REQUEST: Public Works Department Updating the City Commission on the Status of
the Town Center Roads project.
PURPOSE: The purpose of this agenda item is to update the City Commission on the progress
of the Town Center Roads project for January 2003.
CONSIDERA TIONS:
Attached is the January 2003 montWy progress report for the Town Center Roads
project. The project which includes the reconstruction and construction of Tuskawilla
Road and Hickory Park Grove Boulevard is 85% complete.
Schrimsher has executed the sanitary sewer easement and provided a special
warranty deed for the right of way conveyance. The City Attorney is reviewing the deed.
The project completion date is projected for March 19,2003, however, Florida
Power has not relocated the poles several of which are in the road.
ATTACHMENTS:
1. January Report
COMMISSION ACTION:
.
.
.
Hickory Grove Park Road
CPH Project No. W04100.1
Owner:
Contractor:
City of Winter Springs
Esterson Construction Co., Inc.
MONTHLY PROGRESS REPORT
February 6, 2003
Kip Lockcuff, City of Winter Springs
The following items reflect the current status of work completed for the above listed project:
1) The block column subcontractor has completed the construction of the block columns and
installation of the concrete caps around the retention pond. The aluminum fence
subcontractor has completed the installation of the aluminum fencing around the pond,
including the gates at the boat ramp and the pedestrian gate near the cell tower.
2) A final set of storm water as-builts for Hickory Grove Road and the retention pond have
been received by the Engineer and submitted to the water management district for
certification. To date the district has not provided a certification for this system.
3) The Contractor has completed construction of Hickory Grove Park Road including the
storm system and retention pond fencing. However, the final acceptance ofthe road is
pending completion of the punch list items for the road, which have been provided to the
Contractor in letter form, with attached plans depicting the areas of concern.
4) The Contractor has completed installation of the main trunk line for the gravity sanitary
sewer along Tuskawilla Road including the service laterals that cross Tuskawilla Road.
The Contractor has not scheduled an inspection with the City and the Engineer to review
this work. The Engineer has received as-builts for this portion of the system and has
received certification of the sanitary sewer system from FDEP.
5) The Contractor has completed the installation of the water main along Tuskawilla Road
from SR 434 north to the tie in point at the school road. The water line has been pressure
tested and witnessed by the City. The test was acceptable to the City. The Contractor is
to provide the as-builts and the bacteriological test results to the Engineer the week of
February 7, 2003. Once received, the Engineer shall submit the water line to FDEP for
certification.
6) The Contractor completed the storm water collection system along Tuskawilla Road on or
about January 31, 2003. The three large outfall structures have also been installed. The
Engineer and the City are scheduled to inspect the storm water system the week of
February 14,2003. There is still an issue with the modification to storm structure S-5.
.
.
'..
Currently, the City has rejected the modifications due to the limited access to the
structure.
7) To date there have been ten submittals for Change Orders.
The following items are items that are in progress:
1 Florida Power is to be contacted by Esterson Construction in an effort to coordinate
the relocation of the existing power utilities from the west side of Tuskawilla Road to
the east side. The Power Company has begun installation of the new utilities along the
east side of the road. Once completed, the power company is then scheduled to
relocate the existing utilities from the west to the east side of the road. The relocation
ofthe existing power poles is scheduled for mid-March per Florida Power.
2 The City and the Engineer have received a copy of the signed agreement from Mr.
Schrimsher dedicating additional right-of-way on the east side of Tuskawilla Road
from Mr. Schrimsher to the City. Additionally, Mr. Schrimsher has requested
additional parking spaces be added to the east side of Tuskawilla Road just north of
the McDonalds property. This information has been added to the plans and may result
in additional costs to construct the road.
3
The Engineer is coordinating with the Seminole County Trail Engineer. Possible
additional costs may result in changing from brick to asphalt at the Trail Crossing.
4 Due to the existing elevations on the school road at the intersection ofTuskawilla
Road, additional work is required of the Contractor to construct the intersection of the
School Road at Tuskawilla Road. This may also result in additional costs.
Please review the above listed items and if you have any comments or questions, please contact
Allen Lane.
Sincerely,
CPR ENGINEERS, INC.
Allen C. Lane, Jr.
CC: David Mahler, P.E.