REQUEST: Public Works Department is advising the City Commission of the status of
various Capital Improvement Projects
PURPOSE: This agenda item is to update the Commission on the status of current Capital
Improvement projects.
CONSIDERATION:
. UTILITY
16" Water Distribution Main - Water line installed and tied into Water Plant #1. Awaiting tie into
water line on Tuskawilla Road. Estimated completion date is in January 2003.
East Water Reclamation Facility Filters - Project construction began on December 2, 2002.
Estimated completion is in March 2003.
SR 434 Water Main (Vistawilla Road to Spine Road) - Design 90% complete. Waiting for
easements from Casscells and Schrimsher
Utility / Public Works Compound Force Main - Retained Lochrane Engineering to reuse the
Respite Center design for permitting and bidding.
Utility / Public Works Compound - SRI conducting Needs and Space Analysis. Staff to be
interviewed the week of 12/9.
Well #4 - CPH modifying Consumptive Use Permit to permit new proposed well location adjacent
to Northern Way in Trotwood Park.
Reclaimed Water Augmentation - CPR analyzing current demands to project future needs.
. TRAFFIC/TRANSPORTATION IMPROVEMENT
Tuskawilla Road / SR 434 Traffic Signal - Construction proceeding. Waiting delivery of mast
arms for traffic signal. Estimated Completion May 2003.
.
.
.
December 9, 2002
Information Item A
Page 2
Main Street / Hickory Grove Streetscape - Bids were opened 11/20 with the low bid being
$781,795.37. References of contractor being reviewed. Need right of way for Tuskawilla Road
from Schrimsher and One Cent Interlocal agreement in place. Estimated completion of Phase 1 is
April 2003, Phase 2 is October 2003.
SR 434 / Wagner's Curve Traffic Signal - Commission approval to piggyback off Seminole
County contract scheduled for 12/9/02.
SR 419/ Edgemon Traffic Signal- LAP Agreement approved in November. FDOT will fund up
to $211,000 for the signalization and turn lane improvements. Final design underway. Projected
construction completion June 2003.
SR 434/ Doran Drive Traffic Signal - CPH submitting warrant analysis to FDOT for approval. It
is likely the City Hall median opening will be required to be changed to a directional only to get
signalization at Doran Drive.
SR 434 Improvements - FDOT 90% design documents received in November. Staff reviewed
hardscape and landscape with consultant on 11/21/02. Will be forwarded to City Commission in
January as informational item. Construction projected for July 2003.
SR 419/ Moss Road Turn Lane - Design 90% complete by PEC. FDOT permit pending.
Cross Seminole Trail - 90% Design plans have been received. The proposed construction limits for
the paved are from Wade Street to approximately 500 east of Magnolia Park and from the SR 434
trail bridge to Gardena. The unpaved portion of the trail and paved portion in the middle of the
Schrimsher property impacted by the eagle are not included in the design.
Pedestrian Bridge - Cross Seminole Trail - Approved by Seminole County Commission. The
designlbuild contract is 18 months with construction projected to begin in August 2003.
Fisher Road - Design 90% complete. SJRWMD permit to be submitted 12/15/02.
Central Winds Park Boulevard - Preliminary design underway by CPH in conjunction with
Michael Design Associates. Projected construction start date is July 2003 with a completion date of
January 2004.
Winter Springs Boulevard Reconstruction - Design budgeted for this year. Waiting for One Cent
funds to be available.
PARKS and RECREATION
Torcaso Park Expansion - Project substantially complete. Final punch list items being completed.
Central Winds Park Expansion - Clearing of project site SJR WMD in permitting. Construction to
begin January 2003. Estimate project completion May 2003.