HomeMy WebLinkAbout2002 11 11 Regular H Paw Park Workshop
COMMISSION AGENDA
ITEM H
CONSENT
INFORMA TIONAL
PUBLIC HEARING
REGULAR X
11/11/02
Meeting
MGR. (2/ /DEPT CG?
Authorization
REQUEST:
The Parks and Recreation Department is requesting the City
Commission to accept the Winter Springs Paw Park Citizen
Advisory Committee Report and Concept Plan and establish a date _
for a workshop to go over the information.
PURPOSE:
The purpose of this agenda item is to obtain commission
approval to accept the Winter Springs Paw Park Citizen Advisory
Committee Report and Concept Plan and establish a date for a
workshop to go over the information.
CONSIDERATIONS:
. On March 18, 2002 The City Commission conducted a Paw Park Workshop.
. On April 2,2002 the City Commission approved Resolution 2002-16, which
established the creation of the Winter Springs Paw Park Advisory Committee and
set out the responsibilities.
. Appointments were as follows: Veterinarian, Dr. Paul Williams, Dog Trainer, Richard
Parsons, person with knowledge of development and operations of dog parks, Bob
Rucci, Dog Owners with interest in using the facility after it is completed, Anne
Pennington, Gene Lein and Diane Ferraro,
. The Committee met on June 23rd, July 1ih, August 22nd, Sept. 30th and Oct. 24th,
The Committee received verbal citizen input at all its meetings.
. After much study, discussion, and public input, the Winter Springs Paw Park Citizen
Advisory Committee recommends the attached report and concept plan.
1
. The committee is recommending a three phase development plan that would be
constructed over several years as follows:
Phase I
Phase II
Phase III
Construction Cost
Construction Cost
Construction Cost
$ 287,000
$ 628,000
$ 608,548
Phase I is basic development activities intended to make the site usable and minimal
improvements.
. The development of the park will be determined through negotiations with the
county. This situation with the county is very fluid and undefined at this time.
. Three things have got to happen before we can move forward:
1. The city and county must agree on a master plan for the total site.
2. The utilization of frontage has to be finalized (commercial or parks).
3. The city and county must agree on funding of development, operations and
maintenance cost.
FUNDING:
To be determined.
RECOMMENDA TION:
1. Approval of the Winter Springs Paw Park Citizen Advisory Committee Report
and Concept Plan with any changes the commission desires appropriate and
establishment of a date for a workshop to go over the information.
2. Direct staff to work with the county in developing master plan, utilization of the
front parcels, and funding arrangements.
IMPLEMENTATION SCHEDULE:
N/A
ATTACHMENTS:
Attachment #1
City of Winter Springs Paw Park Citizen Advisory Committee
report with concept plan.
COMMISSION ACTION:
2
ATTACHMENT III
REPORT AND RECOMMENDATIONS
OF
THE CITY OF WINTER SPRINGS
PAW PARK CITIZEN ADVISORY COMMITTEE
PRESENTED TO
THE CITY OF WINTER SPRINGS
MAYOR AND COMMISSION
NOVEMBER 11, 2002
Committee Member Paul Williams
Committee Member Gene Lien
Committee Member Diane Ferraro
Committee Member Bob Rucci
Committee Member Anne Pennington
Committee Member Richard Parsons
INTRODUCTION
On April 2, 2002, the Winter Springs City Commission approved Resolution
2002-16 establishing the Six Member Winter Springs Paw Park Advisory
Committee.
The purpose of this committee as defined in the Resolution was to assist the City
Staff, City Consultant and City Commission in developing the plans for the
design, operations and maintenance of a Dog Park at Jetta Point.
The Committee held its first meeting on June 20, 2002, which was dedicated to
orientation/swearing in, charge, Seminole County Information, Bill Starmer's Site
Information, and Work Plan.
All together the Committee has had Five meetings. All meetings were held in
accordance with the Florida Sunshine Act requirement and public input was
encouraged at all meetings. Seminole County Staff Representatives were
present at Two meetings.
The final recommendations of the Committee represent the Committee best
efforts to comply with its charge of responsibilities provided in Resolution 2002-
16 in consideration of the ideas and input provided by the Public, the City Staff,
City Consultant and Members of the Committee.
LETTER OF TRANSMITTAL
November 11. 2002
Mayor and Commission:
The members of the Winter Springs Paw Park Citizen Advisory Committee are pleased to present
to you our recommendations for a Paw Park at Jetta Point.
We believe that the recommendations contained in our report are consistent with the change of
responsibilities provided by the City Commission in Resolution 2002-16,
In arriving at our recommendations we considered with great interest all the input provided by
Interested Citizens, the City Consultants, City Staff and Members of the Committee.
We believe that implementation of our recommendations will result in the highest and best use of
(5) Five acres of property at Jetta Point and will result in a first class facility that will carry on the
tradition of excellence for which Winter Springs Parks are known,
In performance of our responsibilities it didn't take long to realize that there is a large local
interest in a Paw Park, The Jetta Point site located next to 434 and 417 will attract many users
from all over Seminole County and Central Florida, To meet the demand the proposed Paw Park
would need to be about 5 acres in size (including parking area),
Also, after Mr. Bill Starmer incorporated all of our thoughts and ideas into the site plan and came
up with an estimate cost, we were all shocked. We all knew the facility was needed and would be
the finest in the state and possibly the country, However, fiscal responsibility is important so we
broke the project down into 3 phases,
In the first phase we put in the essentials to construct a Paw Park for the citizens, Due to the fact
that the site is wooded and undeveloped over $ 150,000,00 of the total estimated cost of
$ 286,251.00 is needed just for basic infrastructure needs,
Phase /I & /II could further enhance the Paw Park based on the need and desire at a later date,
We would like to acknowledge that the successful completion of our responsibilities could not
have been provided without the excellent assistance of the City Consultant, Bill Starmer of
Starmer/Ranaldi Planning and Architecture Inc" Chuck Pula, Winter Springs Parks and
Recreation Director, other Staff and the Citizens who took time to come forward and present their
ideas and thoughts.
In closing, we would like to thank the Mayor and City Commission for giving us this opportunity to
serve our community through our participation on the Advisory Committee and inclusion in this
most important and worthy community project.
We look forward to seeing the vision and dreams of the Community, the City, and the Members of
the Advisory Committee become a reality in the near future. We stand ready to assist the City in
accomplishing that goal in any way the Commission might deem appropriate,
Committee Member
Committee Member
Committee Member
Paul Williams Committee Member
Gene Lien Committee Member
Diane Ferraro Committee Member
Bob Rucci
Anne Pennington
Richard Parsons
TABLE OF CONTENTS
OPERATING RULES.............................................. .PAGE 1-2
OPERATING PLAN COSTS...................................... PAGE 3-8
DEVELOPMENT PLANS......................................... .PAGE 9-10
ESTIMATED DEVELOPMENT COSTS ........................PAGE 11
OPERATING RULES
PAW PARK RULES
1. No animals other than dogs shall be permitted in this park.
2. All dogs must be legally licensed and vaccinated and shall
wear a visible dog license.
3. Female dogs in heat are prohibited from the park.
4. Dogs must be leashed when entering and leaving this park
and dog owners must have a leash in their possession at all
times,
5. Three dog limit per handler.
6. Keep small children under strict supervision.
7. Dog owners must be in the park and within view and voice
contact of their dogs at all times.
8. Dogs exhibiting aggressive behavior are prohibited form this
park.
9. Dogs must be removed from the park at first sign of
aggression.
10, Dog owners must clean up dog waste.
11. Pet owners must immediately fill any holes their dogs dig.
12. Dog owners are responsible for their dog's action and for
ensuring that their dogs don't escape the fenced area.
13. Cruel or harsh treatment of an animal is not permitted.
14. Users of this facility do so at their own risk, City of Winter
Springs shall not be liable for any injury or damage caused by
any dog in this park.
-1-
The Winter Springs Paw Park Citizen Advisory Committee approved
the following regarding liability and indemnification. It was their
recommendation that this information be sent to the City Attorney to
guide him in drafting a City Ordinance.
EXPRESS ASSUMPTION OF LIABILITY AND INDEMNIFICATION
BY USERS OF THE OFF-LEASH AREAS
"The use of an off-leash area by a dog owner or other person having
care, custody, or control of that shall constitute agreement by the dog
owner and the person having care, custody, or control of that dog to
... a waiver of liability of the city, and his or her agreement to protect
indemnify, defend and hold harmless the City from any claim, injury,
or damage arising from or in connection with such use." (City of
Winter Springs Ordinance).
A. Signage: Full and complete signage, both advising visitor that the
park is an off-leash area and that they use the area at their own
risk, and advising dog owners of their assumption of liability and
hold harmless agreement.
B. Insurance: Purchase a commercial insurance policy specifically
protecting the City from dog-related claims.
-2-
OPERATING PLAN COSTS
PAW PARK OPERATIONS PLAN
PROJECTED MAINTENANCE, MATERIALS, AND OTHER EXPENDITURES
RECOMMENDED LEVEL OF SERVICE
PHASE I
TASKS X MAN HOURS X RATE PER HOUR = LABOR COST
1. MOWING, EDGING. WEED-EATING. BLOWING: 2 PEOPLE X 4 MAN-HOURS
EACH = 8 MAN HOURS - 1 TIME PER WEEK = 8 TOTAL MAN-HOURS PER
WEEK X 4 WEEKS = 32 MAN HOURS PER MONTH X $ 10.00 PER HOUR =
$ 640.00 X 12 MONTHS = $ 3,840.00 PER YEAR.
2. TRASH PICKUP AND REMOVAL: 2 PEOPLE X 1 MAN-HOUR EACH = 2
MAN HOURS PER DAY X 7 DAYS PER WEEK = 14 MAN HOURS PER
WEEK X 52 WEEKS = 728 MAN-HOURS PER WEEK X $ 10.00 PER
HOUR = $ 7,280.00 PER YEAR.
3. FERTILlZATIONIWEED CONTROL: APPLICATIONS TO BE DONE
QUARTERL Y, 4 ACRES AT 1-ACRE PER HOUR X 1 PERSON = 4
HOURS PER APPLICATION X 4 APPLICATIONS PER YEAR = 16 MAN
HOURS PER YEAR X $ 10.00 PER HOUR = $160.00 PER YEAR
(APPLICATION ONLY).
4. INSECT CONTROL: (MOLE CRICKETS, SOD WEBWORMS, CHINCH
BUGS, FLEAS, TICKS, FIREANTS) 1-PERSON DONE BI-MONTHL Y 1
HOUR PER ACRE TO APPLY X 4 ACRES = 4 MAN HOURS EVERY
OTHER MONTH = 24 MAN HOURS PER YEAR X $ 10.00 PER HOUR =
$ 240.00 PER YEAR (APPLICATION ONLY).
5. IRRIGATION SYSTEM CHECK AND MAINTENANCE: 1 PERSON, 1
TIME PER MONTH - 1.50 MAN-HOURS PER CHECK = 18 MANHOURS
PER YEAR X $ 10.00 PER HOUR = $ 180.00 PER YEAR (P.M. WORK
ONLY DOES NOT INCLUDE REPAIRS).
TOTAL DOLLAR AMOUNT OF LABOR COST FOR MAINTENANCE/OPERATIONS
PER YEAR = $ 11,700.00.
-3-
PHASE I
MATERIALS AND OTHER EXPENDITURES COST PER YEAR
1. JANITORIAL SUPPLIES: TRASH BAGS, $ 2,000.00 PER YEAR (EXAMPLE
COST - 12 TRASH RECEPTACLES EMPIED 2 TIMES PER DAY = 24 TRASH
BAGS PER DAY X 7 DAYS = 168 BAGS PER WEEK X 52 WEEKS = 8,738
BAGS PER YEAR DIVIDED 100 BAGS PER CASE = 87.36 CASES PER YEAR
X 22.50 PER CASE + $ 1,965.60 JUST FOR TRASH BAGS.
2. IRRIGATION SUPPLIES: MATERIALS SUCH AS PVC, GLUE, CLEMENT,
SPRINKLER HEADS, PVC FITTINGS, PVC PIPE, TELFON TAPE, VALVES
AND SOLENOIDS = $1,000.00 PER YEAR.
3. UTILITIES: ELECTRICITY, WATER, SEWER, AND DUMPSTER FEES =
$ 3,500.00 PER YEAR.
4. EQUIPMENT MAINTENANCE: MOWER BLADES, WEED-EATER STRING,
FILTERS, OIL, BELTS, ETC. = $ 1,200.00 PER YEAR.
5, FERTILlZER/WEED CONTROL: APPLIED 4 TIMES PER YEAR AT A RATE 1.5
TONS PER 4 ACRES X $ 600.00 PER TON = $ 900.00 PER APPLICATION X 6
= $ 3,600.00 PER YEAR (PRODUCT ONLY).
6. INSECT CONTROL: APPLIED 6 TIMES PER YEAR AT A RATE OF 1.5 TONS
PER 4 ACRES = $ 600.00 PER TON = $ 900.00 PER APPLICATION X 6 =
$ 5,400.00 PER YEAR (PRODUCT ONLY).
TOTAL COST OF MATERIALS AND OTHER EXPENDITURES = $16,700.00 PER YEAR.
-4-
SUMMARY PHASE I OPERATING COST
TOTAL LABOR COST = $ 11,700.00 PER YEAR.
TOTAL MATERIALS AND OTHER EXPENDITURES COST = $16,700.00 PER YEAR.
TOTAL PROPOSED MAINTENANCE/OPERA TION BUDGET = $ 28,400.00 PER YEAR.
WORKING WITH LOCAL ADVOCACY GROUPS AND FINDING
CORPORA TE SPONSORSHIP ARE OPTIONS TO HELP DEFRA Y SOME
OF THE MAINTENANCE AND OPERTIONAL AND OPERA TIONAL
COSTS OF A PAW PARK.
-5-
PAW PARK OPERATIONS PLAN
PROJECTED MAINTENANCE, MATERIALS, AND OTHER EXPENDITURES
RECOMMENDED LEVEL OF SERVICE
TOTAL BUILD OUT
TASKS X MAN HOURS X RATE PER HOUR = LABOR COST
1. MOWING. EDGING, WEED-EATING, BLOWING: 2 PEOPLE X 4 MAN-HOURS
EACH = 8 MAN HOURS - 2 TIMES PER WEEK = 16 TOTAL MAN-HOURS PER
WEEK X 4 WEEKS = 64 MAN HOURS PER MONTH X $ 10.00 PER HOUR =
$ 640.00 X 12 MONTHS = $ 7,680.00 PER YEAR.
2. TRASH PICKUP AND REMOVAL: 2 PEOPLE X 1 MAN-HOUR EACH = 2 MAN
HOURS PER DAY X 7 DAYS PER WEEK = 14 MAN HOURS PER WEEK X 52
WEEKS = 728 MAN-HOURS PER WEEK X $ 10.00 PER HOUR = $ 7,280.00
PER YEAR.
3. FACILITY CLEAN UP: WASH DOWN PAVILIONS, BENCHES, TRAIL PATH AND
DO RESTROOM MAINTENANCE DAILY, 2 PEOPLE X 1.25 MAN-HOURS EACH
= 2.50 MAN-HOURS PER DAY X 7 DAYS PER WEEK = 17.50 MAN-HOURS PER
WEEK X 52 WEEKS PER YEAR = 910 MAN HOURS PER YEAR X $ 10.00 PER
HOUR = $ 9,100.00.
4. FERTILlZATION/WEED CONTROL: APPLICATIONS TO BE DONE QUARTERLY,
4 ACRES AT 1-ACRE PER HOUR X 1 PERSON = 4 HOURS PER APPLICATION
X 4 APPLICATIONS PER YEAR = 16 MAN HOURS PER YEAR X $ 10.00 PER
HOUR = $160.00 PER YEAR (APPLICATION ONLY).
5. INSECT CONTROL: (MOLE CRICKETS, SOD WEBWORMS, CHINCH BUGS,
FLEAS, TICKS, FIREANTS) 1-PERSON DONE BI-MONTHL Y 1 HOUR PER ACRE
TO APPLY X 4 ACRES = 4 MAN HOURS EVERY OTHER MONTH = 24 MAN
HOURS PER YEAR X $10.00 PER HOUR = $ 240.00 PER YEAR (APPLICATION
ONLY).
6. IRRIGATION SYSTEM CHECK AND MAINTENANCE: 1 PERSON, 1 TIME PER
MONTH - 1.50 MAN-HOURS PER CHECK = 18 MAN HOURS PER YEAR X $
10.00 PER HOUR = $ 180.00 PER YEAR (P.M. WORK ONLY DOES NOT
INCLUDE REPAIRS).
TOTAL DOLLAR AMOUNT OF LABOR COST FOR MAINTENANCEI
OPERATIONS PER YEAR = $ 24,640.00.
-6-
TOTAL BUILD OUT
MATERIALS AND OTHER EXPENDITURES COST PER YEAR
1. JANITORIAL SUPPLIES: TRASH BAGS, CLEANING SUPPLIES, PAPER SUPPLIES,
ECT. $ 3,000.00 PER YEAR (EXAMPLE COST -12 TRASH RECEPTACLES EMPIED
2 TIMES PER DAY = 24 TRASH BAGS PER DAY X 7 DAYS = 168 BAGS PER WEEK
X 52 WEEKS = 8,738 BAGS PER YEAR DIVIDED 100 BAGS PER CASE = 87.36
CASES PER YEAR X 22.50 PER CASE + $ 1,965.60 JUST FOR TRASH BAGS.
2. IRRIGATION SUPPLIES: MATERIALS SUCH AS PVC, GLUE, CLEMENT,
SPRINKLER HEADS, PVC FITTINGS, PVC PIPE, TELFON TAPE, VALVES AND
SOLENOIDS = $1,000.00 PER YEAR.
3. UTILITIES: ELECTRICITY, WATER AND SEWER, DUMPSTER FEES =
$ 5,500.00 PER YEAR.
4. EQUIPMENT MAINTENANCE: MOWER BLADES, WEED-EATER STRING, FILTERS,
OIL, BELTS, ETC. = $ 1,200.00 PER YEAR.
5. FERTILlZER/WEED CONTROL: APPLIED 4 TIMES PER YEAR AT A RATE 1.5 TONS
PER 4 ACRES X $ 600.00 PER TON = $ 900.00 PER APPLICATION X 6 = $ 3,600.00
PER YEAR (PRODUCT ONLY).
6. INSECT CONTROL: APPLIED 6 TIMES PER YEAR AT A RATE OF 1.5 TONS PER
4 ACRES = $ 600.00 PER TON = $ 900.00 PER APPLICATION X 6 =
$ 5,400.00 PER YEAR (PRODUCT ONLY).
TOTAL COST OF MATERIALS AND OTHER EXPENDITURES = $ 18,700.00 PER YEAR.
-7-
SUMMARY
TOTAL BUILDOUT OPERATING COST
TOTAL LABOR COST = $ 24,640.00 PER YEAR.
TOTAL COST OF MATERIALS AND OTHER EXPENDITURES = $ 18,700,00 PER YEAR.
TOTAL PROPOSED MAINTENANCE/OPERA nON BUDGET = $ 43,340.00 PER YEAR.
WORKING WITH LOCAL ADVOCACY GROUPS AND FINDING
CORPORA TE SPONSORSHIP ARE OPTIONS TO HELP DEFRA Y SOME
OF THE MAINTENANCE AND OPERTIONAL AND OPERA TIONAL
COSTS OF A DOG PARK.
-8-
DEVELOPMENT PLANS
I
1..0
I
Hound Ground
J etta Park
Winter Springs Florida
p~
I Ir.lnln. ....
,
phase I
Scale: ." = 30'
master plan ~
31 oct 02 NORTH
rule sign age
sign/disp/waste
drinking/wash fountain
~e.t- Ranaldi
Planning and Architecture he
I
......
o
I
Hound Ground
J etta Park
Winter Springs Florida
00 sttlf8':C
DDD
'Vendin2
admin office
hL
perimeter fencing
master plan
Scale: ." = 30' 23 S'P 02
~
Planning and Archilccturc Inc
NORTlI
~u. Ranaldi
ESTIMATED DEVELOPMENT COSTS
Jetta Park Hound Ground Master Plan
Opinion of Construction Value
(rev 2) 31 Oct 02
Description Unit Quantity Value Subtotal Total Possible Project Phasing
Site Work Phase I Phase II Phase III
clear and grub ac 5 $ 3,500 $ 17,500 $ 17,500
import structure fill cy 880 $ 5 $ 3,960 $ 2,000 $ 1,960
roadway from 434 to site sy 6306 $ 22 $ 138,732 $ 70,000 $ 68,732
roadway parrallel to parking sy 884 $ 21 $ 18,564 $ 18,564
roadway and parking with in site sy 5446 $ 16 $ 87,136 $ 20,000 $ 67,136
stormwater retention alow 1 $ 40,000 $ 40,000 $ 40,000
utilities allow 1 $ 50,000 $ 50,000 $ 5,000 $ 22,500 $ 22,500
concrete sidewalk cy 47 $ 160 $ 7,520 $ 7,520
resilient surface trail sf 10100 $ 6 $ 60,600 $ 30,000 $ 30,600
landscape and irrigation allow 1 $ 75,000 $ 75,000 $ 75,000
site lighting ea 48 $ 2,000 $ 96,000 $ 48,000 $ 48,000
subtotal $ 595,012 $ 165,500 $ 305,720 $ 123,792
Structures
office I storage I restroom bldg sf 650 $ 150 $ 97,500 $ 97,500
maintenance building sf 500 $ 90 $ 45,000 $ 45,000
pavilions ea 8 $ 20,000 $ 160,000 $ 60,000 $ 100,000
covered entry gate ea 2 $ 10,500 $ 21,000 $ 10,500 $ 10,500
decorative fencing If 1470 $ 85 $ 124,950 $ 124,950
chain link fencing If 1090 $ 9 $ 9,810 $ 20,000
water feature allow 1 $ 60,000 $ 60,000 $ 60,000
subtotal $ 518,260 $ 20,000 $ 168,000 $ 340,450
Miscelaneous
entry kiosk ea 2 $ 7,500 $ 15,000 $ 7,500 $ 7,500
signaqe/trash/dispenser/benches ea 10 $ 2,200 $ 22,000 $ 22,000
water spigots ea 8 $ 1,800 $ 14,400 $ 14,400
subtotal $ 51,400 $ 36,400 $ 7,500 $ 7,500
construction subtotal $ 1,164,672 $ 221,900 $ 481,220 $ 471,742
design contingency 5% $ 58,234 $ 11,095 $ 24,061 $ 23,587
fees and permits 10% $ 116,467 $ 22,190 $ 48,122 $ 47,174
contractor oh&p 14% ~ $ 163,054 $ 31 ,066 $ 67,371 $ 66,044
project total $ 1,502,427 $ 286,251 $ 620,774 $ 608,547
I
...-j
...-j
I
Notes:
1, Roadway and parking with in site is limited to clearing and base stabilization only for phase I
2, Chain link fencing is increased to fence the entire park initially for phase I