REQUEST: The Public Works Department is advising the City Commission on current
progress of the Urban Beautification Division.
PURPOSE: This agenda item is to update the Commission on status of current Urban
Beautification projects and activities within the City of Winter Springs.
CONSIDERATION:
BOARDS
Tuscawilla Lighting and Beautification District - Beautification improvements are continually
underway consisting of landscaping and lighting enhancements. The main entrance lighting at
Tuskawilla Road is currently being upgraded to replace lights that become inoperative during
heavy rains. Annual color is being added at all entrances to further beautify the community. The
street lighting study with Progress Energy is still underway to determine cost feasibility of
installing lighting along roadways on Northern Way, Shetland, Tuscora, Howell Creek, Deer Run,
and Seneca. Upgraded street sign age in these areas is also being considered, bringing the estimated
capital project cost near $400,000.00. The Advisory Board expects to bring this project to the
Commission in November 2004. Designs and cost estimates are being drafted to add additional
tree canopy along Winter Springs Boulevard, in the Rights-of-way areas. P&L Lawn
Maintenance, grounds maintenance contractor, is performing to standard and communicating with
staff. The annual grounds maintenance contract was renewed on June 1 S\ 2004, with a current
contract value of$101,626.20.
Oak Forest Wall and Beautification District - The landscaping and irrigation capital project
along the Oak Forest wall is currently under review by the Commission. An Informational Agenda
item was submitted for the March 08, 2004 Commission meeting on this project. Government
Services Group has provided a revised critical events schedule for this project.
f
July 12,2004,2004
Information Item 305
Page 2
The Advisory Board is reviewing plans for a Lorie Taylor Memorial Garden to potentially be
installed on one of the Winter Springs Boulevard medians in Oak Forest. Entrance signs (8) at Oak
Forest are currently being re-painted at a cost of$2,100.00. Eastwood Tuff Turf, grounds
maintenance contractor, is performing to standard and communicating with staff. The annual
grounds maintenance contract was renewed on May 1 st, 2004, with a current contract value of
$8,004.00.
Beautification of Winter Springs - A complete landscape and irrigation plan for George Street is
currently under review by the Advisory Board. The Urban Beautification Coordinator, City
Arborist, and The Beautification of Winter Springs Advisory Board are working on a Draft Florida
Friendly Landscape Ordinance for the City of Winter Springs. The Board is also reviewing our
recent Arbor Day function and strategizing to improve the event for next year. Replacement of
expired plant material is currently in progress for the Moss Road and Murphy Road medians, as
discussed by the Advisory Board.
FACILITIES
Our facilities consist of City Hall, Public Safety Building, Public Works Building, the Fire
Stations, the Water Plants, and the Reclaimed Water Plants. The appearance of our facilities
continues to be upgraded with minor landscape enhancements at each location. Eastwood Tuff
Turf, the grounds maintenance contractor, is performing to standard. The annual grounds
maintenance contract was renewed on February 1 s\ 2004, and is currently valued at
$ 37,790.16 per year.
TUSKA WILLA ROAD
Designs are being developed for adding tree canopy along Tuskawilla Road in medians as well as
seasonal tree color. Eastwood Tuff Turf, the grounds maintenance contractor, is performing to
standard and communicating with staff. The annual grounds maintenance contract was renewed
on May 1st, 2004, with a current contract value of$ 40,875.00 per year.
CITY RIGHTS OF WAY, MEDIANS, AND PONDS
Fisher Road and landscapes related to the improvement project have been added to.the grounds
maintenance schedule at a cost of$975.00 per month. DawnaLee Corporation, grounds
maintenance contractor, is performing to standard and communicating on a weekly basis with
staff. The annual grounds maintenance contract, which started August 1 s\ 2003, is currently
valued at $110,025.00 per year.
SR 434 RIGHTS OF WAY, MEDIANS, AND PONDS
Plantings and sod installations are scheduled for the third quarter of 2004 for the SR 434 medians
between Tuskawilla Road and SR 419; where existing plant material has expired. Landscape
maintenance of the new plantings recently installed as part of the SR 434 Beautification Project
was started in May 2004, at a cost of$I,OOO.OO per month. Dora Corporation, the grounds
July 12, 2004, 2004
Information Item 305
Page 3
maintenance contractor, is performing to standard and communicating with staff. The annual
maintenance contract, which started October 1 st, 2003, is currently valued at $77,000.00 per year.
TOWN CENTER DISTRICT
The Town Center District currently consists of Market Square, Magnolia Square, and Blumberg
Boulevard; including rights-of-way areas in the vicinity. Grounds maintenance began in May
2004 for the Market and Magnolia Square areas at a cost of $1 ,214.33 per month. The initial
maintenance contractor, Ken-Lin Landscaping, will provide warranty and maintain the project
until September 30,2004, when the regular (1) year contract starts on October 1 st, 2004. The
landscape maintenance will be let for public bid in August 2004.
PROJECTS
SR 434 Beautification Project (Grant) - Funding amount $214,079.03 with installation by the
Public Works and Utility Departments. Installation of irrigation 98% complete, landscaping 95%
complete, with only the area directly around the Seminole County Bridge remaining. Project
deadline has been extended due to the Seminole County Bridge Project until
January 30, 2005.
Fisher Road - Landscape enhancements are scheduled to begin mid-July 2004. Improvements
will be made as per information contained in Agenda Item 306 from the May 10, 2004
Commission Meeting.
Tree Canopy Project - Phase 1 of the tree canopy project includes installing canopy trees along a
section of Winter Springs Boulevard near Northern Way and the medians on Tuskawilla Road.
The budget for phase I of the project will be $5,000.00 for installation plus costs to establish the
new trees. Canopy trees being considered for the project include, but are not limited to: Live
Oaks, Winged Elms, Sycamore (in limited quantities), Sweet Gum, Shmnard Oak, Tulip Poplar,
and Southern Magnolia.
COMMISSION ACTION: