REQUEST: Public Works Department, Capital Projects Division, is Requesting Approval
of The Second Contract Agreement with Progress Energy for Installation of 94
Streetlights Along Northern Way South as Part of The Tuscawilla Lighting and
Beautification District TLBD Phase 2 Beautification Project.
PURPOSE: This agenda item is needed for the City Commission to approve a contract between
the City of Winter Springs and Progress Energy for the installation of 94 decorative
streetlights as part of the TLBD Phase 2 Beautification Project located on Northern
Way (South) side at a capital cost of$51, 362.48.
CONSIDERATIONS:
On November 14, 2005, the City Commission adopted Resolution 2005-43, The
Final Improvement Assessment Resolution And Maintenance Assessment Resolution For The
Tuscawilla Phase II Assessment Area, which implemented the Capital and Maintenance
Assessment Program for the TLBD Phase II Beautification Project. On February 27
2006, the City Commission adopted Resolution 2006-14, Accepting the Bank Loan
Proposal, from Wachovia Bank N A in the amount of $430,000 to finance the TLBD Phase
II Project.
The Phase II Beautification Project consists of two components streetlighting and
street signage. Below is a breakdown of the streetlighting portion of the project from
Progress Energy, divided into 8 construction phases in chronological order;
Phase Number of Lights Section Cost
1 105 Northern Way N $63,400 (80% complete)
2 94 N orthem Way S $51,363 (July-August)
3 60 Shetland / Dyson
4 64 Deer Run
5 54 Trotwood / Tuscora
6 36 Vi stawill a
7 74 Seneca
8 48 Tuscora / Greenbrier
062606_ COMM _ Consent_ 402_ TLBD _Progress_Energy _Phase _2
Consent Agenda Item 402
June 26, 2006
Page 2 of2
FUNDING:
Funding for the TLBD Phase II Beautification Project (Phase 2, Northern Way
South) in the amount of $51,363 will be taken from the TLBD Improvement Fund (Phase
II) Line Code (313-65000 -30106)
RECOMMENDATION:
Staff recommends the City Commission approve contracting with Progress Energy
for the TLBD Phase II Beautification Project (Phase 2) in the amount of$51,363 to be taken
from the TLBD Improvement (Fund Phase II) Line Code (313-65000-30106).
IMPLEMENTATION SCHEDULE:
This portion of the project will begin immediately upon completion of Phase 1,
Northern Way North. Start of construction is expected to begin July 2006 and be complete
within 120 days.