REQUEST:
The Community Development Department requests the Commission consider the proposed
Development Agreement for the West End Professional Center. The West End Professional Center is
located on the south side ofS.R. 434, immediately west of Jesup's Reserve in the Town Center.
PURPOSE:
The purpose of this Agenda Item is for the Commission to consider the development agreement for the
West End Professional Center.
APPLICABLE REGULATIONS:
Chapter 166, Florida Statutes
Development Agreement (DA) & Modifications
Chapter 5, City Code
Chapter 9, City Code.
Town Center District Code (sections 20-320 thru 20-327).
CHRONOLOGY:
. February 27, 2006 - City Commission approval of the conceptual development plan for
the West End Center.
. June 26, 2006 - City Commission Aesthetic Review Approval (subject to Staffs
findings)
. August 14, 2006 - City Commission approved final engineering for Phase I
CONSIDERATIONS:
The West End Professional Center is located on 2.65 acres in the Town Center district, on the south side
ofS.R. 434, across from City Hall and immediately west of Jesup's Reserve.
Phase I consists of one 24,390 square foot three-story professional office building, a parking area
containing 105 parking spaces, a stormwater management system, utilities, landscaping,
December 11, 2006
Regular Item 306
Page 2 of 3
irrigation, hardscaping, and other associated improvements as shown on the attached final
engineering plans.
Phase II consists of a second 24,390 square foot professional office building and 23 additional
parking spaces. At buildout of both phases, there will be a total of 131 parking spaces serving
48,780 square feet of professional office space, for an overall parking ratio of 2.67 spaces per
1,000 square feet of gross building area.
The following items are addressed as part of the proposed Development Agreement:
1. The proposed building is located approximately 45-feet from the S.R. 434 right-of-way
line with a pedestrian plaza located between the building and the right-of-way and no
frontage road. This deviates from Section 20-325 (c) (8), which requires the typical
build-to line to be at the right-of-way of a frontage road parallel to S.R. 434.
2. The public sidewalk along the property frontage shall be located onsite in the plaza area,
with sidewalk connections to the existing sidewalks at both ends of the property. The
plaza area shall be maintained in perpetuity as fully accessible to the general public.
3. The design of seat walls are intended to be comfortable for sitting leisurely for extended
periods of time, and as such will be maintained for these public purposes.
4. The wall at the northeast comer shall connect to and be coordinated with the proposed
Jesup's Reserve wall.
5. The developer is responsible for obtaining permission from Levitt & Sons to construct the
improvements shown on Levitt's property along the eastern property boundary.
6. The Developer's Agreement shall provide permission from the City for the developer to
utilize the existing 30-foot wide City right-of-way along the southern property boundary
for parking and the stormwater pond.
7. Retaining walls may be utilized at the pond perimeter in lieu of 4: 1 side slopes as
required by Section 9-241.d.2.
8. FDOT does not require a right-turn deceleration lane, this will deviate from Section 9-
206.a and is recorded as part of the proposed Developer's Agreement.
9. Old Farm Road (Jesup's Reserve) shall be permitted to terminate at the West End Center
parking area.
10. Installation and ongoing maintenance of the trees in the plaza area shall be to the City's
satisfaction, and such trees shall be subject to replacement if they diminish in condition.
2
December 11, 2006
Regular Item 306
Page 3 of 3
FINDINGS:
1. The proposed development is located within the City of Winter Springs Town Center.
2. Deviations from the Code have been addressed in the proposed Development Agreement.
RECOMMENDATION:
Staff recommends the City Commission approve the proposed Development Agreement for the West
End Professional Center.
ATTACHMENTS:
A - Development Agreement
B - Final Engineering/Site Plan
COMMISSION ACTION:
3
ATTACHMENT A
DEVELOPMENT AGREEMENT
DEVELOPMENT AGREEMENT
TO BE PROVIDED BY
CITY ATTORNEY
ATTACHMENT B
FINAL ENGINEERING/SITE PLAN
WEST END CENTER ONE