REQUEST: Public Works Department is advising the City Commission of the status of
various Capital Improvement Projects
PURPOSE: This agenda item is to update the Commission on the status of current
Capital Improvement projects.
CONSIDERATION:
TRAFFIClTRANSPORTATION IMPROVEMENT
SR 434 Improvements (Village Walk) - Mast Arm Signals have been delivered and are
scheduled for installation. Irrigation has been installed in all medians and in the plant beds
east of Moss Road. Irrigation mainline from SR 419 to Moss Road is tested and complete
except for the intersections at Sherry and Wade. Mainline installation continues west of
Moss Road on the north side of 434. Directional bores are proceeding in front of irrigation
installation. Tree and plant installation to begin after installation of electrical power for
controller at the Moss Road connection. Expected completion of contract has been moved
out past the end of August. Change orders allowing extra time for storm delays, holidays
and construction of the city requested turn lane at Moss to be presented at the August 28
Seminole Commission Meeting. (7/27/05)
SR 434 Town Center Corridor Analysis - The draft report was delivered on March 21 st and staff
is working with Glatting Jackson representatives to schedule a meeting with FDOT. Crash data
is being assimilated into the report. (4/18/2005)
SR 434 / Doran Drive Traffic Signal - This is a joint design project with CPH Engineers and
PEC, Inc. The project involves installation of a traffic signal at Doran Drive and SR 434. Notice
of Award mailed to Traffic Control Devices week of February 7th. Final design of the
intersection with the addition of Jesup's Reserve entrance is pending review from FDOT
for intersection modifications. (7/27/05)
SR 419/ Moss Road Turn Lane - Construction is complete, requirements for transfer of the
funds from FDOT pending receipt of certified as-built plans from contractor. As-built plans
August 8, 2005
Information Item 303
Page 2
received and have been forwarded to FDOT for direction regarding approximately 150 feet
where a portion of the required super elevated curve of7.5% is sub standard at 3.5 to 4% slope.
(5/11/05)
Cross Seminole Trail North (Wade Street to Town Gardena Avenue) - Construction continues
by Schuller Contractors, Inc of Orlando on this $1,589,000.00 project. The proposed
construction limit for the 3.5 miles of paved trail is from Gee Creek (500 feet east of Wade
Street) to approximately 500 east of Magnolia Park and from the SR 434 trail bridge to Gardena
Avenue. The portion ofthe trail in the middle of the Schrimsher property impacted by the eagles
nest is not included in the project. County staff hopes to perform this work as part of this
contract. Bridge work continues with delays in the re-design of handrails. Sodding
continues along the length of the trail. Signage and hardscape features still awaiting
installation. (7/27/05)
Cross Seminole Trail Connector (Wade Street to Wekiva Trail) - Staff is working with County
staff on evaluating the wetlands along the preferred route. The City Manager and Mayor are
working with Rep. Mealor on state and/or federal funding for this alternative. The wetlands have
been flagged and staff met with Seminole County and the consultant on May 25th.. Seminole
County has turned further development of the alternate trail corridor over to the city for
further planning. (7/27/05)
Magnolia Park Phase II - Phase II of Magnolia Park consists of the construction of the
Amphitheater with restrooms and drinking fountains to act as a trail head for the Cross Seminole
Trail and an inter active water feature in this 0.67::1:: acres. Starmer Ranaldi Planning and
Architecture, Inc (SRI) was approved by the Commission on January 10, 2005, for the
architectural services. CPH Engineers, Inc has been authorized by the Commission under
Amendment 78 on June 9, 2003, for services related to the landscape and hardscape design in
conjunction with SRI. Both SRI and CPH Engineers are currently developing the plans for the
construction of Magnolia Park Phase II. Progress meeting held on May 2nd to review CPH
drawings and coordinate with SRI. (5/11/05)
Blumberg Boulevard Trail - The Blumberg Boulevard Trail consist of the construction of the
trail with amenities from Magnolia Park to the intersection of Blumberg Boulevard and Doran
Drive. The trail will have stone pavers with sitting arboretum and proposed sculpture gardens, to
include the Rotary Club sponsored Veterans Memorial. Starmer Ranaldi Planning and
Architecture, Inc (SRI) was approved by the Commission on January 10, 2005, for the
architectural services. CPH Engineers, Inc has been authorized by the Commission under
Amendment 78 on June 9, 2003, for services related to the landscape and hardscape design in
conjunction with SRI. Progress meeting held on May 2nd to review CPH drawings and
coordinate with SRI. (5/11/05)
Central Winds Park Way - Final road design ongoing by CPR. Additional right of way has
been requested from the Leerdam property and they will be submitting a conceptual site plan to
the City Commission. Final Plan review will incorporate their proposed site plan. (4/18/05)
Winter Springs Boulevard Reconstruction - Preliminary report was presented to the City
Commission on April 11th. Staff is evaluating the costs of all projects in the One Cent Sales Tax
August 8, 2005
Information Item 303
Page 3
to develop a schedule. Received initial cost estimate for reconstruction at 2.4 million dollars.
(4/18/05)
UTILITY
Utility/Public Works Compound - Design is 90% complete. Plan review process ongoing.
FDEP and Corps of Engineers permit application submitted and comments received. Re-
submittal for staff review pending. FDEP has approved the mitigation plan portion of the permit
application. The cost of wetland mitigation for eight acres is $69,000.00. Awaiting issuance of
permit from FDEP. (7/27/05)
Well #4 - Sunshine Building and Development is contractor for this project. Both the first well
and test well were grouted as of 4/7/2005. Well is in development stage. (7/27/05)
Reclaimed Water Augmentation - Consultant provided with staff comments on July 13th.
Customer connection history being developed for projection purposes. (8/8/05)
Tuskawilla Road Stormwater Improvements - The scope of this project to install two 24" storm
pipes and fill the existing ditches along with a strainer/ trash collection box with spreader swale
to improve the quality of run off entering Lake Jesup from Tuskawilla Road North of St. Johns
Landing and Orange Avenue. The contract was awarded to Sunshine Building and Development
with a pre-construction meeting held on June 16th. Construction began the week of July 25.
Contractor has laid approximately 40% of storm pipe. (8/1/05)
PARKS and RECREATION
Central Winds Park Expansion Back Stops - Contract awarded to All-Rite Fence with
Notice to Proceed issued the week of 1 August. (7/27/05)
PUBLIC BUILDINGS
City Hall Expansion - The design of the expansion of City Hall was approved by the
Commission on February 28, 2005. Starmer Ranaldi Planning and Architecture, Inc (SRI)
provided the design of this 4,980 square foot addition to City Hall in the northwest comer of the
City Hall building. New layout presented to Commission at 8/1 workshop and direction
received. (8/8/05)