HomeMy WebLinkAbout2005 01 10 Regular Item 500 Final Engineering Landings at Parkstone
CITY COMMISSION
AGENDA
ITEM 500
Consent
Information
Public Hearin~
Re~ular X
January 10, 2005
Meeting
MGR. ~v/ /Dept. /~
REQUEST: The Community Development Department- Planning Division requests the
City Commission approve the revised Final Engineering plans for The Landings at
Parkstone from the plan adopted by the Commission on July 26, 2004. This item is
continued from the December 13,2004 Commission meeting.
PURPOSE: The purpose of this agenda item is to recommend approval for the revised Final
Engineering plans for 104 town-home units and associated infrastructure on 12 acres along the
north side of SR 434, west of Parks tone Boulevard.
APPLICABLE CITY CODES
Section 9-71. When final development plan is to be filed; extension.
Section 9-72. Processing of final plans.
Section 9-73. Form and contents of final development plans.
Section 9-74. Action on final development plan; expiration of approval.
Section 20-317. Application for construction.
Division 2. General Design Standards for New Development Area (sections 20-463 thru 20-
475).
Division 3. Part B. Planned Unit Development (sections 20-376 thru 20-389).
CHRONOLOGY:
April 21, 1995 - City received rezoning application package (RU to PUD) and master plan
August 28, 1995 - City approved master plan
September 25, 1995 - City approved rezoning to PUD
September 3, 1997 - City approved master plan revision reducing Tract C from 13 to 2 acres and
re-designating tracts C & D from Flexible land use to Neighborhood Commercial &
Professional Office
January 26, 1998 - City approved preliminary engineering and final subdivision plan
@)
January 10,2005
Regular Item 500
Page 2
November 23, 1998 - City approved final engineering (except for 43 lots)
July 12, 1999 - City approved final engineering for remaining 43 lots
January 12, 2004 - City adopted of Ordinance No. 2003-35, the large scale comprehensive plan
amendment from Low Density Residential to High Density Residential
February 13, 2004 - City received PUD amendment package and associated
engineering/subdivision documents
July 7,2004 - P&Z Board recommended approval ofPUD master plan amendment and
engineering/subdivision plans
July 26,2004 - City Commission held a Public Hearing and recommended approval of the
Parkstone PUD master plan amendment.
July 26, 2004 - City Commission recommended approval of development agreement,
preliminary and final subdivision/engineering plans, and restrictive covenants.
Dec. 7, 2004- P&Z Board recommended approval ofthe revised PUD master plan amendment
and engineering/subdivision plans.
CONSIDERATIONS:
The site is located within the City on the north side of SR 434, immediately adjacent to the west
side of Parks tone Boulevard, separated by a wall from the single family portion of Parks tone. It
has a Medium Density Residential Future Land Use (FLU) designation and PUD zoning (as part
of the Parkstone Planned Unit Development). It is also within the SR 434 New Development
Overlay Zoning District. The site is served by a private looped roadway connected to Parkstone
Boulevard, with alternate egress onto SR 434. Emergency vehicle access is proposed through the
southwest comer of the site from SR 434. The site features central water and sewer and uses the
existing storm-water system already engineered and constructed for Parkstone. The site is vacant
open land with no specimen trees, no wetlands, and no known environmental issues. A portion
of the Cross-Seminole Trail extends generally east and west between the SR 434 roadway surface
and the site. A traffic study was provided with the initial approval and no additional on-site and
no off-site traffic improvements were deemed necessary by either traffic consultant.
After final approval was received last July, the developer determined that some revisions
to the approved plans were necessary. The plans were revised to incorporate the
following:
1- Move the front entry drive (Amalie Drive) 90-feet to the south, aligning it with
Caneel Bay Terrace (in order to keep the existing median and landscaping along
Parkstone Blvd. in tact); and
2- Lower the grade of the development by 12" as reflected on the Grading and
Drainage Plan.
These revisions have resulted in a better project (than the previously approved plans)
because they result in less impact to the neighborhood by retaining the existing Parkstone
median landscaping and reducing the overall height of the project by a foot.
Additionally, the applicant has modified the plans further, in response to comments from
the Commission. These changes include:
3- Substantially revising the rear elevation to look like the front of the units.
January 10,2005
Regular Item 500
Page 3
4- Removing the massive 8-unit building (units 97 thru 104) from along Parkstone
Blvd. and replacing it with a 4-unit building (units 96 thru unit 101) and a 3-unit
building (units 102 thru 104). Unit 97 has been turned 90 degrees and placed
adjacent to unit 96.
5- Adjoining driveways have been divided to break up the sea of concrete.
6- Landscaping along SR 434 has been enhanced to supplement the existing metal
fencing and brick pillars that are in place on both sides of the boulevard. The
enhanced landscaping is in addition to the landscaping approved in July.
These changes have been reflected in the Final Engineering and Landscape plans.
FINDINGS:
1. The approved development connects to City potable water and sanitary sewer. The City has
adequate capacity for both.
2. The approved development of 104 units (8.66 units to the acre) are allowed under the future
land use designation of Medium Density Residential.
3. The 12 acre site is within the PUD zoning district, has a Medium Density Future Land Use
(FLU) designation, and is within the SR 434 New Development Overlay Zoning District.
4. The approved development has a private roadway system that is not designed to City
standards and therefore may not be incorporated into the City roadway system for ownership
and/or maintenance.
5. No out-standing traffic issues were found.
6. The revised Final Engineering plans are consistent with the Comprehensive Plan, City Code
of Ordinances, and the Development Agreement.
PLANNING & ZONING BOARD RECOMMENDATION: At the regular meeting of
the Planning and Zoning Board/ Local Planning Agency on Dec. 7, 2004, the Board
recommended "Approval" to the City Commission.
STAFF RECOMMENDATION:
Staff recommends approval of the revised Final Engineering plans for The Landings at Parkstone
subject to any additional StaffDRC review and comments, given the recent changes
implemented.
ATTACHMENTS:
A. Excerpt from Planning & Zoning Board Approved Minutes of December 7,2004.
B. Revised Final Engineering Plans
CITY COMMISSION ACTION:
January 10,2005
Regular Item 500
Page 4
ATTACHMENT A
Excerpt from Planning & Zoning Board Approved Minutes
CITY OF WINTER SPRINGS
MINUTES
PLANNING AND ZONING BOARD/LOCAL PLANNING AGENCY
REGULAR MEETING
DECEMBER 7,2004
(RESCHEDULED FROM DECEMBER 1, 2004)
ADD-ON
IV. PUBLIC HEARINGS AGENDA
PUBLIC HEARINGS
Community Development Department - Planning Division
A. Requests The Planning And Zoning Board Recommend Approval
To The City Commission Of The Revised Parkstone PUD (Planned Unit
Development) Master Plan And Revised Final Engineering Plans For
The Landings At Parkstone.
Board Member Brown said, "And, I would like to commend you on -
bringing the Final Engineering. "It's nice for us to know how it finally ends
up." Board Member Brown added, "So, I appreciate it very much Eloise
[Sahlstrom]."
Ms. Sahlstrom presented this Agenda Item.
Tape lISide B
Discussion.
"I'D RECOMMEND THAT THE PLANNING AND ZONING
BOARD/[LOCAL PLANNING AGENCY] MAKE A
RECOMMENDATION TO THE CITY COMMISSION APPROVING
THE REVISED P ARKS TONE PUD (PLANNED UNIT
DEVELOPMENT) MASTER PLAN." MOTION BY BOARD
MEMBER POE. SECONDED BY BOARD MEMBER VOSKA.
DISCUSSION.
January 10,2005
Regular Item 500
Page 5
ATTACHMENT A
Excerpt from Planning & Zoning Board Approved Minutes
VOTE:
BOARDMEMBERBROWN: AYE
BOARD MEMBER POE: AYE
BOARD MEMBER VOSKA: AYE
MOTION CARRIED
"I ALSO RECOMMEND THAT THE PLANNING AND ZONING
BOARD/[LOCAL PLANNING AGENCY] MAKE A
RECOMMENDATION TO THE CITY COMMISSION APPROVING
THE REVISED FINAL ENGINEERING PLANS FOR THE
LANDINGS AT PARKSTONE." MOTION BY BOARD MEMBER
POE. SECONDED BY BOARD MEMBER VOSKA. DISCUSSION.
VOTE:
BOARD MEMBER BROWN: AYE
BOARD MEMBER VOSKA: AYE
BOARD MEMBER POE: AYE
MOTION CARRIED.
January 10,2005
Regular Item 500
Page 6
ATTACHMENT B
Revised Final Engineering Plans (attached)
FINAL ENGINEERING FOR LANDINGS AT PARKSTONE
GENERAL NOTES
THE LANDINGS AT PARKSTONE
SHEET 2
GRADING AND DRAINAGE PLAN
THE LANDINGS AT PARKSTONE
SHEET 3
SITE DEVELOPMENT PLAN
THE LANDINGS AT PARKSTONE
SHEET 3
COMPOSITE UTILITY PLAN
THE LANDINGS AT PARKSTONE
SHEET 4
PARKSTONE
SHEET NO 1
PARKSTONE PUD MASTER PLAN SHEET 2
PRELIMINARY PLANS FOR
THE LANDINGS AT PARKSTONE
FEBRUARY 13, 2004
PREPARED FOR: MORRISON HOMES REVISED JUNE 22, 2004
SHEET 1
PRELIMINARY DEVELOPMENT PLAN
THE LANDINGS AT PARKSTONE
SHEET 2
PUD MASTER PLAN THE LANDINGS AT PARKSTONE
SHEET NO 3
GRADING AND DRAINAGE PLAN
THE LANDINGS AT PARKSTONE
SHEET NO 4
COMPOSITE UTILITY PLAN
THE LANDINGS AT PARKSTONE
SHEET 5
SANITARY SEWER PROFILES
THE LANDINGS AT PARKSTONE
SHEET 6
SANITARY SEWER PROFILES
THE LANDINGS AT PARKSTONE
SHEET NO 7
GENERAL DETAILS
THE LANDINGS AT PARKSTONE
SHEET 8
STORMWATER DETAILS
THE LANDINGS AT PARKSTONE
SHEET 9
UTILITY DETAILS
THE LANDINGS AT PARKSTONE
SHEET 10
EROSION CONTROL PLAN
THE LANDINGS AT PARKSTONE
SHEET NO 11
EROSION CONTROL DETAILS
THE LANDINGS AT PARKSTONE
SHEET NO 12
LANDSCAPE PLAN
THE LANDINGS AT PARKSTONE
SHEET L-1
LANDSCAPE PLAN
THE LANDINGS AT PARKSTONE
SHEET NO L-2
LANDSCAPE DETAILS AND NOTES
THE LANDINGS AT PARKSTONE
SHEET NO. L-3
IRRIGATION PLAN
PARKSTONE P.U.D.
SHEET NO IR-1
IRRIGATION PLAN
PARKSTONE P.U.D.
SHEET NO. IR-2
IRRIGATION DETAILS AND NOTES
PARKSTONE P.U.D.
SHEET NO. IR-3
Drawing Final Engineering Plans for The Landings at Parkstone
Drawing page 2
page 10
Drawing page 3
page 4
page 5
page 6
page 7
page 8
drawing page 11
drawing page 12
drawing page 13
drawing page 14
drawing page 15
drawing page 16
drawing page 17
drawing page 18
drawing page 9