 300 - Approval of Sewer Main Lining Project (Galloway Drive and Sheoah Blvd)CONSENT AGENDA ITEM 300
CITY COMMISSION AGENDA | APRIL 13, 2026 REGULAR MEETING
TITLE
Approval of Sewer Main Lining Project – Galloway Drive and Sheoah Boulevard
SUMMARY
The Utility Department requests City Commission approval for expenditures associated
with a necessary sewer main lining project located in the area of Galloway Drive and
Sheoah Boulevard. The project will involve the rehabilitation of approximately 2,991
linear feet of existing 8-inch clay pipe.
During routine preventative maintenance, Utilities staff identified multiple defects
within this portion of the system that require corrective action. Addressing these
deficiencies through sewer main lining will improve system integrity, reduce the risk of
future failures, and extend the overall service life of the infrastructure.
Additionally, completing this rehabilitation work in advance will support and protect the
upcoming Sheoah Boulevard paving project by ensuring the underlying sewer system is
in good condition prior to roadway improvements.
The proposed work will be performed utilizing a piggyback agreement with a
competitively procured contract, in accordance with the City’s procurement policies.
This approach allows the city to expedite the project while ensuring cost-effectiveness
and compliance with applicable purchasing requirements.
FUNDING SOURCE
Total project cost will be funded via the Utilities FY26 budget GL# 410-36-3600-560650-
006 Construction in Progress Pipe Relining Sewer.
RECOMMENDATION
The Utility Department requests that City Commission approve the sewer lining project
and authorize the use of Atlantic Pipe Services for a total amount of $195,386.79.
4
FLORIDA'S COMMERCIAL PIPELINE CLEANING, INSPECTION AND REHAB SPECIALIST
1420 Martin Luther King Jr Blvd
Sanford, FL 32771
(407) 792-1360
info@atlanticpipe.us
PROPOSAL 12152
CUSTOMER: CITY OF WINTER SPRINGS
STREET: 1126 East State Road 434
CITY/STATE/ZIP: Winter Springs, FL, 32708
ATTN: Rory Jacobs
PHONE: 407-222-5087
JOB NAME: Galloway System CIPP Proposal
JOB LOCATION: , Winter Springs, FL,
E-MAIL:rjacobs@winterspringsfl.org
DATE: 03/17/2026
QUANTITY DESCRIPTION UOM RATE TOTAL
Seq: 8" CIPP
500.00 500.00EAA-1 Inspection & Cleaning Mobilization (1 per project area) 1.00
3,541.00 3,541.00EAA-2 CIPP Rehabilitation Mobilization (1 per project area) 1.00
9,421.65 3.15LFB-2 CCTV Inspection and Light Cleaning 8" - 12" diameter 2,991.00
19,029.12 12.72LFB-17 Tuberculation Removal 8" - 12" diameter 1,496.00
131,424.54 43.94LFD-13 Mainline CIPP 8" diameter 6.0mm 2,991.00
11,331.20 354.10EAG-1 Lateral Service Reinstatement 32.00
2,139.28 1.43LFK-8 Bypass Services: Mainline CIPP Installation Operation 1,496.00
18,000.00 2,250.00DYSL-2 Maintenance of Traffic: Flagmen (2 required, 8 hr min) 8.00
TOTAL 195,386.79
ANY UNFORSEEN OR ABNORMAL PIPELINE OR SITE CONDITIONS WILL BE SUBJECT TO RENEGOTIATION WITHOUT
PENALTY TO APS
Page 1 of 45
PROPOSED RATES MAY CHANGE BASED UPON THE FOLLOWING CONDITIONS:
1) Calls Outs of less than 1000 LF of readily available pipeline may be billed at the hourly rate, with a 4 hour minimum.
Any time on site beyond the minimum may be billed at the hourly rate
2) Emergeny Call Outs will be subject to increased rates.
3) Heavy Cleaning encountered will be performed at an hourly rate , unless otherwise specified
4) Travel Time charges are assessed on a job by job basis
5) Atlantic Pipe Services provides, free cloud downloads for videos and reports. Hard Copy Reports with DVD or USB may
be purchased at $75.00 per set.
6) Safety Training / Orientation required for projects will be charged at the hourly rate per unit on site
7) Due to rising costs of fuel and overall expenses , additional fees must be assessed. These pass-through costs are
assessed through daily charges, per piece of equipment on site.
Atlantic Pipe Services is comitted to providing the same responsiveness , turn around time and quality of work that our
valued customers have become accustomed to . APS has invested in technologies that allow us to be more efficient with
operations and save on costs, however the extreme volatility within the fuel market is something we cannot control. This
additional charge helps APS cover increased costs , as well as maintain the same level of service.
1420 Martin Luther King Jr Blvd
Sanford, FL 32771
(407) 792-1360
info@atlanticpipe.us
1. Pricing based on Gainesville Regional Utilities, Sanitary Sewer Line and Manhole Rehabilitation Services Contract No .
2024-083-A.
2. Pricing will be based on actual field measurements center of manhole to center of manhole per contract .
3. Price quoted does NOT include point repairs prior to/after installation.
4. Liner(s) to be installed per ASTM 1216 and manufacturer’s specification.
5. Others to dewater/bypass flows from force mains for duration of installation (If required).
6. Others to provide reasonable access to line(s) to be rehabilitated.
7. Pricing includes Temporary Traffic Control, limited to 36inch Cones and Construction Ahead Signs .
We propose to hereby furnish the following:
FLORIDA'S COMMERCIAL PIPELINE CLEANING, INSPECTION AND REHAB SPECIALIST
Page 2 of 46
1420 Martin Luther King Jr Blvd
Sanford, FL 32771
(407) 792-1360
info@atlanticpipe.us
Heavy
Cleaning
Rates
Heavy Cleaning determined by percentage of debris in pipeline
12" Diameter
15" Diameter
18" Diameter
24" Diameter
30" Diameter
36" Diameter
42" Diameter
48" Diameter
54" Diameter
60" Diameter 10.00%
10.00%
15.00%
15.00%
20.00%
20.00%
20.00%
20.00%
25.00%
25.00% 3"
4"
4"
5"
6"
7"
6"
7"
5"
6"
Debris
Debris
Debris
Debris
Debris
Debris
Debris
Debris
Debris
Debris
In the event the required cleaning is beyond normal Heavy Cleaning,
the cleaning will be performed under an hourly rate. Subject to prior
client notification and approval.
CUSTOMER RESPONSIBILITIES
Local Dump-Site for safe disposal of debris / waste material
removed from Project Location
Local Metered Water Source
Exposure of structures and access to all work areas without
delay
Stabilized Access to Work Areas - Two Wheel Drive Accessible
Access to secure site for equipment storage
Maintenance of Traffic - If Applicable
CUSTOMER RESPONSIBILITIES
Delays experienced outside of APS's direct control will be
subject to an hourly charge for each unit on site
Weekend and Night Work may be subject to increase rates
Any unforeseen or abnormal pipe / site conditions will be
subject to renogotiation without penalty to APS
Payment terms are NET 30 days of invoice date. APS does not
agree to "Pay when paid" terms
APS Proposals are valid for 30 days from date of submission.
X
X
X
X
X
ATLANTIC PIPE SERVICES, LLC
PRINT NAME / TITLE
SIGNATURE
DATE
CUSTOMER
PRINT NAME / TITLE
SIGNATURE
DATE
Acceptance of Proposal : The above prices, specifications and conditions are satisfactory and are hereby accepted. You are
authorized to perform the work specified. Payment will be made as outlined.
3/17/2026
FLORIDA'S COMMERCIAL PIPELINE CLEANING, INSPECTION AND REHAB SPECIALIST
Page 3 of 4
Jose Molina / Lining Manager
7
ATLANTIC PIPE SERVICES, LLC
STANDARD TERMS & CONDITIONS OF BUSINESS
COMPANY: Atlantic Pipe Services, LLC, a Florida Limited Liability Company, whose address 1420 Martin Luther King Jr. Blvd, Sanford, Florida, 32771
(Hereinafter referred to as "APS")
CUSTOMER: Any corporation, company, organization, agent or individual entering into a written agreement with APS for the provision of services or materials
or any other business dealing, for which payment is agreed with or becomes due and payable to APS (hereinafter referred to as "Customer")
PROPOSAL & QUOTATION: All proposals or quotations provided by APS must be in writing and signed by an authorized representative of the company to be
valid and any such proposal or quotation is valid for acceptance within 30 days of the respective proposal date, unless agreed otherwise in writing.
PAYMENT TERMS: Payment of all invoices is due within 30 days from the invoice date, unless terms are agreed otherwise, in writing from APS. Any Dispute or
query regarding the invoiced amount must be communicated in writing within 10 days (objection period) from the invoice date and customer will be deemed to
have accepted the invoice as delivered and all services / work standards relating thereto, unless objected to in writing within the objection period. Customer
agrees that no retainage will held for all services performed.
REMEDIES FOR NON-PAYMENT: All sums not paid when due will bear interest at the rate of 1.5% per month from due date until paid or the maximum legal
rate permitted by law, whichever is less. In the event of legal action being deemed necessary to enforce payment, APS shall be entitled to all costs of collection,
including a reasonable attorney's fee. In addition, if the customer fails to make payment to APS as herein provided, then APS may stop work without prejudice
to any other remedy it may have. The parties further agree that in the event of any controversy arising between them, then in such event, the State Courts of
Seminole County, Florida, shall be the forum in which the parties agree to try and have heard any matters of litigation arising out of such controversies.
WARRANTIES: All workmanship and materials are guaranteed against defects in workmanship for a period of one year from the date of substantial completion
of the project. This warranty is in lieu of all other warranties, expressed or implied, including any warranties of merchantability of fitness for a particular purpose.
APS will not be responsible for damage to its work by other parties or normal wear and tear. Any repair work necessitated by caused damage will be considered
as an order for extra work.
INDEPENDENT CONTRACTOR: Both APS and the customer agree that APS will act as an independent contractor in the performance of its duties under this
contract. Accordingly, APS shall be responsible for payment of all taxes, including Federal, State, and local taxes arising out of APS's activities, including by
way of illustration but not limitation, Federal and State income tax, social security tax, Unemployment Insurance taxes, and any other taxes.
UNFORESEEN OCCURRENCE: In the event that any unforeseen occurrences or conditions are encountered after the work has commenced and which APS
judge, at their sole discretion, to significantly affect or may affect the services, the risk involved in providing the services or there being a material change to the
proposed or quoted scope of services, APS may a) Immediately cease work without liability to the customer, or b) renegotiate with customer to change the
scope of work with price adjustment or change order, or c) Apply downtime /hourly or day rates until occurrence or condition is resolved to the satisfaction of
APS.
DOWNTIME/STOPPAGES/ADDITIONAL WORK: In the event that APS is unable to work or encounter stoppages due to circumstances beyond their control or
unforeseen circumstances or occurrences, particularly any underground structure problems causing delay or stoppage of work or in the event of any work being
required beyond the quoted scope of work, then an hourly or daily rate will be charged, subject to prior customer notification in writing from APS.
PROJECT ESTIMATES: APS may from time to time provide written estimates of projected timescale or hours for a particular project at customer request,
however, this in no way binds APS to a final timescale for the services to be provided. The actual hours will be determined by specific site requirements and
operational demands, which cannot be wholly determined due to the nature of the services provided by APS.
CUSTOMER PURCHASE ORDERS: In the event that the customer chooses to issue a purchase order, whether verbal or in writing, such purchase order shall
be governed by APS Standard Terms & Conditions of Business as detailed herein and any such client agreement cannot change the payment terms under any
circumstances unless specifically agreed to in writing APS and such agreement being authorized and signed by the owner or director of APS. In the event of
any inconsistency between the APS terms and conditions as detailed herein and the terms of a service order, the APS terms and conditions shall prevail. In any
event, settlement of all APS correctly submitted invoices must be made within 30 days from invoice date, irrespective of customer having received payment
from their respective customer.
CONTRACT ACCEPTANCE: In the event that the client fails to sign acceptance of an APS proposal or quotation, due to oversight by either or both parties or
any other reason and the services are commenced or completed on the clients written or verbal instruction due to emergency, urgency or some other reason,
then these terms and conditions will be deemed to have been accepted by the client as if such proposal or quotation had been signed.
DISCLAIMER: APS shall perform any and all repairs (e.g sag removal, rerounding, grouting, sectional CIPP, internal joint seals, mechanical repair sleeves,
CIPP, coatings,) services on a best-effort basis and makes no representations or warranties, express or implied, regarding the success or effectiveness of such
services. Billing shall be due and payable regardless of the outcome of the sag removal process. APS shall not be held liable or responsible for any damage,
deformation, failure, or other adverse effects that may occur to the pipeline as a result of the sag removal attempt. Furthermore, APS shall bear no responsibility
or liability for any costs, damages, or liabilities arising from dig-ups, excavations, or other activities outside of APS’s control. The client agrees to indemnify,
defend, and hold harmless APS, its officers, employees, and subcontractors from and against any and all claims, damages, losses, or expenses (including
attorney’s fees) arising out of or related to the sag removal work, except to the extent caused by APS’s sole gross negligence or willful misconduct.
CUSTOMER RESPOSIBILITIES: The customer will normally provide the following services, at no cost to APS for the duration of the project, unless agreed
otherwise in writing by APS, a)Approved dumpsite and disposal for all materials to be removed from site of work, b) Access and exposure of all structures for
APS personnel and equipment without delay, c) All temporary site facilities including suitable storage space for equipment, d)Any special permits and/or
licenses, without delay, e) Supply and access to all water required for the project with meter if applicable. f)Work areas prepared and accessible, without delay,
to enable the services to be provided, g) Authorized representative of the customer at the site of work, at all times services are being performed and with
authority to accept the services as completed and / or hours worked and h) Location and exposure of all manholes in the project area.
Page 4 of 48
Location of Lining
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
City of Gainesville, d/b/a
Gainesville Regional Utilities (GRU)
Atlantic Pipe Services, LLC
Contract# 2024-083-A
CONTRACT BETWEEN THE CITY OF GAINESVILLE, d/b/a
GAINESVILLE REGIONAL UTILITIES,
AND ATLANTIC PIPE SERVICES, LLC.
FOR
SANITARY SEWER LINE & MANHOLE REHABILITATION SERVICES
THIS CONTRACT is made and entered into with an effective date of November 1, 2024, by and between
the CITY OF GAINESVILLE, a Florida municipal corporation d/b/a GAINESVILLE REGIONAL UTILITIES (“GRU”),
with offices located at 301 S.E. 4th Avenue, Gainesville, Florida 32601, and ATLANTIC PIPE SERVICES, LLC, a Florida
limited liability company (“CONTRACTOR”), with its principal place of business at 1420 Martin Luther King Jr. Blvd.,
Sanford, FL 32771, individually referred to as “Party” or collectively as “Parties.”
WHEREAS, GRU requires Sanitary Sewer Line & Manhole Rehabilitation Services; and
WHEREAS, GRU issued a Solicitation on August 8, 2024 for Sanitary Sewer Line & Manhole Rehabilitation
Services; and
WHEREAS, CONTRACTOR submitted a Response dated August 30, 2024 to provide Sanitary Sewer Line &
Manhole Rehabilitation Services; and
WHEREAS, GRU desires to enter into a Contract for the services described herein.
NOW, THEREFORE, in consideration of the covenants contained herein, the Parties agree to the following:
The CONTRACTOR shall provide Sanitary Sewer Line & Manhole Rehabilitation Services as
detailed in the Technical Specifications (ATTACHMENT ) in accordance with the General Terms and
Conditions, and Supplemental Conditions.
GRU shall pay the CONTRACTOR for the faithful performance of this Contract according to the unit
pricing set forth in schedule attached hereto (ATTACHMENT ) on individual line items on an as
needed basis. Adjustments to price may be requested by the CONTRACTOR at least sixty (60)
calendar days prior to the anniversary date of this Contract each year. Any negotiated price changes
shall become effective on the anniversary date of that calendar year. CONTRACTOR shall provide
documentation for any such price increase and the price increase percentage shall not exceed the
Producer’s Price Index (PPI) for the product during the previous twelve calendar months as
published by the U.S. Department of Labor, Bureau of Labor Statistics.
The term of this Contract shall commence upon execution and terminate on October 1, 2027. This
Contract may be extended for two (2) 1-year extensions, upon mutual agreement of the Parties.
Beyond the extensions described above, this Contract may be extended for an additional six (6)
months to allow for completion of a new solicitation.
[Signatures on following page]
26
City of Gainesville, d/b/a
Gainesville Regional Utilities (GRU)
Atlantic Pipe Services, LLC
Contract# 2024-083-A
Page 2 of 13
IN WITNESS WHEREOF, the Parties hereto have executed this Contract on the date first above written.
ATLANTIC PIPE SERVICES, LLC CITY OF GAINESVILLE d/b/a
GAINESVILLE REGIONAL UTILITIES
BY: BY:
Allan Cagle Thomas Brown
President Chief Operating Officer
Date:_________________________ Date:__________________________
By: ___________________________
Debbie Daugherty
Water Wastewater Officer
Date:__________________________
Approved as to Form and Legality:
David Schwartz
Assistant City Attorney
Date: _________________________
Procurement Representative:
Prepared By: Annie Velez
Procurement Specialist III
27
Page 3 of 13
GENERAL TERMS AND CONDITIONS
1.1. DEFINITIONS
Agreement: A written Contract between two or more Parties [“GRU” and “Contractor”]. “Contract” and
“Agreement” are synonymous.
Deliverable: The completion of a milestone or the accomplishment of a task associated with the Work.
Free on Board (FOB) Destination: The Contractor is responsible for delivery of materials to a specified delivery
point. The risks of loss are borne by the seller or consignee. Title passes when delivery is received by the
buyer at destination. Seller has total responsibility until shipment is delivered.
Specification: A description of the physical or functional characteristics of goods or services as defined in the
Solicitation.
Work: Activity involving effort done in order to achieve a purpose or result requested in the scope.
1.2. COMPLIANCE WITH REFERENCED SPECIFICATIONS
All Work, materials, systems, or operations specified by reference to standard trade or manufacturer’s published
specifications shall comply with the requirements, except as modified by this Contract. The specifications used must
be the latest published edition that is in effect on the effective date of this Contract unless a particular edition is
specified. In the event of a conflict, the specifications that contain the more stringent requirements will govern.
1.3. CHANGE ORDERS
a) GRU shall pay Contractor for the Work at the price[s] stated in this Contract. No additional payment will be made to
Contractor except for additional Work or materials stated on a valid change order, and issued by GRU prior to the
performance of the added Work or delivery of additional materials. A change order may be issued without invalidating
the Contract, if a) made in writing; b) signed by the authorized representative(s), and c) accepted by Contractor.
b) Such change shall include the following: change orders that constitute changes: a) the general scope of Work, b)
the schedule, c) administrative procedures not affecting the conditions of the Contract, or d) the Contract price.
1.4. NOTICES.
Notices to Contractor shall be deemed to have been properly sent when delivered to Contractor physical address and
email. Notices to GRU are deemed to have been properly sent when emailed to purchasing@gru.com, mailed to P.O.
Box 147117 Station A105, Gainesville, FL 32614 or delivered to Utilities Procurement Department, 301 SE 4th
Avenue, Gainesville, Florida 32601 and GRU acknowledges receipt.
1.5. PAYMENT
a) Invoicing. Contractor is responsible for invoicing GRU for Work performed pursuant to this Contract. Itemized
invoices shall include the following information (if applicable): Contract number, Purchase Order number, item number,
job number, description of supplies or services, quantities, unit prices, Work location, GRU Project Representative, job
start date, job completion date or other pertinent information. Itemized invoice(s) must be mailed to Gainesville
Regional Utilities, Accounts Payable, P.O. Box 147118, Station A-27, Gainesville, FL 32614-7118 or e-mailed to
accountspayable@gru.com.
b) Receipting Report for Services. An itemized receipting report for services must be provided to the GRU Project
28
Page 4 of 13
Representative prior to invoicing which includes the number of hours and labor rates by job title, overhead, authorized
per diem or travel expenses, and other charges. Receipting reports shall be used by the Project Representative to
verify the services rendered.
c) Payment Terms. Unless otherwise agreed upon in writing, GRU’s payment terms are net thirty (30) days from
receipt of correct invoice. Contractor shall not submit more than one (1) invoice per thirty-day period. Any delay in
receiving invoices, or error and omissions, will be considered just cause for delaying or withholding payment. Invoices
for partially completed Work may be allowed with GRU’s prior approval. All partial invoices must be clearly identified as
such on the invoice. Any charges or fees will be governed by current Florida Statutes.
d) Lien Release. Before the final acceptance of the Work and payment by GRU, Contractor shall furnish to GRU an
affidavit and final waiver that all claims for labor and materials employed or used in the construction of said Work have
been settled and no legal claim can be filed against GRU for such labor and materials. If such evidence is not
furnished to GRU, such amounts as may be necessary to meet the unsatisfied claims may be retained from monies
due to Contractor under this Contract until the liability has been discharged.
e) Final Payment/Acceptance. The acceptance by Contractor of final payment due on termination of the Contract
shall constitute a full and complete release of GRU from any and all claims, demands and causes of action whatsoever
which Contractor, its successors or assigns have or may have against GRU under the provisions of this Contract.
1.6. COMPLIANCE WITH LAWS AND REGULATIONS
All City, County, State and Federal laws, regulations and/or ordinances shall be strictly observed. Contractor is
responsible for taking all precautions necessary to protect life and property.
1.7. GOVERNING LAW, VENUE, ATTORNEY’S FEES, AND WAIVER OF RIGHT TO JURY TRIAL
This Contract shall be governed and construed pursuant to the laws of Florida and may not be construed more strictly
against one party than against the other. In the event of any legal proceedings arising from or related to this Contract:
(1) venue for any state or federal legal proceedings shall be in Alachua County Florida; (2) each Party shall bear its
own attorneys’ fees except to the extent that Contractor agrees to indemnify GRU as described in Supplemental
Conditions, including any appeals; and (3) for civil proceedings, the Parties hereby waive the right to jury trial.
1.8. VERIFICATION OF EMPLOYEES
The Contractor shall comply with all applicable requirements of Section 448.095, Florida Statutes, including but not
limited to: (1) the Contractor shall register with and use the U.S. Department of Homeland Security’s E-Verify system
to verify the work authorization status of all new employees of the Contractor during the term of this Agreement; and
(2) the Contractor shall expressly require any subcontractors performing work or providing services pursuant to this
Agreement to likewise register with and use the U.S. Department of Homeland Security’s E-Verify system to verify the
work authorization status of all new employees of the subcontractor during the term of this Agreement. Section
448.095, Florida Statutes, states the statute must be construed in a manner that is fully consistent with any applicable
federal laws or regulations, and therefore this section does not apply to this Agreement to the extent that this section
would be inconsistent with any federal laws or regulations that are applicable to this Agreement.
1.9. ANTI HUMAN TRAFFICKING
On or before the Effective Date of this Contract and, in addition, on or before the effective date of each renewal or
extension of this Contract, the Contractor shall provide GRU with an affidavit, pursuant to Section 787.06(13), Fla.
Stat., which is signed by an officer or a representative of the Contractor under penalty of perjury attesting that the
Contractor does not use coercion for labor or services as those terms are defined in Section 787.06(13), Fla. Stat.
1.10. SOVEREIGN IMMUNITY
Nothing in this Contract shall be interpreted as a waiver of GRU’s sovereign immunity as granted pursuant to Section
768.28 Florida Statutes.
29
Page 5 of 13
1.11. SEVERABILITY
If any provision of this Contract is declared by a court to be illegal or in conflict with any law, the validity of the
remaining terms and provisions shall not be affected; and the rights and obligations of the Parties shall be construed
and enforced as if this Contract did not contain the particular provision held to be invalid.
1.12. ASSIGNMENT
GRU or Contractor shall not assign or transfer, in whole or in part, any right or obligation pursuant to this Contract,
without the prior written consent of the other Party.
1.13. AUDIT OF RECORDS
Contractor shall maintain records sufficient to document completion of the scope of services pursuant to this contract.
At all reasonable times, these records shall be made available to review, inspect, copy and audit by persons duly
authorized by GRU. These records shall be kept for a minimum of three (3) years after termination of this Contract.
Records that relate to any litigation, appeals or settlement of claim arising pursuant to the performance of this Contract
shall be made available until a final disposition has been made of such litigation, appeal, or claim.
1.14. NONEXCLUSIVE REMEDIES
Except as expressly set forth in this Contract, the exercise by either Party of any of its remedies under this Contract
shall be without prejudice to its other remedies under this Contract or otherwise.
1.15. ADVERTISING
Contractor shall not publicly disseminate any information concerning the Contract without prior written approval from
GRU, including but not limited to, mentioning the Contract in a press release or other promotional material, identifying
GRU as a reference, or otherwise linking Contractor’s name and either a description of the Contract or the name of the
GRU in any material published, either in print or electronically, to any entity that is not a party to Contract, except
potential or actual authorized distributors, dealers, resellers, or service representative.
1.16. MODIFICATION OF TERMS
This Contract constitutes the entire agreement between the Parties. No oral agreements or representations shall be
valid or binding upon GRU or Contractor. No alteration or modification of this Contract, including substitution of
product, shall be valid or binding unless authorized by GRU. Contractor may not unilaterally modify the terms of this
Contract by affixing additional terms to product upon delivery (e.g., attachment or inclusion of standard preprinted
forms, product literature, “shrink wrap” terms accompanying or affixed to a product, whether written or electronic) or by
incorporating such terms onto Contractor’s order or fiscal forms or any other documents forwarded by Contractor for
payment. An acceptance of product or processing of documentation on forms furnished by Contractor for approval or
payment shall not constitute acceptance of the proposed modification to terms and conditions.
1.17. WAIVER
Any delay or failure by GRU to exercise or enforce any of its rights pursuant to this Contract shall not constitute or be
deemed a waiver of GRU’s right thereafter to enforce those rights, nor will any single or partial exercise of any such
right preclude any other or further exercise thereof or the exercise of any other right.
1.18. DISCLOSURE AND CONFIDENTIALITY
a) Florida’s Public Records Law, Chapter 119, Florida Statutes, includes numerous exemptions to the general
requirement to disclose information to the public in response to a public records request. Exemptions are found in
various provisions of the Florida Statutes, including but not limited to Section 119.071, Florida Statutes (General
30
Page 6 of 13
exemptions from inspection or copying of public records), and Section 119.0713, Florida Statutes (Local government
agency exemptions from inspection or copying of public records). Section 815.045, Florida Statutes (Trade secret
information), provides that trade secret information as defined in Section 812.081, Florida Statutes (Trade secrets;
theft, embezzlement; unlawful copying; definitions; penalty) is confidential and exempt from disclosure because it is a
felony to disclose such records. The Parties understand and agree that Florida’s Public Records Law is very broad and
that documents claimed by a Party to be confidential and exempt from public disclosure pursuant to the Public
Records Law may in fact not be deemed such by a court of law. Accordingly, the following provisions shall apply:
i. Identifying Trade Secret or Otherwise Confidential and Exempt Information. For any records or portions
thereof that Contractor claims to be Trade Secret or otherwise confidential and exempt from public disclosure
under the Public Records Law, Contractor shall:
1. Specifically identify the records or specific portions thereof that are confidential and exempt and
reference the particular Florida Statute that grants such status. Provide one redacted copy of the record
and one copy of the record with the confidential and exempt information highlighted. Contractor shall
take care to redact only the confidential and exempt information within a record.
2. Provide an affidavit or similar type of evidence that describes and supports the basis for Contractor’s
claim that the information is confidential and exempt from public disclosure.
ii. Request for Trade Secret or Otherwise Confidential and Exempt Information.
1. In the event GRU receives a public records request for a record with information labeled by Contractor
as Trade Secret or otherwise as confidential and exempt, GRU will provide the public record requester
with the redacted copy of the record and will notify Contractor of the public records request.
2. However and notwithstanding the above, in the event that GRU in its sole discretion finds no basis for
Contractor’s claim that certain information is Trade Secret or otherwise confidential and exempt under
Florida’s Public Records Law, then GRU shall notify Contractor in writing of such conclusion and provide
Contractor a reasonable amount of time to file for declaratory action requesting a court of law to deem
the requested information as Trade Secret or otherwise as confidential and exempt under Florida’s
Public Records Law. If Contractor fails to file for declaratory action within the reasonable amount of time
provided, then GRU will disclose the information requested.
3. If a public records lawsuit is filed against GRU requesting public disclosure of the information labeled
by Contractor as Trade Secret or otherwise as confidential and exempt, GRU shall notify Contractor and
Contractor shall intervene in the lawsuit to defend the nondisclosure of such information under Florida’s
Public Records Law.
4. Contractor hereby indemnifies and holds GRU, its officers and employees harmless from any and all
liabilities, damages, losses, and costs of any kind and nature, including but not limited to attorney’s fees,
that arise from or are in any way connected with Contractor’s claim that any information it provided to
GRU is Trade Secret or otherwise confidential and exempt from public disclosure under Florida’s Public
Records Law.
b) “Work Product" may include creative work which may lead to programs, intellectual properties, computer software,
computer programs, codes, text, hypertext, designs, and/or any other work products associated with or arising directly
out of the performance of the Work.
1.19. PUBLIC RECORDS
If Contractor is either a “contractor” as defined in Section 119.0701(1)(a), Florida Statutes, or an “agency” as defined in
Section 119.011(2), Florida Statutes, Contractor shall:
i. Keep and maintain public records, as defined in Section 119.011(12) of the Florida Statutes, required by GRU
to perform the service.
ii. Upon request from GRU’s custodian of public records, provide the public agency with a copy of the requested
31
Page 7 of 13
records or allow the records to be inspected or copied within a reasonable time at a cost that does not exceed
the cost provided in this chapter or as otherwise provided by law.
iii. Ensure that public records that are exempt or confidential and exempt from public records disclosure
requirements are not disclosed except as authorized by law for the duration of the contract term and following
completion of the contract if the contractor does not transfer the records to GRU.
iv. Upon completion of the contract, transfer, at no cost, to GRU all public records in possession of the
contractor or keep and maintain public records required by GRU to perform the service. If the contractor
transfers all public records to GRU upon completion of the contract, the contractor shall destroy any duplicate
public records that are exempt or confidential and exempt from public records disclosure requirements. If the
contractor keeps and maintains public records upon completion of the contract, the contractor shall meet all
applicable requirements for retaining public records. All records stored electronically must be provided to GRU,
upon request from GRU’s custodian of public records, in a format that is compatible with the information
technology systems of GRU.
IF THE CONTRACTOR HAS QUESTIONS REGARDING THE APPLICATION
OF CHAPTER 119, FLORIDA STATUTES, AS TO THE CONTRACTOR’S
DUTY TO PROVIDE PUBLIC RECORDS RELATING TO THIS CONTRACT,
CONTACT THE GRU CUSTODIAN OF PUBLIC RECORDS AT (352) 393-
1240, PURCHASING@GRU.COM, OR 301 SE 4TH AVENUE, GAINESVILLE
FL 32601.
1.20. SALES TAX
Respondent’s pricing shall include applicable taxes on items purchased or manufactured by Respondent for the
project. GRU is exempt from Florida sales taxes for certain purchases. A “Consumer’s Certificate of Exemption” is
available at https://www.gru.com/WorkWithGRU/Procurement/PurchaseOrders.
1.21. ANTI-DISCRIMINATION
Contractor shall not discriminate on the basis of race, color, religion, sex, gender, national origin, marital status, sexual
orientation, age, disability or gender identity, or other unlawful forms of discrimination in the performance of this
Contract. Contractor understands and agrees that a violation of this clause shall be considered a material breach of
this Contract and may result in termination of the Contract. This clause is not enforceable by or for the benefit of, and
creates no obligation to, any third party.
1.22. CAPTIONS AND SECTION HEADINGS
Captions and section headings used herein are for convenience only and shall not be used in construing this contract.
1.23. COUNTERPARTS
This agreement may be executed in any number of and by the different parties hereto on separate counterparts, each
of which when so executed shall be deemed to be an original, and such counterparts shall together constitute but one
and the same instrument.
1.24. PROHIBITION AGAINST CONSIDERATION OF SOCIAL, POLITICAL, OR IDEOLOGICAL INTEREST IN
GOVERNMENT CONTRACTING
In accordance with Section 287.05701(2)(a), F.S. (2023), GRU may not request documentation of or consider a
vendor's social, political, or ideological interests when determining if the vendor is a responsible vendor, and may not
give preference to a vendor based on the vendor's social, political, or ideological interests.
32
Page 8 of 13
1.25. ATTACHMENTS
All exhibits attached to this contract are incorporated into and made part of this contract by reference.
SUPPLEMENTAL CONDITIONS
These Supplemental Conditions amend or supplement the Solicitation/Contract as indicated below. All provisions
which are not so amended or supplemented remain in full force and effect, except that the Technical Specifications, if
any, shall govern if any conflict arises between such sections and these Supplemental Conditions.
1.26. CONDUCT OF THE WORK
Contractor shall be considered an independent entity and as such shall not be entitled to any right or benefit to which
GRU employees are or may be entitled to by reason of employment. Except as specifically noted in this Contract,
Contractor shall be solely responsible for the means, methods, techniques, sequences, and procedures utilized by
Contractor in the performance of this Contract. Contractor will assign only competent and skilled workers to perform
the Work. All of Contractor’s personnel or subcontractors engaged in any of the Work performed pursuant to this
Contract are under Contractor's sole direction, supervision and control at all times and in all places. Contractor's
employees must be as clean and in good appearance as the job conditions permit, conducting themselves in an
industrious and professional manner. Contractor and its employees cannot represent, act, or be deemed to be an
agent or employee of GRU. Nothing in this Agreement is intended to or shall be deemed to constitute a partnership or
joint venture between the Parties. Further, unless specifically authorized to do so, the Contractor shall not represent to
others that, as the Contractor, it has the authority to bind GRU to any third-party agreement.
1.27. CONTRACTOR RESPONSIBILITIES
a) Performance. Contractor shall perform all Work promptly and diligently in a good, proper and workmanlike manner
in accordance with the Specifications. In performing the Work, Contractor has the freedom to perform Work in the
manner which is most beneficial to the project provided that it is within the limits of these Specifications.
b) Project Related Requirements. Contractor is responsible for providing and paying expenses for all labor, tools,
equipment, and materials. All project related requirements must be of high quality, in good working condition, and
conducive for the particular task. Adequate first aid supplies must be provided by Contractor and accessible to
employees. These may include, but are not limited to, sanitation facilities, potable water, and office trailers.
1.28. COOPERATION/ COORDINATION
a) Access to Work Site. GRU and its authorized representatives are permitted free access to the work site, and
reasonable opportunity for the inspection of all Work and materials.
b) Work by GRU. GRU reserves the right to perform activities in the area where the Work is being performed by
Contractor.
c) Work by Other Contractor. GRU reserves the right to permit other Contractors to perform work within the same
work area. Contractor shall not damage, endanger, compromise or destroy any part of the site, including by way of
example and not limitation, work being performed by others on the site.
d) Coordination. Contractor shall, in the course of providing the Work, cooperate and communicate with GRU and all
other persons or entities as required for satisfactory completion. Contractor will afford GRU and other Contractors
reasonable opportunity for the introduction and storage of their equipment and materials and the execution of their
Work concurrently and coordinating its Work in the best interest of GRU.
1.29. INDEMNIFICATION
a) Contractor(s) shall be fully liable for its action, the actions of its agents, employees, partners, or subcontractors and
fully indemnifies, defends, and holds harmless the City of Gainesville, GRU, its elected officials, its officers, agents,
and employees, from any such suits, actions, damages, and/or costs of every name and description, including
33
Page 9 of 13
attorneys’ fees, arising from or relating to personal injury and damage to real or personal tangible property alleged to
be caused in whole or in part by Contractor(s), its agents, employees, partners, or subcontractors.
b) Further, Contractor(s) shall fully indemnify, defend, and hold harmless the City of Gainesville and/or GRU from any
suits, actions, damages, and costs of every name and description, including attorneys’ fees, arising from or relating to
violation or infringement of a trademark, copyright, patent, trade secret or intellectual property right, provided, however,
that the foregoing obligation will not apply to GRU’s misuse or modification or Contractor(s)’s products or GRU’s
operation or use of Contractor(s)’s products in a manner not contemplated by the Contract or the purchase order. If
any product is the subject of an infringement suit or in Contractor(s)’s opinion is likely to become the subject of such a
suit, Contractor(s) may at its sole expense procure for GRU the right to continue using the product or to modify it to
become non-infringing. If Contractor(s) is not reasonably able to modify or otherwise secure GRU the right to continue
using the product, Contractor(s) shall remove the product and refund GRU the amounts paid in excess of a reasonable
rental for past use. GRU shall not be liable for any royalties if applicable.
c) Contractor(s)’s obligations under the preceding two paragraphs with respect to any legal action are contingent upon
GRU giving Contractor(s) written notice of any action or threatened action, defending the action at Contractor(s)’s sole
expense. Contractor(s) shall not be liable for any costs or expenses incurred or made by GRU in any legal action
without Contractor(s)’s prior written consent, which will not be unreasonably withheld.
d) The provisions of this section shall survive the termination or expiration of this Contract.
1.30. DAMAGE TO WORK
Until final acceptance of the Work by GRU, Work will be under the charge and care of Contractor who must take every
necessary precaution against damage to the Work by the elements or from any other cause whatsoever. Contractor
will rebuild, repair, restore, or make good at their expense, damages to any portion of the Work before its completion
and acceptance. Failure to do so will be at Contractor’s own risk. Contractor is not relieved of a requirement of the
specifications on the plea of error.
1.31. DISPUTES
If a dispute arises out of or relates to this Agreement, or the breach thereof, and if the dispute cannot be settled
through negotiation, either party may, by giving written notice, refer the dispute to a meeting of appropriate higher
management, to be held within 20 business days after giving of notice. If the dispute is not resolved within 30 business
days after giving notice, or such later date as may be mutually agreed, the Parties will submit the dispute to a
mediator. The Parties shall mutually agree to the mediator and the costs of the mediator will be borne equally by both
parties. The venue for mediation and any subsequent litigation shall be in Alachua County, Florida.
1.32. DELAY
Notwithstanding the completion schedule, GRU has the right to delay performance for up to three (3) consecutive
months as necessary or desirable and such delay will not be deemed a breach of Contract, but the performance
schedule will be extended for a period equivalent to the time lost by reason of GRU's delay. Such extension of time will
be Contractor's sole and exclusive remedy for such delay.
If the project is stopped or delayed for more than three (3) consecutive months and GRU or Contractor elects to
terminate the Contract because of such delay, or if such stoppage or delay is due to actions taken by GRU within its
control, then Contractor's sole and exclusive remedy under the Contract will be reimbursement for costs reasonably
expended in preparation for or in performance of the Contract. None of the aforementioned costs will be interpreted to
include home office overhead expenses or other expenses not directly attributable to performance of the Contact.
Contractor is not entitled to make any other claim, whether in breach of Contract or in tort for damages resulting in
such delay.
1.33. DEFAULT
If Contractor should be adjudged as bankrupt, or make a general assignment for the benefit of its creditor(s), or if a
receiver should be appointed for Contractor, or if there is persistent or repeated refusal or failure to supply sufficient
properly skilled workforce or proper materials, or if Contractor should refuse or fail to make payment to persons
supplying labor or materials for the Work pursuant to this Contract, or persistently disregards instructions of GRU, or
fails to observe or perform or is guilty of a substantial violation of any provision of the Contract documents, then GRU,
after serving at least ten (10) calendar days prior written notice to Contractor of its intent to terminate and such default
should continue un-remedied for a period of ten (10) calendar days, may terminate the Contract without prejudice to
34
Page 10 of 13
any other rights or remedies and take possession of the Work; and GRU may take possession of and utilize in
completing the Work such materials, appliances, equipment as may be on the site of the Work and necessary
therefore. Contractor will be liable to GRU for any damages resulting from such default.
1.34. TERMINATION
a) Termination for Convenience. GRU may, by providing thirty (30) calendar days written notice to Contractor,
terminate this Contract, or any part thereof, for any or no reason, for GRU’s convenience and without cause. After the
termination date, Contractor shall stop all Work and cause its suppliers and/or subcontractors to stop all Work in
connection with this Contract. If GRU terminates for convenience, GRU shall pay Contractor for goods and services
accepted as of the date of termination, and for Contractor’s actual and reasonable, out of pocket costs incurred directly
as a result of such termination. GRU is not responsible for Work performed after the effective termination date of this
contract.
b) Termination for Cause (Cancellation). GRU may terminate this Contract for cause if Contractor materially breaches
this Contract by:
i. refusing, failing or being unable to properly manage or perform;
ii. refusing, failing or being unable to perform the Work pursuant to this Contract with sufficient numbers of
workers, properly skilled workers, proper materials to maintain applicable schedules;
iii. refusing, failing or being unable to make prompt payment to subcontractors or suppliers;
iv. disregarding laws, ordinances, rules, regulations or orders of any public authority or quasi-public authority
having jurisdiction over the Project;
v. refusing, failing or being unable to substantially perform pursuant to the terms of this Contract as determined
by GRU, or as otherwise defined elsewhere herein; and/or
vi. refusing, failing or being unable to substantially perform in accordance with the terms of any other agreement
between GRU and Contractor.
c) Funding out Clause. If funds for this Contract are no longer available, GRU reserves the right to terminate this
Contract without cause by providing Contractor with thirty (30) calendar day’s written notice to Contractor.
1.35. FORCE MAJEURE
a) No Party to this Contract shall be liable for any default or delay in the performance of its obligations under this
Contract due to an act of God or other event to the extent that: (a) the non-performing Party is without fault in causing
such default or delay; and (b) such default or delay could not have been prevented by reasonable precautions. Such
causes include, but are not limited to acts of civil or military authority (including but not limited to courts of
administrative agencies); acts of God; war; terrorist attacks; riot; insurrection; inability of GRU to secure approval;
validation or sale of bonds; inability of GRU or Supplier to obtain any required permits, licenses or zoning; blockades;
embargoes; sabotage; epidemics; fires; hurricanes, tornados, floods; or strikes.
b) In the event of any delay resulting from such causes, the time for performance of each of the Parties hereunder
(including the payment of invoices if such event actually prevents payment) shall be extended for a period of time
reasonably necessary to overcome the effect of such delay. Any negotiated delivery dates established during or after a
Force Majeure event will always be discussed and negotiated if additional delays are expected.
c) In the event of any delay or nonperformance resulting from such cause, the Party affected will promptly notify the
other Party in writing of the nature, cause, date of commencement, and the anticipated impact of such delay or
nonperformance. Such written notice, including change orders, will indicate the extent, if any, to which is anticipated
that any delivery or completion date will be affected.
35
Page 11 of 13
1.36. LIMITATION OF GRU’S LIABILITY
To the fullest extent permitted by law, GRU shall not be liable to Contractor for any incidental, consequential, punitive,
exemplary or indirect damages, lost profits, revenue or other business interruption damages, including but not limited
to, loss of use of equipment or facility.
1.37. WORK HOURS
GRU normal business hours are 8:00 AM EST to 5:30 PM EST. Contractor(s) may perform the Work outside business
hours only with prior approval from the Authorized Representative or designee.
1.38. PERFORMANCE TIME
Contractor shall complete the Work no later than the date set forth in the Contract. Contractor further understands and
agrees that time is of the essence. If Contractor fails to complete the Work on or before the date established for Final
Completion, then Contractor will be solely responsible for liquidated damages or other costs as set forth in the
Solicitation or Contract.
1.39. LIQUIDATED DAMAGES
Liquidated damages shall be assessed in the amount of $500 per calendar day for each day after the agreed upon
completion date or the last day of September for year scope was provided
1.40. COMPLETION OF WORK
1. Substantial Completion: The time at which the Work (or a specified part thereof) has progressed to the point where,
in the opinion of Engineer, the Work (or a specified part thereof) is sufficiently complete, in accordance with the
Contract Documents, so that the Work (or a specified part thereof) can be utilized for the purposes for which it is
intended. The terms “substantially complete” and “substantially completed” as applied to all or part of the Work refer to
Substantial Completion thereof.
2. Final Completion: The date that the Owner receives and agrees with written notice from the Contractor stating that
the Work has been completed and is ready for final payment.
1.41. DELIVERY
Once a written PO is emailed to the successful Bidder, the work shall be scheduled and started within sixty (60)
calendar days. However, should the work have to be performed on an emergency basis, work will be scheduled and
started within two (2) calendar days. Holiday and weekend deliveries may be needed as product use or circumstances
require. If the successful Bidder cannot meet the delivery requirements for any of the product or services specified
herein, GRU reserves the right to procure the product or services from the next lowest responsive, responsible bidder,
or to solicit new pricing. The goal of this agreement is for the speedy acquisition of water and sewer materials and
accessories; therefore, successful Bidder’s responsiveness under the terms of this agreement is paramount. Delivery
of orders resulting from award of this bid shall be made within seven (7) to ten (10) business days after receipt of a
valid PO number for the items listed on the Bid Form. For all other items, deliveries shall be made complete within
thirty (30) calendar days after receipt of a valid PO number. Failure to respond within the time specified may result in
materials being ordered from and delivered by others and/or termination of award.
1.42. INSURANCE
Contractor shall meet the minimum insurance requirements at all times as required by law and GRU. Contractor shall
notify GRU of any changes in coverage within seven (7) business days of knowledge of such change taking effect.
Failure to maintain minimum coverage may result in breach of Contract. Contractor shall procure and maintain
insurance with coverage amounts as required. Contractor must furnish GRU a certificate of insurance in a form
acceptable to GRU for the insurance required with endorsement naming GRU as additional insured.
1.43. MINIMUM INSURANCE AMOUNTS REQUIRED
Insurance is required in the amounts set forth below:
Commercial General Liability: $1,000,000 combined single limit for bodily injury and property damage
Automobile Liability: $1,000,000 combined single limit for bodily injury and property damage
36
Page 12 of 13
Worker’s Compensation:
o State (Florida): Statutory
o Applicable Federal: Statutory
o Employer’s Liability:
$500,000 per Accident
$500,000 Disease, Policy Limit
$500,000 Disease, Each Employee
Excess Liability: $1,000,000
1.44. WARRANTY/GUARANTEE
1. Contractor warrants and guarantees to GRU that all materials will be new unless otherwise specified and that all
Work will be of a quality free from defects and in accordance with the Specifications. Contractor agrees to remedy
promptly, and without cost to GRU, any defective materials or workmanship which appear within the stated warranty
period.
2. No provision contained in the Specifications shall be interpreted to limit Contractor’s liability for defects. No provision
contained in the Specifications shall be interpreted to limit the terms and conditions of the manufacturer's warranty and
Contractor will secure parts, materials and equipment to be installed with manufacturer's full warranty as to parts and
service wherever possible. Contractor must indicate if any warranty is being provided by either Contractor or a
manufacturer and if any such warranty is being provided, such warranty will be stated. When the manufacturer
warrants the equipment or materials being supplied, Contractor must provide such warranty to GRU or must state as a
Clarification and Exception the reason Contractor is not able to provide such warranty.
3. All maintenance, repair and construction services furnished as defined herein shall be guaranteed and warranted by
the successful Bidder for a minimum period of three (3) years, unless otherwise specified, from final acceptance by
GRU to be free from defects due either to faulty materials or equipment or faulty workmanship. All materials,
equipment, and workmanship furnished and/or furnished and installed by the successful Bidder is warranted and
guaranteed by the successful Bidder to meet the required standards specified herein and to accomplish the purposes
and functions of the project. GRU shall, following discovery of faulty materials or workmanship, promptly give written
notice to the successful Bidder of faulty materials, equipment, or workmanship within the period of the guarantee and
the successful bidder(s) shall promptly replace any part of the faulty equipment, material, or workmanship at its own
cost. These warranty and guarantee provisions create no limitations on GRU as to any claims or actions for breach of
guaranty or breach of warranty that GRU might have against parties other than the successful Bidder, and do not
constitute exclusive remedies of GRU against the successful Bidder.
1.45. SAFETY AND SECURITY
Each location has unique safety and security procedures and guidelines that must be followed. Acceptance of a
project or work assignment in a particular location will be an acceptance of the safety and security requirements for
that location. GRU will provide the safety and security requirements along with the scope of work requested. The
contractor shall at all times take all reasonable precautions for the safety of its employees engaged in services and
shall comply with all safety laws, rules and regulations as mentioned in the contractors safety orientation and/or
manual as instruction may be site specific.
a. Confinement to Work Area/Parking. Contractor's employees shall stay in the designated work area to the
maximum extent possible and shall not traverse other areas of GRU’s site except for travel to and from sanitary
facilities or designated parking areas. Contractor and its employees shall park personal vehicles and equipment
in areas designated by GRU.
b. Sanitation. If sanitary facilities are available near the work site, Contractor may request GRU’s permission to
use such facilities by its employees, obtaining written permission from GRU prior to the use of such facilities.
Unless such permission has been obtained, Contractor is responsible for the cost, provision and maintenance
of sanitary facilities for persons employed by Contractor. If responsible for providing sanitary facilities,
Contractor is also responsible for all labor and supplies necessary to maintain such facilities and must comply
37
Page 13 of 13
with the State Board of Health requirements. Upon completion of the Work, facilities must be removed from the
site.
c. Personal Protection Equipment requirements during a Pandemic, Epidemic, Sporadic, Endemic or Outbreaks
event.
d. The Contractor shall supply all safety and personal protective equipment (PPE) required to complete the
scope of the contracted work (or as stated in the Contract). Equipment supplied by the Contractor must meet or
exceed all GRU requirements and the requirements of the appropriate governmental regulatory agency
e. It is the sole responsibility of the contractor to supply and train all workers with reasonably anticipated
occupational potential exposure to any work place hazards.
f. This training includes when to use PPE; what PPE is necessary; how to properly put on, use, and take off
PPE; how to properly dispose of or disinfect, inspect for damage, and maintain PPE; and the limitations of PPE.
g. Protocols should be in place to prevent or reduce the likelihood of exposure and be in compliance with
operating site PPE requirements. Local, state, and federal mandates must be followed.
1.46. WARRANTY OF TITLE
Contractor warrants that it holds and shall transfer unencumbered title of the property to GRU and further warrants that
it has the right and authority to transfer the title to the property.
1.47. NERC CIP COMPLIANCE REQUIREMENTS
Pursuant to federally mandated security standards from the North American Electric Reliability Corporation (NERC)
regarding Critical Infrastructure Protection (CIP), GRU has implemented specific requirements for any contract
employee requiring access to protected systems and facilities. These requirements are outlined in NERC Standard
“CIP-004-6 Table R3 – Personnel Risk Assessment Program”, and apply to anyone who shall have physical and/or
electronic access to these designated locations. Compliance verification for an employee, including annual training as
well as a qualified criminal history background screening, will be required prior to granting that employee authorized
access to the designated protected systems and/or facilities.
1.48. CONTRACTOR'S RESPONSIBILITIES
1. Contractor will recruit, screen, interview, hire and assign its employees to perform the work pursuant to this
Contract; compensate its employees for hours worked at GRU; withhold and transmit payroll taxes, provide
unemployment insurance and workers’ compensation benefits; and handle unemployment and workers’ compensation
claims involving employees.
2. Contractor shall obtain background check and drug screening services of its employees who will perform work at
GRU locations. To ensure compliance with the Fair Credit Reporting Act, Contractor will not provide copies of such
background check or drug screening results to GRU but will instead provide an attestation of completion of such
services to GRU. Background check services may be conducted by one or more of Contractor’s preferred, third-party
vendors (e.g., Hire Right, A-Check Global).
3. Contractor shall require all of the Employees to self-report in writing to Contractor within forty-eight hours any
incidents of arrests by local, state or federal law enforcement agencies. If the Employee is unable to report in writing
due to incarceration or confinement, the Employee shall notify Contractor within forty-eight (48) hours after the arrest
by text message, email, phone call, or voicemail. In addition, all Employees holding a Commercial Driver’s License
(CDL) as a condition of employment shall self-report, in writing, to Contractor within forty-eight (48) hours after any
citations, arrests, or charges disqualifying the Employee from holding a CDL.
1.49. ORDER OF PRECEDENCE
In the event that there is any conflict between the terms and conditions, the order of precedence shall be as follows:
a. Any modification to this Contract
b. Contract
c. GRU Technical Specifications
d. GRU Supplemental Conditions
e. GRU General Conditions
f. GRU Instructions
g. Contractor Response
38
A-1 Inspection and Cleaning Mobilization (1 per Project Area)EA $500.00 5 $2,500.00
A-2 CIPP Rehabilitation Mobilization (1 per Project Area)EA $3,541.00 5 $17,705.00
A-3 Lateral Service and Cleanout Mobilization (1 per Project Area )EA $0.00 5 $0.00
A-4 MH Rehabilitation Mobilization (1 per Project Area)EA 5
A-5 Easement Access Road Matting LF $6.37 500 $3,185.00
Easement Reel Access
A-6 6" to 12" diameter LF $3.50 500 $1,750.00
A-7 14" to 18" diameter LF $4.50 500 $2,250.00
A-8 20" to 24" diameter LF $5.50 500 $2,750.00
CCTV Inspection and Light Cleaning (4 Line Passes or less)
B-1 6" diameter LF $4.15 5,000 $20,750.00
B-2 8" - 12" diameter LF $3.15 10,000 $31,500.00
B-3 14" - 18" diameter LF $4.45 5,000 $22,250.00
B-4 20" - 24" diameter LF $5.85 2,500 $14,625.00
B-5 27" - 42" diameter LF $7.00 1,000 $7,000.00
Heavy Cleaning (Up to 4 Line Passes in addition to Light Cleaning)
B-6 6" diameter LF $3.15 5,000 $15,750.00
B-7 8" - 12" diameter LF $2.15 10,000 $21,500.00
B-8 14" - 18" diameter LF $2.50 5,000 $12,500.00
B-9 20" - 24" diameter LF $8.25 2,500 $20,625.00
B-10 27" - 42" diameter LF $20.00 1,000 $20,000.00
Root Cutting
B-11 6" diameter LF $9.75 1,000 $9,750.00
B-12 8" - 12" diameter LF $11.00 2,500 $27,500.00
B-13 14" - 18" diameter LF $19.69 500 $9,845.00
B-14 20" - 24" diameter LF $24.00 500 $12,000.00
B-15 27" - 42" diameter LF $50.00 500 $25,000.00
Tuberculation Removal
B-16 6" diameter LF $10.54 1,000 $10,540.00
B-17 8" - 12" diameter LF $12.72 5,000 $63,600.00
B-18 14" - 18" diameter LF $14.32 5,000 $71,600.00
B-19 20" - 24" diameter LF $16.25 1,000 $16,250.00
B-20 27" - 42" diameter LF $61.29 500 $30,645.00
C-1 Service Lateral CCTV Inspection EA $75.00 500 $37,500.00
C-2 Service Lateral Cleaning EA $100.00 500 $50,000.00
C-3 Service Lateral Tuberculation Removal LF $35.00 250 $8,750.00
C-4 Protruding Service Lateral Removal EA $950.00 100 $95,000.00
End Seals
D-1 6" Dia. End Seals (Per Segment)EA $52.50 100 $5,250.00
D-2 8" Dia. End Seals (Per Segment)EA $280.98 100 $28,098.00
D-3 10" Dia. End Seals (Per Segment)EA $316.06 100 $32,606.00
D-4 12" Dia. End Seals (Per Segment)EA $351.16 100 $35,116.00
D-5 14" Dia. End Seals (Per Segment)EA $388.48 50 $19,424.00
D-6 15" Dia. End Seals (Per Segment)EA $398.00 50 $19,900.00
D-7 16" Dia. End Seals (Per Segment)EA $447.34 50 $22,367.00
D-8 18" Dia. End Seals (Per Segment)EA $444.80 50 $22,240.00
D-9 20" Dia. End Seals (Per Segment)EA $630.74 50 $31,537.00
D-10 21" Dia. End Seals (Per Segment)EA $620.36 50 $31,018.00
D-11 24" Dia. End Seals (Per Segment)EA $667.18 50 $33,359.00
6" diameter
D-12 4.5 mm manufactured thickness (.177)LF $42.60 2,000 $85,200.00
8" diameter
D-13 6.0 mm manufactured thickness (.236)LF $43.94 5,000 $219,700.00
D-14 Add Item - 1.5mm increaser per LF LF $2.61 5,000 $13,050.00
10" diameter
D-15 6.0 mm manufactured thickness (.236)LF $50.95 2,500 $127,375.00
D-16 Add Item - 1.5mm increaser per LF LF $2.95 2,500 $7,375.00
12" diameter
D-17 6.0 mm manufactured thickness (.236)LF $57.01 2,500 $142,525.00
D-18 Add Item - 1.5mm increaser per LF LF $3.26 2,500 $8,150.00
14" diameter
D-19 6.0 mm manufactured thickness (.236)LF $67.26 2,500 $168,150.00
D-20 Add Item - 1.5mm increaser per LF LF $3.56 2,500 $8,900.00
15" diameter
D-21 7.5 mm manufactured thickness (.295)LF $71.18 2,500 $177,950.00
D-22 Add Item - 1.5mm increaser per LF LF $4.07 2,500 $10,175.00
16" diameter
D-23 7.5 mm manufactured thickness (.295)LF $83.41 2,500 $208,525.00
D-24 Add Item - 1.5mm increaser per LF LF $5.92 2,500 $14,800.00
18" diameter
D-25 7.5 mm manufactured thickness (.295)LF $90.75 5,000 $453,750.00
D-26 Add Item - 1.5mm increaser per LF LF $4.47 5,000 $23,700.00
20" diameter
D-27 7.5 mm manufactured thickness (.295)LF $104.34 2,500 $260,850.00
D-28 Add Item - 1.5mm increaser per LF LF $7.14 2,500 $17,850.00
21" diameter
D-29 9.0 mm manufactured thickness (.354)LF $118.80 1,000 $118,800.00
D-30 Add Item - 1.5mm increaser per LF LF $7.15 1,000 $7,150.00
24" diameter
D-31 10.5 mm manufactured thickness (.413)LF $138.92 1,000 $138,920.00
D-32 Add Item - 1.5mm increaser per LF LF $6.16 1,000 $6,160.00
Item
No. DESCRIPTION Unit of Measure Unit Price
Estimated
Annual Quantity Total Amount
Mobilization
Mainline Clean & Inspection - Sanitary
Service Lateral Clean & Inspection - Sanitary
Mainline Cured In Place Pipe (CIPP) Installation - Sanitary
39
27" diameter
D-33 10.5 mm manufactured thickness (.413)LF $151.89 1,000 $151,890.00
D-34 Add Item - 1.5mm increaser per LF LF $7.16 1,000 $7,160.00
30" diameter
D-35 12 mm manufactured thickness (.472)LF $185.69 1,000 $185,690.00
D-36 Add Item - 1.5mm increaser per LF LF $8.23 1,000 $8,230.00
36" diameter
D-37 12 mm manufactured thickness (.472)LF $214.11 1,000 $214,110.00
D-38 Add Item - 1.5mm increaser per LF LF $10.57 1,000 $10,570.00
42" diameter
D-39 13.5 mm manufactured thickness (.531)LF $281.52 1,000 $281,520.00
D-40 Add Item - 1.5mm increaser per LF LF $11.27 1,000 $11,270.00
Drop Pipe Setup, CCTV, Cleaning and CIPP Installation
6" diameter
E-1 Setup, CCTV Inspection, and Cleaning EA 20
E-2 4.5 mm manufactured thickness LF 150
E-3 Add Item - 1.5mm increaser per LF LF 150
8" diameter
E-4 Setup, CCTV Inspection, and Cleaning EA 20
E-5 4.5 mm manufactured thickness LF 150
E-6 Add Item - 1.5mm increaser per LF LF 150
10" diameter
E-7 Setup, CCTV Inspection, and Cleaning EA 10
E-8 6.0 mm manufactured thickness LF 100
E-9 Add Item - 1.5mm increaser per LF LF 100
12" diameter
E-10 Setup, CCTV Inspection, and Cleaning EA 10
E-11 6.0 mm manufactured thickness LF 100
E-12 Add Item - 1.5mm increaser per LF LF 100
14" diameter
E-13 Setup, CCTV Inspection, and Cleaning EA 10
E-14 6.0 mm manufactured thickness LF 100
E-15 Add Item - 1.5mm increaser per LF LF 100
15" diameter
E-16 Setup, CCTV Inspection, and Cleaning EA 2
E-17 6.0 mm manufactured thickness LF 25
E-18 Add Item - 1.5mm increaser per LF LF 25
16" diameter
E-19 Setup, CCTV Inspection, and Cleaning EA 10
E-20 6.0 mm manufactured thickness LF 100
E-21 Add Item - 1.5mm increaser per LF LF 100
18" diameter
E-22 Setup, CCTV Inspection, and Cleaning EA 2
E-23 6.0 mm manufactured thickness LF 25
E-24 Add Item - 1.5mm increaser per LF LF 25
20" diameter
E-25 Setup, CCTV Inspection, and Cleaning EA 10
E-26 6.0 mm manufactured thickness LF 100
E-27 Add Item - 1.5mm increaser per LF LF 100
21" diameter
E-28 Setup, CCTV Inspection, and Cleaning EA 2
E-29 6.0 mm manufactured thickness LF 25
E-30 Add Item - 1.5mm increaser per LF LF 25
24" diameter
E-31 Setup, CCTV Inspection, and Cleaning EA 2
E-32 6.0 mm manufactured thickness LF 25
E-33 Add Item - 1.5mm increaser per LF LF 25
Drop Pipe Setup, CCTV, Cleaning and CIPP Installation
6" diameter
F-1 Setup, CCTV Inspection, and Cleaning EA 5
F-2 4.5 mm manufactured thickness (.236)LF 50
F-3 Add Item - 1.5mm increaser per LF LF 50
8" diameter
F-4 Setup, CCTV Inspection, and Cleaning EA 5
F-5 4.5 mm manufactured thickness (.236)LF 50
F-6 Add Item - 1.5mm increaser per LF LF 50
10" diameter
F-7 Setup, CCTV Inspection, and Cleaning EA 5
F-8 6.0 mm manufactured thickness (.236)LF 50
F-9 Add Item - 1.5mm increaser per LF LF 50
12" diameter
F-10 Setup, CCTV Inspection, and Cleaning EA 5
F-11 6.0 mm manufactured thickness (.236)LF 50
F-12 Add Item - 1.5mm increaser per LF LF 50
14" diameter
F-13 Setup, CCTV Inspection, and Cleaning EA 5
F-14 6.0 mm manufactured thickness (.236)LF 50
F-15 Add Item - 1.5mm increaser per LF LF 50
15" diameter
F-16 Setup, CCTV Inspection, and Cleaning EA 5
F-17 6.0 mm manufactured thickness (.236)LF 50
F-18 Add Item - 1.5mm increaser per LF LF 50
16" diameter
F-19 Setup, CCTV Inspection, and Cleaning EA 5
F-20 6.0 mm manufactured thickness (.236)LF 50
F-21 Add Item - 1.5mm increaser per LF LF 50
18" diameter
F-22 Setup, CCTV Inspection, and Cleaning EA 2
F-23 6.0 mm manufactured thickness (.236)LF 20
F-24 Add Item - 1.5mm increaser per LF LF 20
20" diameter
F-25 Setup, CCTV Inspection, and Cleaning EA 5
F-26 6.0 mm manufactured thickness (.236)LF 50
F-27 Add Item - 1.5mm increaser per LF LF 50
21" diameter
F-28 Setup, CCTV Inspection, and Cleaning EA 2
F-29 6.0 mm manufactured thickness (.236)LF 20
Lift Station External Drop Cured in Place Pipe Services
Manhole External Drop Cured in Place Pipe Services
40
F-30 Add Item - 1.5mm increaser per LF LF 20
24" diameter
F-31 Setup, CCTV Inspection, and Cleaning EA 2
F-32 6.0 mm manufactured thickness (.354)LF 20
F-33 Add Item - 1.5mm increaser per LF LF 20
41
G-1 Lateral Service Reinstatement EA $354.10 200 $70,820.00
G-2 Segment Dewatering Operation (Well point)DAY $7,500.00 5 $37,500.00
Internal Spot Repair
8" diameter
G-3 316L Stainless Steel Mechanical Point Repair Insert EA $3,500.00 3 $10,500.00
G-4 4.5 mm manufactured thickness (4 LF Repair Length)EA $4,500.00 3 $13,500.00
10" diameter
G-5 316L Stainless Steel Mechanical Point Repair Insert EA $3,750.00 3 $11,250.00
G-6 4.5 mm manufactured thickness (4 LF Repair Length)EA $4,750.00 3 $14,250.00
12" diameter
G-7 316L Stainless Steel Mechanical Point Repair Insert EA $3,900.00 3 $11,700.00
G-8 4.5 mm manufactured thickness (4 LF Repair Length)EA $4,900.00 3 $14,700.00
14" diameter
G-9 316L Stainless Steel Mechanical Point Repair Insert EA $4,000.00 3 $12,000.00
G-10 4.5 mm manufactured thickness (4 LF Repair Length)EA $5,000.00 3 $15,000.00
15" diameter
G-11 316L Stainless Steel Mechanical Point Repair Insert EA $4,200.00 2 $8,400.00
G-12 4.5 mm manufactured thickness (4 LF Repair Length)EA $5,200.00 2 $10,400.00
16" diameter
G-13 316L Stainless Steel Mechanical Point Repair Insert EA $4,300.00 3 $12,900.00
G-14 4.5 mm manufactured thickness (4 LF Repair Length)EA $5,300.00 3 $15,900.00
18" diameter
G-15 Trenchless 316L Stainless Steel Mechanical Point Repair Insert EA $4,400.00 2 $8,800.00
G-16 4.5 mm manufactured thickness (4 LF Repair Length)EA $5,400.00 2 $10,800.00
20" diameter
G-17 316L Stainless Steel Mechanical Point Repair Insert EA $4,500.00 3 $13,500.00
G-18 4.5 mm manufactured thickness (4 LF Repair Length)EA $5,500.00 3 $16,500.00
21" diameter
G-19 Trenchless 316L Stainless Steel Mechanical Point Repair Insert EA $4,600.00 2 $9,200.00
G-20 4.5 mm manufactured thickness (4 LF Repair Length)EA $5,600.00 2 $11,200.00
24" diameter
G-21 Trenchless 316L Stainless Steel Mechanical Point Repair Insert EA $4,700.00 2 $9,400.00
G-22 4.5 mm manufactured thickness (4 LF Repair Length)EA $5,700.00 2 $11,400.00
G-23 Grout Injection Soil Stabilization (Cost + 10%)ALLOWANCE $25,000.00 1 $25,000.00
H-1 4" Diameter PVC Cleanout Installation (Depth less than 5 feet)EA 150
H-2 6" Diameter PVC Cleanout Installation (Depth less than 5 feet)EA 50
H-3 Additional Material, Excavation and Compacted Backfill for Cleanout (5 feet to 10 feet in depth)EA 25
H-4 Provide and Install Cleanout Service Box and Cover (Composite) EA 200
H-5 Install Cleanout Service Box (Metal) (Owner to Provide Box and Cover Material)EA 15
H-6 Cleanout Sod Placement (25 SF per Cleanout Install)EA 200
H-7 Sidewalk and Driveway Concrete Repair (4 inch to 6 inch in thickness)SF 25
H-8 Asphalt Repair SF 50
I-1 Lateral Service CIPP Setup (1 per Mainline Segment)EA 50
I-2 4” Lateral up to 3' long in 8" main EA 100
I-3 4” Lateral up to 3' long in 10" main EA 25
I-4 4” Lateral up to 3' long in 12" main EA 25
I-5 6” Lateral up to 3' long in 8" main EA 10
I-6 6” Lateral up to 3' long in 10" main EA 10
I-7 6” Lateral up to 3' long in 12" main EA 10
I-8 Additional Length of CIPP (4" or 6" service) LF 2,500
Existing Manhole Liner Removal
J-1 HDPE Lining Removal (9 VF Avg. Depth)EA 2
J-2 Polymer/Epoxy Lining Removal (9 VF Avg. Depth)EA 25
J-3 Fiberglass Lining Removal (9 VF Ave. Depth)EA 5
J-4 Internal DIP Drop Pipe Removal (9 VF Avg Depth)EA 25
J-5 Inside Iron Step Removal per Manhole (5 Avg per MH)EA 100
J-6 Manhole Ring and Cover Remove and Replace (New Ring and Cover Provided by Owner)EA 200
J-7 Manhole Ring and Cover Adjustments LF 2
J-8 Exterior Severe Leak Stoppage/Groundwater Mitigation (Cost + 10%)ALLOWANCE 1 $50,000.00
Internal Manhole Minor Leak Stoppage
J-9 Manhole Depth - 0' to 5'EA 100
J-10 Manhole Depth - Over 5' to 10'EA 75
J-11 Manhole Depth - Over 10' to 15'EA 50
J-12 Manhole Depth - Over 15' to 20'EA 50
J-13 Manhole Depth -Over 20'EA 25
Bench Rehabilitation
J-14 Bench and Invert Demo, Repair and Rebuild 48" MH Diameter EA 150
J-15 Bench and Invert Demo, Repair and Rebuild 60" MH Diameter EA 50
J-16 Bench and Invert Demo, Repair and Rebuild 72" MH Diameter EA 25
J-17 Bench and Invert Demo, Repair and Rebuild 96" MH Diameter EA 5
Structural Build Back Rehabilitation Application
J-18A Structural Rebuild Layer (Build Back over 1" in thickness) - 48" MH Diameter VF 80
J-18B Structural Rebuild Layer (Build Back over 1" in thickness) - 60" MH Diameter VF 40
J-18C Structural Rebuild Layer (Build Back over 1" in thickness) - 72" MH Diameter VF 20
J-18D Structural Rebuild Layer (Build Back over 1" in thickness) - 96" MH Diameter VF 20
Rehabilitation Lining Application
J-19A Non-Structural Substrate Underlayment Layer 0.50" (13mm) Thickness Minimum - 48" MH Diameter VF 200
J-19B Non-Structural Substrate Underlayment Layer 0.50" (13mm) Thickness Minimum - 60" MH Diameter VF 20
J-19C Non-Structural Substrate Underlayment Layer 0.50" (13mm) Thickness Minimum - 72" MH Diameter VF 20
J-19D Non-Structural Substrate Underlayment Layer 0.50" (13mm) Thickness Minimum - 96" MH Diameter VF 10
J-20A Corrosion Protection Lining System 0.25" (6mm) Thickness Minimum - 48" MH Diameter VF 1,500
J-20B Corrosion Protection Lining System 0.25" (6mm) Thickness Minimum - 60" MH Diameter VF 250
J-20C Corrosion Protection Lining System 0.25" (6mm) Thickness Minimum - 72" MH Diameter VF 25
J-20D Corrosion Protection Lining System 0.25" (6mm) Thickness Minimum - 96" MH Diameter VF 15
J-21 Inside Drop installation (Hardware and Drop Provided by Owner)EA 25
Mainline CIPP Ancillary Services
Service Lateral Cleanout Installation
Service Lateral Cured In Place Pipe (CIPP) Installation
Manhole Rehabilitation Services
42
Low Flow By-Pass Setup (Less Than 500 GPM with 100% Onsite Redundancy)
K-1 Bypass Pump Setup EA $4,389.00 75 $329,850.00
Low Flow By-Pass Pumping Operations (Less Than 500 GPM)
K-2 Mainline CCTV Inspection Operation LF $1.43 15,000 $21,450.00
K-3 Lateral CCTV Inspection Operation (Avg of 7 Laterals per Mainline Segment) ($/LF of Mainline)LF $1.43 15,000 $21,450.00
K-4 Mainline Light Cleaning Operation (Up to 4 Line Passes)LF $1.43 15,000 $21,450.00
K-5 Mainline Heavy Cleaning Operation (Up to 4 Line Passes in addition to Light Cleaning)LF $4.00 5,000 $20,000.00
K-6 Light Tuberculation Removal (Up to 4 Passes with Cutting Tool)LF $4.00 5,000 $20,000.00
K-7 Heavy Tuberculation Removal (Up to 4 Passes with Cutting Tool in addition to Light Tub. Removal)LF $4.00 5,000 $20,000.00
K-8 Mainline CIPP Installation Operation LF $1.43 15,000 $20,000.00
K-9 Lateral CIPP Installation Operation (Avg of 7 Laterals per Mainline Segment) ($/LF of Mainline)LF 15,000 $21,450.00
K-10 High Flow By-Pass Setup (Greater Than 500 GPM with 100% Onsite Redundancy) (Cost + 10%)ALLOWANCE 1 $100,000.00
K-11 High Flow By-Pass Pumping Operations (Greater Than 500 GPM, no redundancy) (Cost + 10%)ALLOWANCE 1 $100,000.00
K-12 High Flow By-Pass Pumping Operations (Greater Than 500 GPM with 100% Redundancy) (Cost + 10%)ALLOWANCE 1 $150,000.00
Wastewater Hauling Operations
K-13 Initial Hauling Startup and Mobilization (6 Hour Min)EA $1,000.00 30 $30,000.00
K-14 Hauling (Up to 2000 Gal Debris Capacity) HR/TRK $350.00 500 $175,000.00
K-15 Hauling (2000 to 4000 Gal Debris Capacity) (10 Hr = 1 Day)DAY/TRK $3,500.00 100 $350,000.00
Bypass Ancillary Services
K-16 Roadway Hose Ramp Setup EA $250.00 150 $37,500.00
Traffic Control - Right of Way per FDOT Index
L-1 Maintenance of Traffic (Cost + 10%, without Flagmen)ALLOWANCE 1 $300,000.00
L-2 Flagmen (2 Required, 8 hour min)DAY $2,250.00 100 $225,000.00
Performance and Payment Bond (1% for Estimate Value Only)%1%$64,428.00
Project Contingency (15%)%15%$996,420.00
7,503,648.00$
General Conditions
Total Estimated Value
Bypass Services
Maintenance of Traffic (MOT) Services
43
44
45
ATTACHMENT 1
Item
No. DESCRIPTION Unit of Measure Unit Price
Estimated
Annual Quantity Total Amount
Mobilization
A-1 Inspection and Cleaning Mobilization (1 per Project Area) EA $500.00 5 $2,500.00
A-2 CIPP Rehabilitation Mobilization (1 per Project Area) EA $3,541.00 5 $17,705.00
A-3 Lateral Service and Cleanout Mobilization (1 per Project Area ) EA $0.00 5 $0.00
A-4 MH Rehabilitation Mobilization (1 per Project Area) EA 5
A-5 Easement Access Road Matting LF $6.37 500 $3,185.00
Easement Reel Access
A-6 6" to 12" diameter LF $3.50 500 $1,750.00
A-7 14" to 18" diameter LF $4.50 500 $2,250.00
A-8 20" to 24" diameter LF $5.50 500 $2,750.00
Mainline Clean & Inspection - Sanitary
CCTV Inspection and Light Cleaning (4 Line Passes or less)
B-1 6" diameter LF $4.15 5,000 $20,750.00
B-2 8" - 12" diameter LF $3.15 10,000 $31,500.00
B-3 14" - 18" diameter LF $4.45 5,000 $22,250.00
B-4 20" - 24" diameter LF $5.85 2,500 $14,625.00
B-5 27" - 42" diameter LF $7.00 1,000 $7,000.00
Heavy Cleaning (Up to 4 Line Passes in addition to Light Cleaning)
B-6 6" diameter LF $3.15 5,000 $15,750.00
B-7 8" - 12" diameter LF $2.15 10,000 $21,500.00
B
-
8
14" - 18" diameter LF $2.50 5,000 $12,500.00
B-9 20" - 24" diameter LF $8.25 2,500 $20,625.00
B-10 27" - 42" diameter LF $20.00 1,000 $20,000.00
Root Cutting
B-11 6" diameter LF $9.75 1,000 $9,750.00
B-12 8" - 12" diameter LF $11.00 2,500 $27,500.00
B-13 14" - 18" diameter LF $19.69 500 $9,845.00
B-14 20" - 24" diameter LF $24.00 500 $12,000.00
B-15 27" - 42" diameter LF $50.00 500 $25,000.00
Tuberculation Removal
B-16 6" diameter LF $10.54 1,000 $10,540.00
B-17 8" - 12" diameter LF $12.72 5,000 $63,600.00
B-18 14" - 18" diameter LF $14.32 5,000 $71,600.00
B-19 20" - 24" diameter LF $16.25 1,000 $16,250.00
B-20 27" - 42" diameter LF $61.29 500 $30,645.00
Service Lateral Clean & Inspection - Sanitary
C-1 Service Lateral CCTV Inspection EA $75.00 500 $37,500.00
C-2 Service Lateral Cleaning EA $100.00 500 $50,000.00
C-3 Service Lateral Tuberculation Removal LF $35.00 250 $8,750.00
C-4 Protruding Service Lateral Removal EA $950.00 100 $95,000.00
Mainline Cured In Place Pipe (CIPP) Installation - Sanitary
End Seals
D-1 6" Dia. End Seals (Per Segment) EA $52.50 100 $5,250.00
D-2 8" Dia. End Seals (Per Segment) EA $280.98 100 $28,098.00
D-3 10" Dia. End Seals (Per Segment) EA $316.06 100 $32,606.00
D-4 12" Dia. End Seals (Per Segment) EA $351.16 100 $35,116.00
D-5 14" Dia. End Seals (Per Segment) EA $388.48 50 $19,424.00
D-6 15" Dia. End Seals (Per Segment) EA $398.00 50 $19,900.00
D-7 16" Dia. End Seals (Per Segment) EA $447.34 50 $22,367.00
D-8 18" Dia. End Seals (Per Segment) EA $444.80 50 $22,240.00
D-9 20" Dia. End Seals (Per Segment) EA $630.74 50 $31,537.00
D-10 21" Dia. End Seals (Per Segment) EA $620.36 50 $31,018.00
D-11 24" Dia. End Seals (Per Segment) EA $667.18 50 $33,359.00
6" diameter
D-12 4.5 mm manufactured thickness (.177) LF $42.60 2,000 $85,200.00
8" diameter
D-13 6.0 mm manufactured thickness (.236) LF $43.94 5,000 $219,700.00
D-14 Add Item - 1.5mm increaser per LF LF $2.61 5,000 $13,050.00
10" diameter
D-15 6.0 mm manufactured thickness (.236) LF $50.95 2,500 $127,375.00
D-16 Add Item - 1.5mm increaser per LF LF $2.95 2,500 $7,375.00
12" diameter
D-17 6.0 mm manufactured thickness (.236) LF $57.01 2,500 $142,525.00
D-18 Add Item - 1.5mm increaser per LF LF $3.26 2,500 $8,150.00
14" diameter
D-19 6.0 mm manufactured thickness (.236) LF $67.26 2,500 $168,150.00
D-20 Add Item - 1.5mm increaser per LF LF $3.56 2,500 $8,900.00
15" diameter
D-21 7.5 mm manufactured thickness (.295) LF $71.18 2,500 $177,950.00
D-22 Add Item - 1.5mm increaser per LF LF $4.07 2,500 $10,175.00
16" diameter
D-23 7.5 mm manufactured thickness (.295) LF $83.41 2,500 $208,525.00
D-24 Add Item - 1.5mm increaser per LF LF $5.92 2,500 $14,800.00
18" diameter
D-25 7.5 mm manufactured thickness (.295) LF $90.75 5,000 $453,750.00
D-26 Add Item - 1.5mm increaser per LF LF $4.47 5,000 $23,700.00
20" diameter
D-27 7.5 mm manufactured thickness (.295) LF $104.34 2,500 $260,850.00
D-28 Add Item - 1.5mm increaser per LF LF $7.14 2,500 $17,850.00
21" diameter
D-29 9.0 mm manufactured thickness (.354) LF $118.80 1,000 $118,800.00
D-30 Add Item - 1.5mm increaser per LF LF $7.15 1,000 $7,150.00
24" diameter
D-31 10.5 mm manufactured thickness (.413) LF $138.92 1,000 $138,920.00
D-32 Add Item - 1.5mm increaser per LF LF $6.16 1,000 $6,160.00
46
27" diameter
D-33 10.5 mm manufactured thickness (.413) LF $151.89 1,000 $151,890.00
D-34 Add Item - 1.5mm increaser per LF LF $7.16 1,000 $7,160.00
30" diameter
D-35 12 mm manufactured thickness (.472) LF $185.69 1,000 $185,690.00
D-36 Add Item - 1.5mm increaser per LF LF $8.23 1,000 $8,230.00
36" diameter
D-37 12 mm manufactured thickness (.472) LF $214.11 1,000 $214,110.00
D-38 Add Item - 1.5mm increaser per LF LF $10.57 1,000 $10,570.00
42" diameter
D-39 13.5 mm manufactured thickness (.531) LF $281.52 1,000 $281,520.00
D-40 Add Item - 1.5mm increaser per LF LF $11.27 1,000 $11,270.00
Manhole External Drop Cured in Place Pipe Services
Drop Pipe Setup, CCTV, Cleaning and CIPP Installation
6" diameter
E-1 Setup, CCTV Inspection, and Cleaning EA 20
E-2 4.5 mm manufactured thickness LF 150
E-3 Add Item - 1.5mm increaser per LF LF 150
8" diameter
E-4 Setup, CCTV Inspection, and Cleaning EA 20
E-5 4.5 mm manufactured thickness LF 150
E-6 Add Item - 1.5mm increaser per LF LF 150
10" diameter
E-7 Setup, CCTV Inspection, and Cleaning EA 10
E-8 6.0 mm manufactured thickness LF 100
E-9 Add Item - 1.5mm increaser per LF LF 100
12" diameter
E-10 Setup, CCTV Inspection, and Cleaning EA 10
E-11 6.0 mm manufactured thickness LF 100
E-12 Add Item - 1.5mm increaser per LF LF 100
14" diameter
E-13 Setup, CCTV Inspection, and Cleaning EA 10
E-14 6.0 mm manufactured thickness LF 100
E-15 Add Item - 1.5mm increaser per LF LF 100
15" diameter
E-16 Setup, CCTV Inspection, and Cleaning EA 2
E-17 6.0 mm manufactured thickness LF 25
E-18 Add Item - 1.5mm increaser per LF LF 25
16" diameter
E-19 Setup, CCTV Inspection, and Cleaning EA 10
E-20 6.0 mm manufactured thickness LF 100
E-21 Add Item - 1.5mm increaser per LF LF 100
18" diameter
E-22 Setup, CCTV Inspection, and Cleaning EA 2
E-23 6.0 mm manufactured thickness LF 25
E-24 Add Item - 1.5mm increaser per LF LF 25
20" diameter
E-25 Setup, CCTV Inspection, and Cleaning EA 10
E-26 6.0 mm manufactured thickness LF 100
E-27 Add Item - 1.5mm increaser per LF LF 100
21" diameter
E-28 Setup, CCTV Inspection, and Cleaning EA 2
E-29 6.0 mm manufactured thickness LF 25
E-30 Add Item - 1.5mm increaser per LF LF 25
24" diameter
E-31 Setup, CCTV Inspection, and Cleaning EA 2
E-32 6.0 mm manufactured thickness LF 25
E-33 Add Item - 1.5mm increaser per LF LF 25
Lift Station External Drop Cured in Place Pipe Services
Drop Pipe Setup, CCTV, Cleaning and CIPP Installation
6" diameter
F-1 Setup, CCTV Inspection, and Cleaning EA 5
F-2 4.5 mm manufactured thickness (.236) LF 50
F-3 Add Item - 1.5mm increaser per LF LF 50
8" diameter
F-4 Setup, CCTV Inspection, and Cleaning EA 5
F-5 4.5 mm manufactured thickness (.236) LF 50
F-6 Add Item - 1.5mm increaser per LF LF 50
10" diameter
F-7 Setup, CCTV Inspection, and Cleaning EA 5
F-8 6.0 mm manufactured thickness (.236) LF 50
F-9 Add Item - 1.5mm increaser per LF LF 50
12" diameter
F-10 Setup, CCTV Inspection, and Cleaning EA 5
F-11 6.0 mm manufactured thickness (.236) LF 50
F-12 Add Item - 1.5mm increaser per LF LF 50
14" diameter
F-13 Setup, CCTV Inspection, and Cleaning EA 5
F-14 6.0 mm manufactured thickness (.236) LF 50
F-15 Add Item - 1.5mm increaser per LF LF 50
15" diameter
F-16 Setup, CCTV Inspection, and Cleaning EA 5
F-17 6.0 mm manufactured thickness (.236) LF 50
F-18 Add Item - 1.5mm increaser per LF LF 50
16" diameter
F-19 Setup, CCTV Inspection, and Cleaning EA 5
F-20 6.0 mm manufactured thickness (.236) LF 50
F-21 Add Item - 1.5mm increaser per LF LF 50
18" diameter
F-22 Setup, CCTV Inspection, and Cleaning EA 2
F-23 6.0 mm manufactured thickness (.236) LF 20
F-24 Add Item - 1.5mm increaser per LF LF 20
20" diameter
F-25 Setup, CCTV Inspection, and Cleaning EA 5
F-26 6.0 mm manufactured thickness (.236) LF 50
F-27 Add Item - 1.5mm increaser per LF LF 50
21" diameter
F-28 Setup, CCTV Inspection, and Cleaning EA 2
F-29 6.0 mm manufactured thickness (.236) LF 20
47
F-30 Add Item - 1.5mm increaser per LF LF 20
24" diameter
F-31 Setup, CCTV Inspection, and Cleaning EA 2
F-32 6.0 mm manufactured thickness (.354) LF 20
F-33 Add Item - 1.5mm increaser per LF LF 20
48
Mainline CIPP Ancillary Services
G-1 Lateral Service Reinstatement EA $354.10 200 $70,820.00
G-2 Segment Dewatering Operation (Well point) DAY $7,500.00 5 $37,500.00
Internal Spot Repair
8" diameter
G-3 316L Stainless Steel Mechanical Point Repair Insert EA $3,500.00 3 $10,500.00
G-4 4.5 mm manufactured thickness (4 LF Repair Length) EA $4,500.00 3 $13,500.00
10" diameter
G-5 316L Stainless Steel Mechanical Point Repair Insert EA $3,750.00 3 $11,250.00
G-6 4.5 mm manufactured thickness (4 LF Repair Length) EA $4,750.00 3 $14,250.00
12" diameter
G-7 316L Stainless Steel Mechanical Point Repair Insert EA $3,900.00 3 $11,700.00
G-8 4.5 mm manufactured thickness (4 LF Repair Length) EA $4,900.00 3 $14,700.00
14" diameter
G-9 316L Stainless Steel Mechanical Point Repair Insert EA $4,000.00 3 $12,000.00
G-10 4.5 mm manufactured thickness (4 LF Repair Length) EA $5,000.00 3 $15,000.00
15" diameter
G-11 316L Stainless Steel Mechanical Point Repair Insert EA $4,200.00 2 $8,400.00
G-12 4.5 mm manufactured thickness (4 LF Repair Length) EA $5,200.00 2 $10,400.00
16" diameter
G-13 316L Stainless Steel Mechanical Point Repair Insert EA $4,300.00 3 $12,900.00
G-14 4.5 mm manufactured thickness (4 LF Repair Length) EA $5,300.00 3 $15,900.00
18" diameter
G-15 Trenchless 316L Stainless Steel Mechanical Point Repair Insert EA $4,400.00 2 $8,800.00
G-16 4.5 mm manufactured thickness (4 LF Repair Length) EA $5,400.00 2 $10,800.00
20" diameter
G-17 316L Stainless Steel Mechanical Point Repair Insert EA $4,500.00 3 $13,500.00
G-18 4.5 mm manufactured thickness (4 LF Repair Length) EA $5,500.00 3 $16,500.00
21" diameter
G-19 Trenchless 316L Stainless Steel Mechanical Point Repair Insert EA $4,600.00 2 $9,200.00
G-20 4.5 mm manufactured thickness (4 LF Repair Length) EA $5,600.00 2 $11,200.00
24" diameter
G-21 Trenchless 316L Stainless Steel Mechanical Point Repair Insert EA $4,700.00 2 $9,400.00
G-22 4.5 mm manufactured thickness (4 LF Repair Length) EA $5,700.00 2 $11,400.00
G-23 Grout Injection Soil Stabilization (Cost + 10%) ALLOWANCE $25,000.00 1 $25,000.00
Service Lateral Cleanout Installation
H-1 4" Diameter PVC Cleanout Installation (Depth less than 5 feet) EA 150
H-2 6" Diameter PVC Cleanout Installation (Depth less than 5 feet) EA 50
H-3 Additional Material, Excavation and Compacted Backfill for Cleanout (5 feet to 10 feet in depth) EA 25
H-4 Provide and Install Cleanout Service Box and Cover (Composite) EA 200
H-5 Install Cleanout Service Box (Metal) (Owner to Provide Box and Cover Material) EA 15
H-6 Cleanout Sod Placement (25 SF per Cleanout Install) EA 200
H-7 Sidewalk and Driveway Concrete Repair (4 inch to 6 inch in thickness) SF 25
H-8 Asphalt Repair SF 50
Service Lateral Cured In Place Pipe (CIPP) Installation
I-1 Lateral Service CIPP Setup (1 per Mainline Segment) EA 50
I-2 4” Lateral up to 3' long in 8" main EA 100
I-3 4” Lateral up to 3' long in 10" main EA 25
I-4 4” Lateral up to 3' long in 12" main EA 25
I-5 6” Lateral up to 3' long in 8" main EA 10
I-6 6” Lateral up to 3' long in 10" main EA 10
I-7 6” Lateral up to 3' long in 12" main EA 10
I-8 Additional Length of CIPP (4" or 6" service) LF 2,500
Manhole Rehabilitation Services
Existing Manhole Liner Removal
J-1 HDPE Lining Removal (9 VF Avg. Depth) EA 2
J-2 Polymer/Epoxy Lining Removal (9 VF Avg. Depth) EA 25
J-3 Fiberglass Lining Removal (9 VF Ave. Depth) EA 5
J-4 Internal DIP Drop Pipe Removal (9 VF Avg Depth) EA 25
J-5 Inside Iron Step Removal per Manhole (5 Avg per MH) EA 100
J-6 Manhole Ring and Cover Remove and Replace (New Ring and Cover Provided by Owner) EA 200
J-7 Manhole Ring and Cover Adjustments LF 2
J-8 Exterior Severe Leak Stoppage/Groundwater Mitigation (Cost + 10%) ALLOWANCE 1 $50,000.00
Internal Manhole Minor Leak Stoppage
J-9 Manhole Depth - 0' to 5' EA 100
J-10 Manhole Depth - Over 5' to 10' EA 75
J-11 Manhole Depth - Over 10' to 15' EA 50
J-12 Manhole Depth - Over 15' to 20' EA 50
J-13 Manhole Depth -Over 20' EA 25
Bench Rehabilitation
J-14 Bench and Invert Demo, Repair and Rebuild 48" MH Diameter EA 150
J-15 Bench and Invert Demo, Repair and Rebuild 60" MH Diameter EA 50
J-16 Bench and Invert Demo, Repair and Rebuild 72" MH Diameter EA 25
J-17 Bench and Invert Demo, Repair and Rebuild 96" MH Diameter EA 5
Structural Build Back Rehabilitation Application
J-18A Structural Rebuild Layer (Build Back over 1" in thickness) - 48" MH Diameter VF 80
J-18B Structural Rebuild Layer (Build Back over 1" in thickness) - 60" MH Diameter VF 40
J-18C Structural Rebuild Layer (Build Back over 1" in thickness) - 72" MH Diameter VF 20
J-18D Structural Rebuild Layer (Build Back over 1" in thickness) - 96" MH Diameter VF 20
Rehabilitation Lining Application
J-19A Non-Structural Substrate Underlayment Layer 0.50" (13mm) Thickness Minimum - 48" MH Diameter VF 200
J-19B Non-Structural Substrate Underlayment Layer 0.50" (13mm) Thickness Minimum - 60" MH Diameter VF 20
J-19C Non-Structural Substrate Underlayment Layer 0.50" (13mm) Thickness Minimum - 72" MH Diameter VF 20
J-19D Non-Structural Substrate Underlayment Layer 0.50" (13mm) Thickness Minimum - 96" MH Diameter VF 10
J-20A Corrosion Protection Lining System 0.25" (6mm) Thickness Minimum - 48" MH Diameter VF 1,500
J-20B Corrosion Protection Lining System 0.25" (6mm) Thickness Minimum - 60" MH Diameter VF 250
J-20C Corrosion Protection Lining System 0.25" (6mm) Thickness Minimum - 72" MH Diameter VF 25
J-20D Corrosion Protection Lining System 0.25" (6mm) Thickness Minimum - 96" MH Diameter VF 15
J-21 Inside Drop installation (Hardware and Drop Provided by Owner) EA 25
49
Bypass Services
Low Flow By-Pass Setup (Less Than 500 GPM with 100% Onsite Redundancy)
K-1 Bypass Pump Setup EA $4,389.00 75 $329,850.00
Low Flow By-Pass Pumping Operations (Less Than 500 GPM)
K-2 Mainline CCTV Inspection Operation LF $1.43 15,000 $21,450.00
K-3 Lateral CCTV Inspection Operation (Avg of 7 Laterals per Mainline Segment) ($/LF of Mainline) LF $1.43 15,000 $21,450.00
K-4 Mainline Light Cleaning Operation (Up to 4 Line Passes) LF $1.43 15,000 $21,450.00
K-5 Mainline Heavy Cleaning Operation (Up to 4 Line Passes in addition to Light Cleaning) LF $4.00 5,000 $20,000.00
K-6 Light Tuberculation Removal (Up to 4 Passes with Cutting Tool) LF $4.00 5,000 $20,000.00
K-7 Heavy Tuberculation Removal (Up to 4 Passes with Cutting Tool in addition to Light Tub. Removal) LF $4.00 5,000 $20,000.00
K-8 Mainline CIPP Installation Operation LF $1.43 15,000 $20,000.00
K-9 Lateral CIPP Installation Operation (Avg of 7 Laterals per Mainline Segment) ($/LF of Mainline) LF 15,000 $21,450.00
K-10 High Flow By-Pass Setup (Greater Than 500 GPM with 100% Onsite Redundancy) (Cost + 10%) ALLOWANCE 1 $100,000.00
K-11 High Flow By-Pass Pumping Operations (Greater Than 500 GPM, no redundancy) (Cost + 10%) ALLOWANCE 1 $100,000.00
K-12 High Flow By-Pass Pumping Operations (Greater Than 500 GPM with 100% Redundancy) (Cost + 10%) ALLOWANCE 1 $150,000.00
Wastewater Hauling Operations
K-13 Initial Hauling Startup and Mobilization (6 Hour Min) EA $1,000.00 30 $30,000.00
K-14 Hauling (Up to 2000 Gal Debris Capacity) HR/TRK $350.00 500 $175,000.00
K-15 Hauling (2000 to 4000 Gal Debris Capacity) (10 Hr = 1 Day) DAY/TRK $3,500.00 100 $350,000.00
Bypass Ancillary Services
K-16 Roadway Hose Ramp Setup EA $250.00 150 $37,500.00
Maintenance of Traffic (MOT) Services
Traffic Control - Right of Way per FDOT Index
L-1 Maintenance of Traffic (Cost + 10%, without Flagmen) ALLOWANCE 1 $300,000.00
L-2 Flagmen (2 Required, 8 hour min) DAY $2,250.00 100 $225,000.00
General Conditions
Performance and Payment Bond (1% for Estimate Value Only) % 1% $64,428.00
Project Contingency (15%) % 15% $996,420.00
→→→Total Estimated Value $ 7,503,648.00