HomeMy WebLinkAbout2006 12 11 Regular 307 Vistawilla Office Center
CITY COMMISSION
ITEM 307
REGULAR
December 11. 2006
Meeting
REQUEST:
The Community Development Department requests the City Commission consider the proposed
development agreement modification for the Vistawilla Office Center, located on the south side
ofSR 434, just west of the Greeneway interchange.
PURPOSE:
To consider a request for the third modification to the development agreement Vistawilla Office
Center, a 79,800 square foot (S.F.) office complex, comprised of two (2) 3-story, 39,900 S.F.
buildings on a 9.17 acre site abutting SR 434 within the Tuscawilla Planned Unit Development
(PUD). The development is proposed in two phases. Phase I includes the westernmost building
and its associated parking area and dumpster. Phase II includes the second building, its
associated parking, and use of an existing curb-cut that serves as access to the Cross-Seminole
Trailhead area.
The site is subject to the SR 434 New Development Overlay Zoning District regulations (sections
20-463 through 20-474) and existing development agreement and settlement agreement. The
applicant has proposed a third modification to the development agreement to address the
following items:
1. Enhanced Landscaping along S.R. 434
2. Sidewalk layout along S.R. 434
3. Relocation of the project phasing line
4. Location ofthe proposed Centerline Homes sign
APPLICABLE LAW:
Chapter 166, Florida Statutes.
Development Agreement (DA) & Modifications
Chapter 9 (Code). Land Development.
December 11, 2006
Regular Agenda Item 307
Page 2 of 3
Chapter 20 (Code). Zoning.
CHRONOLOGY:
August 22, 2005 - City Commission approved Conceptual Plan (relative to the reduced setback
from 50' to 25' along SR 434) for construction of two office buildings totaling 79,000 SF.
January 23,2006 - Final engineering/site plan for Phase I and development agreement (DA)
approval.
April 24, 2006 - Aesthetic review for both buildings approved.
June 12,2006 - DA amendment approved to allow lighting before CO.
August 28, 2006 - Final engineering/site plan for Phase II approved.
CONSIDERATIONS:
A non-binding conceptual approval was granted for the project by the City Commission on
August 22,2005, for two (2) 39,500 S.F. buildings. The Commission and staff both supported a
deviation from the 50 foot SR 434 building setback, to move the buildings closer to the SR 434
right-of-way (ROW). This reduced setback is the basis for two of the items in this third
modification request for the development agreement. The applicant is requesting to use the
existing sidewalk in the S.R. 434 right-of-way instead of the meandering sidewalk as referenced
in the Original Development Agreement. This request is supported by staff because of the
reduced building setback approved by the Commission in 2005. Attachment B provides a
concept of this sidewalk layout. The enhanced landscaping that was discussed in the Original
Development Agreement will be reviewed by staff to ensure compliance with said agreement in
the context of the existing sidewalk layout.
The developer has requested that the phase line between phase 1 and phase 2 of the project be
shifted westward approximately 40 feet to the eastern exterior wall of the Phase 1 building. The
request will not affect the overall construction of the project and will accommodate the tilt-up
construction area necessary to construct the Phase 2 building.
Finally, Attachment C indicates a sign proposal for Centerline Homes to be placed on Building
# 1. Staff is bringing this item to the Commission because the letter "c" in the proposed sign is
larger than the 24" height stipulated in Section 20-470 (3-f). The letter "c" in the proposed sign
is 4' -5" in height. The sign will also be installed at a height greater than the 14' stipulated in
Section 20-470 (3-c). The proposed sign will be mounted on the third floor fa9ade of the
building and the approximate height to the top of the sign is 43'.
December 11, 2006
Regular Agenda Item 307
Page 3 of 3
FINDINGS:
1. The Vistawilla Office site is located on the south side of SR 434, west of the Greeneway
interchange and east of the Hess gas station, within both the Commercial portion of the
Tuscawilla PUD and within the SR 434 New Development Overlay Zoning District.
2. The Proposed third modification to the Development Agreement is consistent with the
overall design intent for the Vistawilla Office Center.
RECOMMENDATION:
Staff recommends that the City Commission approve the proposed third modification to the
existing Vistawilla Office Center development agreement to allow for certain modifications to
the sidewalk and landscaping layout along S.R. 434, to allow for a relocation ofthe phase line
approximately 40' westward to the eastern exterior wall of the Phase I Building, and to allow for
the installation of the Centerline Homes sign as depicted on Attachment C contained herein.
ATTACHMENTS:
A Draft Development Agreement
B. Sidewalk layout drawing
C. Centerline Homes Sign graphic
D. Selected Text from the Original Development Agreement
CITY COMMISSION ACTION:
ATTACHMENT A
DEVELOPMENT AGREEMENT - THIRD MODIFICATION
DEVELOPMENT AGREEMENT
TO BE PROVIDED BY
CITY ATTORNEY
ATTACHMENT B
SIDEWALK LAYOUT DRAWING
SR 434
ATTACHMENT C
CENTERLINE HOMES SIGN GRAPHIC
CENTERLINE HOMES
ATTACHMENT D
SELECTED TEXT FROM ORIGINAL DEVELOPMENT AGREEMENT
33 The City agrees that the enhanced landscaping together with a six foot masonry wall
at or along the rear (south) boundary of the property described on Exhibit "A" in the MasttJ,
Development Program separating the commercial property from the adjacent residentii
. 434 Corridor Vision Plan New Development Area Ordinance, constraints of the site and1
potential impact on the surrounding properties.
3.4 Landscape and wall construction plans shall be incorporated into the construction
documents. Failure of the Property Owner or his assigns to install the landscaping and six (6')
masonry wall (as lots are developed), agreed to and required by this Agreement shall be a
breach of this Agreement and shall constitute a basis authorizing of the City to withhold
issuance of permits, and/or certificates of occupancy, until the landscaping and wall
construction obligations imposed by this Agreement are fully complied with.
> 3.5
This Agreement obligates the Property Owner to install a meandering six (61) foot
wide sidewalk along the State Road 434 frontage of this property as shown on the Master
Development Program. The City acknowledges that the landscape design depicted on Sheet
3 of the Master Development Program requires use ofD.O.T. State Road 434 right-of-way
and modification of D.O. T. sidewalk placement and width requirements and therefore is
subject to review and approval by the D.O.T. It shall be the Property Owner1s obligation to
obtain said approval with the cooperation and assistance of the City.
In the event this
cannot be accomplished, the design shall be modified and all landscaping will be constructed
south of the road right-of-way within the Property Owner's property with the sidewalk being
constructed byF.D.O.T.
5
2.4 This Agreement does not and cannot exempt any real property from complying with
state or local law or ordinances relating to platting, environmental permitting, wetlands
regulations, stormwater, or other matters nor any development issues not directly addressee!:.
by this Agreement.
3.
Enhanced Landscaping. Sidewalks. WalL and Retention Ponds.
The development of all or any part of the real property described on Exhibit II All shall be subject to
the enhanced landscaping including berms and meandering sidewalks (to the extent such meanders
and additional width are allowed by the Florida Departp1ent of Transportation (DOT)), as set forth
on the Master Development Program for Tuscawilla Tract IS, Parcell-B (Sheets 2 & 3), dated
December 23, 1997, and revised February 23, 1998 and March 4, 1998, prepared by Bower-
Singleton and Associates, Inc. (hereinafter called the Mater Development Program), and on file with
the Office of the City Clerk, Winter Springs, Florida. The enhanced landscaping to be provided by
and at the cost to the Property Owner per the terms and conditions of the following:
3.1 The enhanced landscaping specified herein shall be provided by the Property Owner
or his heirs, assigns, successors, or agents, as a condition of development of the property and
at the time of installation of other site related improvements for each parcel created from the
real property described on Exhibit II A" of this Agreement.
3.2 The Hess site described on Exhibit liB II shall be, subject to and comply with the
landscaping specifications set forth on the Master Development Program, on file with the
Office of the City Clerk, Winter Springs Florida, as a Final Engineering Permit condition for
site development of said parcel.
4
TUSCAWILL TRACT 15
(PARCELS 18)
SIGNAGE LOCATION/LANDSCAPE BUFFER PLAN
CITY OF WINTER SPRINGS, FLORIDA
ROBERT YEAGER, TRUSTEE