HomeMy WebLinkAbout2003 02 24 Informational E Capital Improvement Projects
.
COMMISSION AGENDA
ITEM E
CONSENT
INFORMATIONAL X
PUBLIC HEARING
REGULAR
January 13, 2003
Meeting
MGR. ~/DEPT /~
Authorization
REQUEST: Public Works Department is advising the City Commission of the status of
various Capital Improvement Projects
PURPOSE: This agenda item is to update the Commission on the status of current Capital
Improvement projects.
CONSIDERATION:
. UTILITY
16" Water Distribution Main - Waiting to issue Completion Certificate. Waiting for as-builts and
final payment request. Tracer wire in fiber conduit pending. DEP certification received. (2/24/03)
East Water Reclamation Facility Filters - Project construction began on December 2,2002. Project
on schedule and 70% complete. Estimated completion is in March 2003. (1/6/03)
SR 434 Water Main (Vistawilla Road to Spine Road) - Design 90% complete. Waiting for
easements from Casscells and Schrimsher. (12/9/02)
Utility / Public Works Compound Force Main - Retained Lochrane Engineering to reuse the
Respite Center design for permitting and bidding. Permits pending for FDEP and CSX Railroads.
Additional CSX permit needed for fiber optic line. (1/6/03)
Utility / Public Works Compound - SRI conducting Needs and Space Analysis. Received bubble
diagrams and space request summarys. Conceptual building layout and site plan received 2/12.
(2/24/03)
Well #4 - CPH modifying Consumptive Use Permit to permit new proposed well location adjacent
to Northern Way in Trotwood Park. (12/9/02)
.
Reclaimed Water Augmentation - CPH analyzing current demands to' project future needs.
(12/9/02)
.
.
.
February 24, 2003
Infonnation Item E
Page 2
TRAFFIClTRANSPORTATION IMPROVEMENT
Tuskawilla Road / SR 434 Traffic Signal - Construction proceeding. Triple luminaires aproved by
City Commission and ordered. Waiting delivery of mast arms for traffic signal. Estimated
Completion May 2003. (2/24/03)
Main Street / Hickory Grove Streetscape - Low bid of $781,795.37 awarded to Gel. Waiting for
Esterson to complete project so no conflicts between the two contractors. Estimated Notice to
Proceed of April 1, 2003. (2/24/03)
SR 434 / Wagner's Curve Traffic Signal - Commission approved to piggyback off Seminole
County contract on 12/9/02. Preconstruction meeting held on December 26,2002. Received $25,000
from School Board for signal. Estimated completion May 2003. (2/24/03)
SR 419/ Edgemon Traffic Signal- LAP Agreement approved in November. FDOT will fund up
to $211,000 for the signalization and turn lane improvements. Final design underway. Projected
construction completion June 2003. (12/9/02)
SR 434/ Doran Drive Traffic Signal- CPH submitting warrant analysis to FDOT for approval. It
is likely the City Hall median opening will be required to be changed to a directional only to get
signalization at Doran Drive. (12/9/02)
SR 434 Improvements (Village Walk)- FDOT 90% design documents received in November,
project certified final plans design in March 2003. Construction projected for August 2003 through
April 2004. (1/6/03)
SR 434 Highway Beautification Grant - Funding amount approved $214,079.03. Received and
executed agreement forms. Construction scheduled to begin July 2003. Work to be performed by
Utility and Public Works Department staff (2/24/03)
SR 419/ Moss Road Turn Lane - Design 95% complete by PEC. FDOT permit pending. (1/6/03)
Cross Seminole Trail- 90% Design plans have been received. The proposed construction limits for
the paved are from Wade Street to approximately 500 east of Magnolia Park and from the SR 434
trail bridge to Gardena. The unpaved portion of the trail and paved portion in the middle of the
Schrimsher property impacted by the eagle are not included in the design. (12/9/02)
Pedestrian Bridge - Cross Seminole Trail - Approved by Seminole County Commission. The
design/build contract is 18 months with construction projected to begin in August 2003. (12/9/02)
Fisher Road - Design 90% complete. Received final design plans on 2/10/03. SJRWMD permit
submitted 12/15/02. (2/24/03)
.
.
.
February 24, 2003
Information Item E
Page 3
Central Winds Park Boulevard - Preliminary design underway by CPH in conjunction with
Michael Design Associates. Projected construction start date is July 2003 with a completion date of
January 2004. (12/9/02)
Winter Springs Boulevard Reconstruction - Design budgeted for this year. Waiting for proposals
from PEC. (2/24/03)
PARKS and RECREATION
Torcaso Park Expansion - Project substantially complete. Final punch list items were not
complete by 2/14 so Parks staff will complete and deduct from contract. (2/24/03)
Central Winds Park Expansion - Clearing of project site SJRWMD permit received. Bids received
January 29,2003 under review. (2/24/03)
COMMISSION ACTION: