REQUEST:
The Parks and Recreation Department would like to inform the City
Commission regarding the Central Winds Park Expansion.
PURPOSE:
The purpose of the item is to clarify the Park Expansion Phases.
CONSIDERATIONS:
. On January 26,2004, Commissioner Miller and Commissioner McLeod asked staff to
bring back information regarding the Central Winds Expansion.
. The phases of the project that are underway are:
1. Clearing, Grubbing, Storm water Ponds and Under Drains, Add Fill and
Final Grading. Funded by Bond Funds & FRDAP #4. Anticipated Completion,
April 2004. .
2. Central Winds Parkway Storm Water Piping. Funded by One Cent Sales Tax.
Anticipa.ted completion, July 2004.
3. Site Irrigation and Sodding. Funded by FRDAP # 5 and L.W.C.F. Grant.
Anticipa.ted completion, August 2004.
4. Install Portable Backstops, Football, Soccer, and Lacrosse Goals, Clay
Infields and Bike Trail. Funding by FRDAP # 6. Anticipated completion,
October 2004.
5, Central Winds Parkway Design, Permitting, Bid, Bid Award, and Construction,
Funded by One Cent Sales Tax. Anticipated completion, September 2005.
FUNDING:
Bond Funding, FRDAP #4, FRDAP #5, LWCF, FRDAP # 6, and One Cent
Sales Tax.
RECOMMENDATIONS:
N/A
IMPLEMENTATION SCHEDULE:
All phases are underway.
ATTACHMENTS:
Attachment # 1
A Cohesive park and practice field expansion plan.