REQUEST: Community Development Department is advising the City Commission of
the status of various current planning projects.
PURPOSE: This agenda item is to update the Commission on the status of current planning
projects.
CONSIDERATION:
Avery Park - Construction continues. The Contractor has obtained a permit to install the water
fountain the storm-water pond. A letter of credit in the amount of$26,710.00 was issued April
2 and received by the Community Development Department on April 8, 2002, in lieu of a
maintenance bond for the potable water and sanitary sewer improvements to be accepted by the
City. The original was provided to the City Clerk and a copy to the City Attorney.
Belfaire(formerly Battle Ridge) - No activity.
B. V. Models- On March 27, staff received the application and plans for preliminary site plan
review for a 1,600 square-foot single story addition to an existing commercial structure at 170
SR 419. This item was reviewed at the April 2, 2002, DRC.
Fox Run Preliminary Subdivision Plan- On March 26, staff received the application and plans
for preliminary subdivision of a 5-10t residential subdivision on 1.28 acres at the west end of
Panama Circle. This item was reviewed at the April 2, 2002, DRC.
Highlands Apts., Phase II - The 42 unit apartment preliminary site plan was approved on
April 22, 2002. Staff awaits a final site plan submittal.
JDC Calhoun - Construction continues. The applicant has been notified of the modifications
required by the City Commission, in its capacity as the DRC, at the April 22, 2002 meeting.
May 13, 2002
Information Item A
Page 2
Miranda - There has been no activity since staff provided an amended draft development
agreement back to the applicant. The special exception to allow automotive repair in the Town
Center expired on April 22, 2002. The applicant and his contractor scheduled a meeting with
staff for May 1, 2002. At that meeting, Mr. Miranda stated that he plans to proceed with his
plans to construct his auto-repair facility at the site.
Nursery Road (Phil Reece) - Staff met with Mr. Reece on April 16, 2002, to discuss a revised
draft development agreement. The FLU amendment and rezoning are tentatively scheduled for
June 10, 2002.
Oak Forest Unit 7 (Triangular-shaped O.86-Acre Tract between Oak Forest & Tuskawilla
Office Park) - The City-initiated Future Land Use map amendment and rezoning had first
readings at the April, 8, 2002, City Commission meetings are tentatively scheduled for the
May 13, 2002, City Commission meeting, due to public notice requirements.
Parkstone - Construction continues.
SR 434 Retail(a.k.a. Vil/agio) - The project was scheduled to be heard at the May 1, 2002,
Planning and Zoning Board. The applicant requested the item be postponed to try to resolve
the Stone Gable homeowners and engineering issues. The P & Z Board voted to postpone the
item and the applicant volunteered to notify the president of the homeowners' association
when the project is re-scheduled for the P & Z.
SR 434 Roadway Improvements Project - No additional information.
Torcaso Park Improvements- On March 27, staff received the final engineering/site plan for
the City's Torcaso Park improvements. This item was reviewed at the April 2, 2002, DRC
meeting.
Tuskawil/a Office Park - Construction is proceeding.
Tuskawilla Trails. - The preliminary subdivision plan received a recommendation for
approval at the May 1, 2002, Planning and Zoning Board.
Wagner's Curve - The preliminary subdivision plan was approved at the April 22, 2002, City
Commission meeting. Staff awaits submittal of the final subdivision plans.
Board of Adjustment - The Board of Adjustment (BOA) will meet on May 2, 2002, to
consider a request to remove, rebuild, and enlarge a screen room as much as 7 feet into a 25'
rear yard building setback.
Staff is awaiting a re-submittal from the applicant at 1521 W oodsglen Drive. The matter was
heard at the December 6,2001, BOA meeting, for a variance for an addition to encroach 8 feet
into the 20 foot rear yard setback set forth for Fox Glen at Chelsea Park. The BOA requested
that the applicant bring in other alternative designs with less encroachment.
FUNDING: None required
May 13, 2002
Information Item A
Page 3
RECOMMENDATION: None required
ATTACHMENTS: None
COMMISSION ACTION: