HomeMy WebLinkAbout2002 05 13 Informational K Status of Town Center Roads Project
COMMISSION AGENDA
ITEM K
CONSENT
INFORMATIONAL X
PUBLIC HEARING
REGULAR ,
May 13, 2002
Meeting
MGR ~EPT In--
.
Authorization
REQUEST: Public Works Department Updating the City Commission on the Status of
the Town Center Roads project.
PURPOSE: The purpose of this agenda item is to update the City Commission on the progress
ofthe Town Center Roads project for April 2002.
CONSIDERATIONS:
Attached is the April 2002 monthly progress report for the Town Center Roads
project. The project was awarded to Esterson Construction at a cost of$1~883,215 and
includes the reconstruction and construction of Tuskawilla Road and Hickory Park Grove
Boulevard and their associated drainage, utilities, and brick pavers on TuskawiUa Road.
The completion date is November 2,2002. The project is approximately 8%
complete.
ATTACHMENTS:
1. April Report
COMMISSION ACTION:
A TT ACHMENT NO. 1
Owner:
Contractor:
City of Winter Springs
Esterson Construction Co., Inc.
CPH Engineers, Inc.
1117 East Robinson Street
Suite C
Orlando, Florida 32801
Phone: 407-425.0452
Fax: 407-648-1036
www.cphengineers.com
Hickory Grove Park Road
CPH Project No. W041 00.1
MONTHLY PROGRESS REPORT
April 29, 2002
Kip Lockcuff, City of Winter Springs
Kip,
The following items reflect the current status of work complete for the above listed project:
1. The retention pond. excavation is nearing completion. The Contractor is approximately
70 percent complete. Currently, the Contractor is excavating the top portion of the pond
down to elevation 38.00 in preparation of the trenching for the vinyl sheet pile. Once the
excavation is complete, the Contractor shall begin final grading on the side slopes. The
Contractor shall schedule the grading on the side slopes with the installation of the vinyl
sheet pile wall. Once the vinyl sheet pile wall is installed and the tie back system is in
place, the decorative block wall shall be constructed. As the wall is constructed, the soil
on the backside of the wall will be brought back up, in lifts, the surrounding finished
ground elevations. Once the excavation is complete, the Contractor shall begin final
grading on the side slopes.
2. Installation of the storm water'collection system has begun. Currently, the 42-inch pipe
from manhole S19 to S15 has been installed including all storm manholes. A portion of
the backfill and compaction from manhole S19 to S17 has been completed. The
Contractor is currently working on installing. the balance of the 42" storm pipe from
manhole S15 to inlet S10, near the intersection of SR 434 and Hickory Grove Park
Road.
3. To date there have been no submittals for change orders. CPH Engineers has reviewed
the second pay request and has determined that there will be ,at a minimum two change
orders for the project. Once the project is complete, the Engineer will review a final
quantities change order.
4. The City and the Contractor have received revised plans showing the parking spaces
sloping towards the flow line along the edge of pavement for both Tuskawilla and
Hickory Grove Park Roads.
The following items are items that are in progress:
1 The locations of the right-of-way and utility easement areas along the east side of
Tuskawilla Road have been drafted by Tinklepaugh Surveying. Tinklepaugh is
SANFORD . ORLANDO . OELAND . PALM CITY CAPE CORAL . JACKSONVILLE . PALM COAST . PUERTO RICO
~~ "'..
currently drafting the legal descriptions written. This will be forwarded to the
Engineer once completed.
2 The location and description of the additional right-of-way along the south and east
side of Hickory Grove Park Road and along the west side of Tuskawilla Road at SR
434 have been completed. The descriptions have been forwarded to Tinklepaugh
Surveying for their review and confirmation. The proposed RfW dedication for
Hickory Grove Park Road appeared to be correct. The City was notified of this. The
proposed dedication on the west side of Tuskawilla was not correct and this
description is being redone.
3 The location of the Florida Power "switch gear" still needs to be finalized. It is our
understanding the location is to be inside the Doran site adjacent to right-of-way line
on the west side of Tuskawilla Road.
4 CPH is has received a revised cost estimate for the revisions to the plans at the
intersection of Hickory Grove Park Road and SR 434. Once approved by the City,
they shall be incorporated into the construction of the project.
5 CPH has received a cost estimate for a proposed force main to be installed from the
south side of SR 434 to the first sanitary sewer manhole on Hickory Grove Park
Road. This item has been forwarded to the City for approval.
Please review the above listed items and if you have any comments or questions, please
contact Allen Lane.
Sincerely,
CPH ENGINEERS, INC.
~ne~~
CC: David Mahler, P.E.
J:\W041 00. 1 \WDl0429 Monthly Reporl.DOC