HomeMy WebLinkAbout2006 05 22 Informational 504 Capital Improvement Projects Status
COMMISSION AGENDA
ITEM 504
CONSENT
INFORMATIONAL X
PUBLIC HEARING
REGULAR
May 22, 2006
Meeting
MGR/DEPT
Authorization
REQUEST: Public Works Department is advising the City Commission of the status of
various Capital Improvement Projects
PURPOSE: This agenda item is to update the Commission on the status of current Capital
Improvement projects.
CONSIDERATION:
TRAFFIC/TRANSPORTATION/IMPROVEMENT
SR 434 Improvements (Village Walk) - Substantial Completion awarded on December 10, 2005.
Contractor had 30 days to complete all remaining Punch List items before additional liquidated
damages are accessed. A walkthrough with FDOT performed January 12. CEI cost has currently
exceeded the contingency funds provided by the City from the 1999 One Cent Sales Tax
Agreements. Asphalt Stamping repair completed. Final resolution of Liquidated Damages was
tentative on the contractor completing the work. As of April 21, 2006, the contractor has still not
met requirements for completion. Contractor has agreed to replace plant material damaged by frost
as well as any material that had not returned to required fullness. (4/21/06)
SR 434 Town Center Corridor Analysis - City received verbal approval of the proposed
intersection spacing. Written approval is pending. (5/15/2006)
SR 434/ Hayes Road Turn Lane = Design is complete and traffic accident information has been
forwarded to PEC for development of traffic study. Survey has been completed and city attorney
continues work for obtaining the needed Right of Way. (11/8/05)
SR 434 / Doran Drive Traffic Signal - Traffic Control Devices (TCD) has completed the
installation of the mast arm along with the pull boxes and conduit. Doran Drive paving is complete.
Central Florida Environmental (CFE) attempting to locate pavers specified for the area on
Blumberg that are currently out of production. Progress Energy has made connection for power to
the traffic signal. Traffic signal scheduled to be turned on to flash the week of May 15. CFE
has started the work in the intersection removing the concrete separator and preparing for
repaving. Projected completion of the work with the exception of the stamping and coloring of
the asphalt in the intersection expected by the end of May. (5/12/06)
May 22, 2006
Information Item 504
Page 2
Cross Seminole Trail Connector (Wade Street to Wekiva Trail) - County staff are reviewing
constructing the "temporary trail alignment" on Old Sanford-Oviedo Road as discussed at the
March 27th City Commission meeting. (4/24/06)
Magnolia Park Phase II - Phase II of Magnolia Park consists of the construction of the
Amphitheater with restrooms and drinking fountains to act as a trail head for the Cross Seminole
Trail and an inter active water feature in this 0.67:l: acres. Starmer Ranaldi Planning and
Architecture, Inc (SRI) was approved by the Commission on January 10, 2005, for the architectural
services. CPH Engineers, Inc has been authorized by the Commission under Amendment 78 on
June 9, 2003, for services related to the landscape and hardscape design in conjunction with SRI.
Both SRI and CPH Engineers are currently developing the plans for the construction of Magnolia
Park Phase II. City property has been surveyed and comers marked. Environmental consultant is
evaluating wetland impact if trail is shifted. Property has been bush hogged to give depth
perspective for plan development. (3/21/06)
Blumberg Boulevard Trail - The Blumberg Boulevard Trail consist of the construction of the trail
with amenities from Magnolia Park to the intersection of Blumberg Boulevard and Doran Drive.
The trail will have stone pavers with sitting arboretum and proposed sculpture gardens, to include
the Rotary Club sponsored Veterans Memorial. Starmer Ranaldi Planning and Architecture, Inc
(SRI) was approved by the Commission on January 10, 2005, for the architectural services. CPH
Engineers, Inc has been authorized by the Commission under Amendment 78 on June 9, 2003, for
services related to the landscape and hardscape design in conjunction with SRI. Plans are 100%
complete. Copy of plans has been submitted to State Staff for review. The State Department of
Greenways and Trails has provided verbal approval of the trail plans with exception of
requiring an easement request to construct the opening where delivery trucks have been
crossing to exit to the west. The requirements for the easement request will be presented to the
Commission for approval with the next two weeks. (5/12/06)
Central Winds Park Way - Final road design ongoing by CPH. Additional right of way has been
requested from the Leerdam property and they will be submitting a conceptual site plan to the City
Commission. Final Plan review will incorporate their proposed site plan.(4/18/05)
Winter Springs Boulevard Reconstruction - 30% plans were reviewed and commented on in
March. Projected Schedule:
. 60% submittal - May 12, 2006
. Bid Advertisement - July 2, 2006
. Bid Award - September 11, 2006
Final Plans - June 9,2006
Bid Opening - August 16, 2006
Start construction - October 2006
SR 434 Beatification Trees and Curbing - Completing plan design by CPH pending funding
becoming available for plan to be submitted for FDOT Highway Beautification Grant (1/13/06)
Orange Avenue Extension - Preconstruction meeting held and construction commencing. Project
duration is projected at 6 months. (5/15/06)
May 22, 2006
Information Item 504
Page 3
UTILITY
Utility/Public Works Compound - As of March 17 all trees have been cleared and contractor in
process of hauling debris from site. Building permits pending. Underground pipe installation
started the week of May 1. The tap into the potable water line was made on May 5. (5/15/06)
Well #4 - Well development complete. Installation of 12" water line complete. Pump installation
has began. Electrical work pending the installation of the power drop from Progress Energy.
(5/15/06)
Reclaimed Water Augmentation - Phase I of the project has been included in the FY2007 -FY20 10
SJRWMD grant funding for a total of $2.42 million. CPH engineers will be submitting the
Consumptive Use Permit for withdrawing from Lake Jesup by May 31. (4/24/06)
Electrical Improvements WTP #3 - Recommendation for contract award presented to Commission
on February 27, 2006 for award of contract to Florida Industrial Electric (FIE) for $281240.00.
Pre-Construction meeting held on May 2. Construction to start after delivery of electrical
component schematics and submittals received. (5/15/06)
Village Walk Overhead Utility Undergrounding - Cost received by Progress Energy on August 5,
2005, Progress Energy provided staff with the cost to convert Progress Energy's lines from
overhead to underground. The cost was $403,017.00. Additional cost may be incurred to provide
property owners that have parking lot lighting installed on the power poles with an alternative
lighting solution. The cost provided by Progress Energy does not include the cost to bury other
utility lines. The cost to bury these lines is usually 50% to 75% of the cost to convert the power
lines. There are up to four other utilities with lines on the Progress Energy poles. The estim.ated cost
to convert these lines is $806,032 to $1.2 million. Total cost to convert the overhead utility lines to
underground is $1.2 million to $1.6 million. (1/13/16)
PUBLIC BUILDINGS
City Hall Expansion - The design of the expansion of City Hall was approved by the Commission
on February 28,2005. Starmer Ranaldi Planning and Architecture, Inc (SRI) provided the design of
this 4,980 square foot addition to City Hall in the northwest corner of the City Hall building. New
layout presented to Commission at 8/1 workshop and direction received. 400A> Plans presented to
staff for comments week of January 3. SRI anticipates plans to be ready for final review in time to
advertise in May-June. (3/20/06)
PARKS AND RECREATION
Senior Center Therapy Pool - Commission approved moving forward with design to enclose the
pool March 13,2006. (3/21/06)
FIRE DEPARTMENT
Fire Station House #28 - Initial conceptual site layout proposal received 4/14/06. (4/24/06)
COMMISSION ACTION: