REQUEST: Community Development Department is advising the City Commission of
the status of various current planning projects.
PURPOSE: This agenda item is to update the Commission on the status of current planning
projects.
CONSIDERATION:
Avery Park - Cons~ction continues. The developer is investigating the possibility of
cantilevering the wall of a proposed domicile at lot 18 over the property line and into the air-
space above the common up-land area adjacent to and associated with the storm-water pond.
Belfaire(formerly Battle Ridge) - In May, all files and correspondence relating to the final
engineering/subdivision plan and modification to the annexation and pre-development
agreement were copied for Stenstrom, McIntosh, Colbert, Whigham and Simmons (the City of
Oviedo's Attorney). Construction has been proceeding. A representative from both the
Seminole County Planning Department and the Black Hammock citizens group inspected the
approved plan and the First Addendum to the Annexation and Pre-development Agreement.
Fox Run Preliminary Subdivision Plan- On March 26, staff received the application and plans
for preliminary subdivision of a 5-10t residential subdivision on 1.28 acres at the west end of
Panama Circle. This item was reviewed at the April 2, 2002, DRC. Staff awaits a re-
submittal.
Garcia Driveway Re-locate. - Staff received an application from Manny Garcia to relocate a
private drive/roadway from Tuscawilla Unit 5 onto an adjacent portion of Oak Forest Tract
"A" that Mr. Garcia owns. The item was initially scheduled for the June 18, 2002, DRC, but
was re-scheduled for the July 2, 2002, DRC. Staff received a partial response t~ the DRC
comments and awaits a complete response.
August 12, 2002
Information Item A
Page 2
Highlands Apts., Phase II - The 42 unit apartment preliminary site plan was approved on
April 22, 2002. The final engineering/site plan re-submittal was reviewed at the July2, 2002,
DRC and plans are being revised for the City Commission review.
JDC Calhoun - Construction continues. Buildings 9 and 11 are under construction. Buildings
13 and 14 are still in the permit stage. No solution for the Wendy's (Building No. 15) drive-
thru access has been reached. Any modification of the approved site plan must be approved by
the City Commission. Building 10 (Washington Mutual) received a special exception but has
not submitted building plans.
Miranda - Staff awaits a site plan submittal.
Nursery Road (Phil Reece) - Staff awaits a building plan submittal for the walls and
engineering plans for the storm-water pond.
Oak Forest Unit 7 (Triangular-shaped O.86-Acre Tract between Oak Forest & Tuskawilla
Office Park) - Staff has visited the site to determine the veracity of allegations about the w~ll
and trees. City staff met with one of the City's surveying consultants to try to find an
affordable solution to the subdivision process.
Trees that the homeowners removed without a permit have not been replaced.
Parkstone - Construction continues. Since the City Commission accepted those potable
water and sewer improvements that were to be dedicated to the City, the applicant has
requested that the. -performance.--bonds - (guaranteeing their. installation)-for--units-.J -and. 4 be -..
returned.
SR 434 Retail(a.k.a. ViI/agio) - The FDOT conducted a meeting to discuss access
alternatives. The applicant has submitted another site plan design, minus the cross-access
between the site and Stone Gable Circle, with two curb-cuts onto SR 434, and with a relocated
median-cut. The applicant has contacted the HOA to meet with them about the project
(08/05/02 at 6:30 P.M.). The final site plan is scheduled for the August 7, 2002, Planning and
Zoning Board meeting.
SR 434 Roadway Improvements Project - No additional information.
Torcaso Park Improvements- On March 27, staff received the final engineering/site plan for
the City's Torcaso Park improvements. This item was reviewed at the April 2, 2002, DRC
meeting.
Tuskawilla Office Park - C.onstruction is proceeding. The final plat was recorded with the
Clerk of the Circuit Court. A proposed entry feature with signage was forwarded to Dover
Kohl for review, but no solution has been attained.
Tuskawilla Trails. - The preliminary subdivision plan (36 lots and a storm-water pond on 8.64
acres) was approved at the June 10, 2002, City COjnmission meeting. Staff awaits submittal of
the final engineering plans.
August 12,2002
Information Item A
Page 3
Wagner's Curve - The final subdivision plan was submitted May 24, 2002, and reviewed at
the June 4, 2002, DRC meeting. Staff awaits a re-submittal of the final subdivision plans.
Winter Springs Elementary. - A site plan for a 15,000 SF learning center, to replace existing
portables, was received May 3,2002, and reviewed at the May 21,2002, DRC. Are-submittal
was reviewed at the June 18,2002, DRC.
Board of Adjustment - The Board of Adjustment (BOA) met on August 1 to consider 2 rear-
yard building setback requests.
FUNDING: None required
RECOMMENDATION: None required