HomeMy WebLinkAbout2002 08 26 Informational A NEW Current Planning Projects
.'
COMMISSION AGENDA
ITEM A
CONSENT
INFORMATIONAL X
PUBLIC HEARING
REGULAR
08/26/02
Meeting
MGR. ~/DEPT /tf/
Authorization 01
REQUEST: Community Development Department is advising the City Commission of
the status of various current plaHlning projects.
PURPOSE: This agenda item is to update the Commission on the status of current planning
projects.
CONSIDERATION:
A very Park - Construction continues.
Belfaire(formerly Battle Ridge) - In May, all files and correspondence relating to the final
engineering/subdivision plan and modification to the annexation and pre-development
agreement were copied for Stenstrom, McIntosh, Colbert, Whigham and Simmons (the City of
Oviedo's Attorney). Construction has been proceeding. A representative from both the
Seminole County Planning Department and the Black Hammock citizens group inspected the
approved plan and the First Addendum to the Annexation and Pre-development Agreement.
Engle Homes is investigating the process for providing a sales trailer on-site.
Fox Run Preliminary Subdivision Plan- On March 26, staff received the application and plans
for preliminary subdivision of a 5-lot residential subdivision on 1.28 acres at the west end of
Panama Circle. This item was reviewed at the April 2, 2002, DRC. Staff awaits a re-
submittal.
Garcia Driveway Re-locate. - Staff received an application from Manny Garcia to relocate a
private drive/roadway from Tuscawilla Unit 5 onto an adjacent portion of Oak Forest Tract
"A" that Mr. Garcia owns. The item was initially scheduled for the June 18, 2002, DRC, but
was re-scheduled for the July 2, 2002, DRC. Staff received a partial response to the DRC
comments and awaits a complete response.
August 26, 2002
Information Item A
Page 2
Highlands Apts., Phase II - The 42 unit apartment preliminary site plan was approved on
April 22, 2002. The final engineering/site plan was scheduled on the August l2 City
Commission agenda, but was not heard. It is continued on this agenda.
JDC Calhoun - Construction continues. Buildings 9 and 11 are under construction. Buildings
13 and 14 are still in the permit stage. No solution for the Wendy's (Building No. 15) drive-
thru access has been reached. Any modification of the approved site plan must be approved by
the City Commission. Building 10 (Washington Mutual) received a special exception but has
not submitted building plans.
Miranda - Staff has conducted a pre-application conference with the applicant's engineer and
awaits a site plan submittal.
Nursery Road (Phil Reece) - Staff awaits a building plan submittal for the walls and
engineering plans for the storm-water pond.
Oak Forest Unit 7 (Triangular-shaped O.86.:Acre Tract between Oak Forest & Tuskawilla
Office Park) Trees that the homeowners removed without a permit have not been replaced.
Parkstone - Construction continues. Since the City Commission accepted those potable
water and sewer improvements that were to be dedicated to the City, the applicant has
requested that the performance bonds (guaranteeing their installation) for units 3 and 4 be
returned. A letter was sent to the bonding company clarifying this and that the City is ready to
return the bonds.
SR 434 Retail(a.k.a. Villagio) - The FDOT conducted a meeting to discuss access
alternatives. The applicant has submitted another site plan design, minus the connection to
Stone Gable Circle, with two curb-cuts onto SR 434, and a median-cut to serve the project.
The applicant has held a meeting with the homeowners to discuss potential ways to mitigate
the effects of the project (08120/02 at 6:30 P.M.). The City Engineer and Current Planning
Coordinator attended the meeting and answered homeowner questions about the City's
requirements.
SR 434 Roadway Improvements Project - No additional information.
Torcaso Park Improvements- On March 27, staff received the final engineering/site plan for
the City's Torcaso Park improvements. This item was reviewed at the April 2, 2002, DRC
meeting. The City Engineer is working on plans for the park.
Tuskawilla Office Park - Construction is proceeding. A proposed entry feature with signage
was forwarded to Dover Kohl for review, but no solution has been attained.
Tuskawilla Trails. - The preliminary subdivision plan (36 lots and a storm-water pond on 8.64
acres) was approved at the June 10, 2002, City Commission meeting. Staff received the final
engineering plans, which are scheduled to be reviewed at the August 20, 2002, DRC.
Wagner's Curve - The final subdivision plan was submitted May 24, 2002, and reviewed at
the June 4, 2002, DRC meeting. Staff awaits a re-submittal of the final subdivision plans.
August 26, 2002
Information Item A
Page 3
Winter Springs Elementary. - A memo has been sent to the City Attorney requesting
verification of the applicability of the City's sign and dumpster pad enclosure regulations on
school sites.
Board of Adjustment - The Board of Adjustment (BOA) met on August 1 to consider 2 rear-
yard building setback requests. These requests are on this City Commission agenda.
FUNDING: None required
RECOMMENDATION: None required
ATTACHMENTS: None
COMMISSION ACTION: