City of Winter Springs
East WRF GMP Presentation
CAROLLO / 2
•Schedule Update
•Review of Previous Cost Estimate
•GMP Presentation
•Design and Funding Updates
Meeting Agenda
CAROLLO |3
East WRF Schedule
2025 2026 2027 2028
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
SRF Funding Application and Approval
Finalization of Design and GMP
East WRF Material and Equipment Procurement
East WRF Construction
GMP Approval
CAROLLO / 4
•June 2025 Estimate
•Estimated Cost with contingency: $71,143,026
•Contingency: $10,429,339
•June to December Design Progression
•Wharton Smith, Carollo, and the City worked through value engineering as well as updated and added scope
•January 2026 Cost Estimate
•Estimated Cost with contingency: $72,840,907
•Contingency: $8,486,703
Evolution of Project Cost
CAROLLO / 5
•January 2026 Wharton-Smith publicly advertised 37 bid packages
•228 Questions were received during bidding
•5 Addendum were issued
•February 2026 Wharton-Smith received bids from 85 bidders
•Wharton-Smith and Carollo worked together to evaluate all bidders for accuracy, completeness, and general responsiveness
• March 2026 Wharton-Smith presented GMP to City Staff and Carollo for review & questions
GMP Process
CAROLLO / 6
•Total GMP with contingency: $65,847,589
•Contingency: $5,515,239
GMP Breakdown
CAROLLO / 7
Project Contingency & Allowances
•Risk Categories
•General, Final Design, Project Execution, Start-up and Closeout, Allowances
•Allowances
•Known Expenditures
•Contingency Development
•Contingency Reduction During Design
•Final GMP
•Mitigation Strategies
•Identified in the risk register
•Contingency Release Process
CAROLLO / 8
•Anticipated Mobilization: Early June 2026
•Anticipated Final Completion: November 2028
Construction Schedule
CAROLLO / 9
•Following Commission Approval:
•City Issues Construction Contract
•Wharton-Smith Issues Purchase Orders and Subcontracts to Bidders
•Continued Value Engineering
•Continual Review of the Risk Register
•Owner Direct Purchase – Sales Tax Savings
Next Steps
CAROLLO / 10
•Design
•East WRF design is complete; West WRF is to follow.
•FDEP permitting is complete.
•Additional permitting is underway.
•Funding is secured.
Design Updates
Insert rendering
CAROLLO / 11
•Funding
•Commission authorized project funding for design of both WRFs to be secured through Clean Water State Revolving Fund (CWSRF) financing on June 13, 2022.
•Design funding was secured
•CWSRF loan ($5,452,000)
•ARPA grant (remaining)
•Commission authorized project funding for construction of East WRF to be secured through CWSRF financing on November 10, 2025.
•Construction funding was secured:
•CWSRF loan ($54,179,318)
•Supplemental Appropriation for Hurricanes Helene & Milton loan with 50% principal forgiveness ($19,166,503)
•Protecting Florida Together grant ($600,000)
•Next Commission Approval:
•Project funding for construction of West WRF to be secured through CWSRF financing June 2027.
Funding Updates