REQUEST: Community Development Department is advising the City Commission of
the status of various current planning projects.
PURPOSE: This agenda item is to update the Commission on the status of current planning
projects.
CONSIDERATION:
Badcock Shopping Center - The final site plan, development agreement, and a general
depiction of signage were approved at the June 28, 2004, City Commission meeting. per
7/12/04 agenda.
Barclay Woods (Townhomes) - The latest iteration of final subdivision/engineering plan for
88 townhouse units on 7.45 acres (219 total parking spaces and no on-street parking) was
approved at the June 14,2004, City Commission meeting. per 6/28/04 agenda
Bruster's Ice Cream - Plans for a 1,213 square foot ice cream drive-thru facility on 1.35 acres
were submitted on May 5, 2004, and were reviewed at the May 18 DRC. The site is located at
the southeast comer of Costa Rica Drive and SR 434 and abuts Hacienda Village. The owner
and contractor have met with staff and the City Manager. per 7/12/04 agenda
Dlutz (Apex)Transmission Shop - The conditional use application, including a concept plan,
was approved by the City Commission at its April 26, 2004, meeting, a site plan was submitted
on June 7, and the site plan was reviewed at DRC on June 15. per 6/28/04 agenda
Dr. Courtney's Office - The base of the building has been re-painted from the previous bright
blue. Construction is rapidly approaching a certificate of completion (approval ofthe building
shell) and plans have been submitted for 2 tenant build-outs. per 7/12/04 agenda
Highlands Apts., Phase II - The 42 unit apartment (3 floor) final site plan was apfroved on
March 8, 2004. Clearing has been completed and a meeting was held on April 261 to address
the extension of potable water to the site (jack and bore in lieu of directional bore). GCI is
.'
July 12, 2004
Infonnation Item 300
Page 2
now making preparations for the jack and bore under Sheoah Boulevard to connect to the
City's water main. per 6/14/04 agenda
JDC Calhoun - Construction continues. Buildings 8, 9,10, 11, 12, 13, and 14 have received
certificates of occupancy (COs). Building 1 has received a temporary Certificate of
Completion and some Building No. 1 businesses are open (e.g. Tijuana Plats and the art
studio). Building 2 architectural renderings and conceptual shell building plans were approved
at the March 8, 2004, City Commission meeting. Both teams are proposed to meet on the
afternoon of May 24,2004, to review and discuss the building plans for Building 2.
City records indicate the following businesses are locating in the JDC Calhoun Town Center:
Building 1 - Tijuana Plats (restaurant), an art studio, a coffee shop, and a wine bar cafe;
Building 8 - Leslie Pool Supply, a dentist, tutor, and a tanning salon;
Building 9 - Red Bug Cleaners, E-Nails, Great Clips, and Subway;
Building 10 - Washington Mutual;
Building 11 - State Parm, H & R Block, Rachel Nicole's Salon, ShapeXpress, and a dentist;
Building 12 - Publix;
Building 13 - Winter Springs Liquors, Mailboxes, Etc., and Choice Cellular;
Building 14 - Papa Via's Take & Bake and China Peast; and
Building 15 - Wendy's.
A meeting was held on May 12, 2004, to discuss strategies for "taming" SR 434, to make it
more "pedestrian friendly." City staff and the applicable consultants (Dover Kohl & Partners,
Street Sense, Glatting-Jackson) met with the PDOT and then met with affected property
owners. per 6/14/04 agenda
Medallion Convenience Store - Pinal engineering/site plans were submitted for a convenience
store at the SW comer of SR 434 and Hayes Road, on March 24, 2004. This site is adjacent to
the intersection that was demonstrated to need an east-bound right-hand auxiliary turn lane.
The plans were reviewed at the April 6, 2004, DRC. Staff is investigating the legality of
leaving the existing tanks in the ground. per 6/28/04 agenda
Miranda - Site clearing is completed and no further activity has occurred on-site. per 7/12/04
agenda
Moss Road Townhomes - At its April 12, 2004, meeting, the City Commission approved the
Metropolis Homes conditional use application and concept plan to build as many as 84
condominiums and commercial development on an "L" shaped 9.10 acre site fronting on both
SR 434 and Moss Road, adjacent to the Nations Bank and Victorio's Pizza. per 4/26/04
agenda
Nursery Road (Phil Reece) - The final engineering/site plan was approved at the March 8,
2004, City Commission meeting and a preconstruction meeting was held on March 30. An
aesthetic review of the first new building is scheduled for this meeting. per 7/12/04 agenda
Oak Forest Unit 7 (Triangular-shaped O.86-Acre Tract between Oak Forest & Tuskawilla
Office Park) - BJM Associates has submitted a fully executed re-plat. It has been sent to the
City's surveying consultant for review for consistency with Chapter 177, Florida Statutes and
subsequent certification. A copy of the plat and pertinent support documentation has been
July 12,2004
1nfonnation Item 300
Page 3
provided to the City Attorney. Tinklepaugh Surveying reviewed and certified the plat. The
plat and supporting documents have been provided to the City Attorney for his review and
comment. per 5/24/04 agenda
Parkstolle - The FLU amendment was heard by the LP A at its September 3 and October 1,
2003, meetings and had a transmittal hearing at the October 27,2003, City Commission
meeting. The Commission adopted Ordinance No. 2003-35 at the January 12, 2004, City
Commission meeting. A PUD amendment, final subdivision plan, and final plat have been
provided to the City and were reviewed at the March 9, 2004, DRC. Revised plans were
resubmitted on April 23 and were reviewed at the May 4,2004 DRC. Staff received (June 16)
a traffic study modification, incorporating the AM peak traffic with the new elementary school
on SR 419. The plans are scheduled for the July 7,2004, P& Z meeting. per 7/12/04 agenda
SR 434 Retail (a.k.a. Villagio) - Vertical construction continues. The final segment of the
sanitary sewer construction has been installed. Permits for wall constmction are still pending.
The applicant submitted plans on June 15, scheduled for this meeting, to modify the site design
to include a drive-thru bank at one of the out-buildings. per 7/12/04 agenda
Tuscawilla Square - On June 2, 2004, a preliminary site plan was submitted for Tuscawilla
Square, a restaurant and retail development, totaling 13,600 square feet, on 1.41 acres at Gary
Hillary Drive (formerly Colt) Drive. The existing Tuscany Restaurant currently occupies a
portion of the site. The applicant has been negotiating a development agreement with the City
Manager and City Attorney. A re-submittal was provided July 2 and is scheduled for the July
20 DRC. per 07/12/04 agenda
Winter Springs Elementary (New -located on SR 419) - Construction continues. State
Representative David Mealor, City staff, and the FDOT have been investigating ways to
provide safe access to and from the school site. per 4/26/04 agenda
Winter Springs Town/zomes - Preliminary plans for approximately 420 town-homes on 40
acres within the Town Center were received from Engle Homes on July 2 and are scheduled
for the July 20 DRC. The applicant proposes to modify the park layout set forth in the Town
Center code. per 7/12/04 agenda
Board of Adjustment - No new variance or conditional use applications have been received.
per 7/12/04 agenda
FUNDING: None required
RECOMMENDATION: None required
ATTACHMENTS: None