HomeMy WebLinkAbout2003 07 14 Informational C I.T. Plan
COMMISSION AGENDA
ITEM C
Consent
Informational X
Public Hearing
Regular
July 14. 2003
Regular Meeting
fL-ge
Mgr, 1 Dept.
Authorization
REQUEST:
Information Services wishes to update the commission on
the status of the I.T. Plan created in FY 2002.
PURPOSE:
The purpose of this item is to update the commission on the I.T. Plan
which was created in FY 2002.
CONSIDERATIONS:
See attached Projects worksheet
FUNDING:
None
RECOMMENDATIONS: None
ATT ACHMENTS:
I.T. Projects worksheet - Attachment 1 (3 pages)
COMMISSION ACTION:
Regular Commission Meeting
Informational C
July 14, 2003
I.T. Strategic Plan
Status of Projects for FY 2003
A-1TfTc.>>\ ME-NT
If not
Items completed as completed,
of this date July 14, when is project
2003 denoted with expected to be
Project Due Date ./ completed
Server Upgrades - Attempt to move toward flat Windows 2000 Environment
City Hall PDC (move to Windows 2000 Server) 9/30/2003 ./
Exchange (move to Exchange 2000 and Windows 2000 Server) 9/30/2003 ./
Track-It Server (move to Windows 2000 Server) 9/30/2003 ./
WebSense/SuperScout (move to Windows 2000 Server) 9/30/2003 ./
File and Print Server (move from City Hall PDC to separate Windows 2000 Server) 9/30/2003 in progress 8/31/2003
Centralized Backup - City Hall Side
Network/backup analysis performed 9/30/2003 in progress 7/21/2003
Equipment and software purchase 9/30/2003 not yet started 7/31/2003
Installation & Implementation 9/30/2003 not yet started 8/31/2003
Network Infrastructure & Support Initiatives - to improve network performance and to
avoid data loss
Network analysis - entire network layout - hubs, switches, routers, etc. 9/30/2003 in progress 7/21/2003
Network analysis - Equipment and software purchase 9/30/2003 not yet started 7/31/2003
Network analysis - Installation and Implementation 9/30/2003 not yet started 8/31/2003
Remote Control/Support of Workstations 9/30/2003 ./
UPS for each workstation 9/30/2003 ./
Full Implementation of Blue Ocean Track-It! 9/30/2003 in progress 9/30/2003
Architectural Standards Policy 9/30/2003 in progress 9/30/2003
Operating Systems Upgrade from Windows NT 4 to Windows 2000 Server platform 9/30/2003 in progress 8/31/2003
Technology Policies & Procedures plan 9/30/2003 in progress 9/30/2003
VPN of I.S. Support 9/30/2003 ./
Disaster Recovery Plan 9/30/2003 in progress 9/30/2003
Full implementation of workgroup printing 9/30/2003 ./
WorkStation Upgrades
Revised 7 f712003
I.T. Plan Update July 14, 2003.xls
Page 1 of 3
Regular Commission Meeting
Informational C
July 14, 2003
I.T. Strategic Plan
Status of Projects for FY 2003
Analysis of systems that need to be upgraded in order to move away from Windows 98 I
platform 9/30/2003 ./
Purchase of Phase I Systems (PI! or below, running Windows 98) 9/30/2003 in progress 9/30/2003
Geographic Information Systems
Purchase of WorkStation GIS software for Community Development - Planning Division - 1
workstation 9/30/2003 ./
New Position - Media Specialist
Hire new Media Specialist (Web, Multimedia, and Application Specialist) 9/30/2003 ./
New Web Site Design
Survey and research changes needed for new web site to be more robust and effective for e-
government 9/30/2003 ./
Create demo of new web site and present to the City Commission 9/30/2003 in progress 7/14/2003
Obtain Commission authorization to proceed - new web site should be up and running 9/30/2003 not yet started 8/31/2003
City Forms Conversion to PDF
Research each departments forms and establish plan for their conversion 9/30/2003 in progress 7/31/2003
Implement conversion plan 9/30/2003 not yet started 9/30/2003
Document Management System
Research and put together RFP document
Establish whether or not we must go out to bid or if we can go with existing SNAPs 9/30/2003 in progress 7/21/2003
The rest of this project will depend upon the decision made with the previous item (re: bid)
may have to move this out to FY 2004 to give us more time. I.S. Shorthanded and have other
higher priorities
depends on
first to be imaged is Clerks records (old minutes, agendas, ordinances and resolutions) 9/30/2003 not yet started previous item
Munis Office Implementation
Implement and train on Munis Office 9/30/2003 ./
Munis/ForMunis Implementation
Revised 7/7/2003
I.T. Plan Update July 14, 2003.xls
Page 2 of 3
Regular Commission Meeting
Informational C
July 14, 2003
I.T. Strategic Plan
Status of Projects for FY 2003
Implement E-Purchase Orders I 9/30/2003 in progress 8/31/2003
Online Complaint Tracking (Better Place)
BetterPlace Online complaint tracking (this will be implemented with new web site) 9/30/2003 in progress 8/31/2003
Munis On-line initiatives
Establish Financial/credit card policies (Regular G - July 14, 2003 Commission Meeting) 9/30/2003 in progress 7/14/2003
Viewing of Utility Bills online (via internet - will be implemented with new web site) 9/30/2003 in progress 8/31/2003
depends on
Acceptance of bank drafts (Regular G - July 14,2003 Commission Meeting) 9/30/2003 not yet started previous item
Online payment of Utility Bills (via crediVdebit cards - Regular G - July 14, 2003 Commission depends on
Meeting) 9/30/2003 not yet started previous item
KIVA Interface
Research and outline scope of work for Munis/Kiva interface 9/30/2003 in progress 7/18/2003
Plan with implementors/programmers/City Staff 9/30/2003 not yet started 7/25/2003
Implement this interface 9/30/2003 not yet started 8/15/2003
MultiMedia Productions
Create multimedia productions for SGTV (this project may be delayed until FY 04) 9/30/2003 not yet started 8/15/2003
City Hall Access
Kiosk in lobby (this project was cut out for FY 03 and FY 04 by I.S. Director and City
Manager)
Cartegraph Software
Training and implementation of Cartegraph software for Public Works 9/30/2003 in progress 9/30/2003
Applications Training
on-going Munis and Kiva applications training ongoing I
on-going Microsoft Office modules training ongoing
Revised 717/2003
I.T. Plan Update July 14, 2003.xls