COMMISSION AGENDA
ITEM 300
CONSENT
INFORMATIONAL X
PUBLIC HEARING
REGULAR
April 26, 2004
Meeting
MGR. ~/DEPT ff
Authorization
REQUEST: Community Development Department is advising the City Commission of
the status of various current planning projects.
PURPOSE: This agenda item is to update the Commission on the status of current planning
projects.
CONSIDERATION:
Badcock Shopping Center The traffic study is being reviewed by the City's consultants and
the site plan was reviewed at the October 7,2003, DRC. Revised final site plans were
reviewed at the April 6, 2004, DRC meeting. per 4/26/04 agenda.
Barclay Woods (Townhomes) - On the afternoon of April 16, 2004, the latest iteration of final
subdivision/engineering plan for 88 townhouse units on 7.45 acres was submitted for review.
The plans are scheduled for this City Commission meeting. The per 04/12/04 agenda
Dlutz Transmission Shop - On March 17,2004, the conditional use application package was
received by City staff. The application was reviewed by the DRC on March 30 and received a
hearing at the Board of Adjustment on April 1. The conditional use application, including a
concept plan, is scheduled for this City Commission meeting. per 4/26/04 agenda
Dr. Courtney's Office - Vertical construction continues. Storm-water and sanitary sewer lines
have been completed and inspected. per 4/12/04 agenda
Highlands Apts., Phase II - The 42 unit apartment (3 floor) final site plan was approved on
March 8, 2004. Another preconstruction meeting was held. Crews were to begin barricading
the trees that are to be saved and subsequently beginning site work. per 4/12/04 agenda
JDC Calhoun - Construction continues. Buildings 8, 9,10, 11, 12, 13, and 14 have received
certificates of occupancy (CDs). Building No.1 is under construction. Building 2
architectural renderings and conceptual shell building plans were approved at the March 8,
2004, City Commission meeting. Both teams met at City Hall and discussed how the Town
April 26, 2004
Infonnation Item 300
Page 2
Center Code (and other applicable codes) requirements will be addressed with Building No.2.
The next step is for the architect to design the structural components ofthe building.
Staff believes the development agreement needs to be amended to accommodate the doors at
buildings 1 and 2 that do not meet the 50 foot maximum separation requirement (Subsection
20-327 (d) of the City [Town Center] Code) and the 10 foot minimum clear height requirement
for awnings, marquees, colonnades, and arcades.
A new supplemental Agreement was proposed by the applicant's new attorney at the February
9, 2004, City Commission meeting, in response to the City's proposed Ordinance No. 2004-10.
The Agreement was not approved and Ordinance No. 2004 - 10 was approved on second
reading, with a third (adoption) hearing scheduled for March 8, 2004. Approval of Ordinance
No. 2004-10 was deferred at the March 8, 2004, City Commission meeting.
City records indicate the following businesses are locating in the JDC Calhoun Town Center:
Building 1 - Tijuana Flats (restaurant), an art studio, and a wine bar cafe;
Building 8 - Leslie Pool Supply, a dentist, tutor, and a tanning salon;
Building 9 - Red Bug Cleaners, E-Nails, Great Clips, and Subway;
Building 10 - Washington Mutual;
Building 11 - State Farm, H & R Block, Rachel Nicole's Salon, ShapeXpress, and a dentist;
Building 12 - Publix;
Building 13 - Winter Springs Liquors, Mailboxes, Etc., and Choice Cellular;
Building 14 - Papa Via's Take & Bake and China Feast; and
Building 15 - Wendy's.
per 4/26/04 agenda
Medallion COllvenience Store - Final engineering/site plans were submitted for a convenience
store at the SW corner of SR 434 and Hayes Road, on March 24, 2004. This site is adjacent to
the intersection that was demonstrated to need an east-bound right-hand auxiliary turn lane.
The plans were reviewed at the April 6, 2004, DRC. per 4/26/04 agenda
Mirallda - Site clearing has commenced. per 4/26/04 agenda
Moss Road Towllhomes - At its April 12,2004, meeting, the City Commission approved the
Metropolis Homes conditional use application and concept plan to build as many as 84
condominiums and commercial development on an "L" shaped 9.1 0 acre site fronting on both
SR 434 and Moss Road, adjacent to the Nations Bank and Victorio's Pizza. per 4/26/04
agenda
Nursery Road (Phil Reece) - The final engineering/site plan was approved at the March 8,
2004, City Commission meeting and a preconstruction meeting was held on March 30. per
4/12/04 agenda
Oak Forest Unit 7 (Triangular-shaped O.86-Acre Tract between Oak Forest & Tuskawilla
Office Park) - BJM Associates has submitted a fully executed re-plat. It has been sent to the
City's surveying consultant for review for consistency with Chapter 177, Florida Statutes and
subsequent certification. A copy of the plat and pertinent support documentation has been
provided to the City Attorney. Tinklepaugh Surveying reviewed the plat and has provided
comments to the City and BJM. per 3/08/04 agenda
April 26, 2004
(nfoonation Item 300
Page 3
Parkstone - The FLU amendment was heard by the LP A at its September 3 and October 1,
2003, meetings and had a transmittal hearing at the October 27,2003, City Commission
meeting. The Commission adopted Ordinance No. 2003-35 at the January 12,2004, City
Commission meeting. A Pun amendment, final subdivision plan, and final plat have been
provided to the City and were reviewed at the March 9, 2004, DRC. Staff awaits a resubmittal.
per 4/12/04 agenda
SR 434 Retail (a.k.a. Villagio) - Vertical construction continues. One segment of the sanitary
sewer construction will not take place until building is to a point that the construction of the
last section of sanitary will not conflict with vertical facet construction. The contractor is
preparing to install this segment of the sewer line. The masonry wall issue was settled when
the developer, the homeowners, and the City all agreed at the January 26,2004, City
Commission meeting to split the cost of raising the wall from 6 to 8 feet tall. per 4/12/04
agenda
Tuskawil/a Trails. - At its April 12, 2004, meeting, the City Commission accepted the
infrastructure that was to be conveyed to the City. per 4/26/04 agenda
Wagner's Curve (a.k.a. Heritage Park) - Revised building plans are being reviewed. Staff
has been working with the applicant to correct the gazebo. per 3/08/04 agenda
Winter Springs Elementary (New -located on SR 419) - Construction continues. State
Representative David Mealor, City staff, and the FDOT have been investigating ways to
provide safe access to and from the school site. per 4/26/04 agenda
Board of Adjustment - A conditional use for a major automotive service and repair facility
(transmission shop) along 17-92, north of Boat Lake and south of Shepard Road, is scheduled
to be heard at this City Commission meeting. per 4/12/04 agenda
FUNDING: None required
RECOMMENDATION: None required
ATTACHMENTS: None
COMMISSION ACTION: