COMMISSION AGENDA
ITEM A
CONSENT X
INFORMATIONAL
PUBLIC HEARING
REGULAR
At4(ol
March~l
Meeting
MGR i~EPT ~
I /-
Authorization
REQUEST: Public Works Department Requesting Authorization to Piggyback ofT of the
Seminole County contract for the design of the Vistawilla Drive Traffic Signal.
PURPOSE: The purpose of this Board item is to request authorization to Piggyback off of
Seminole County contract (PS-555-00/BJC) for the Vistawilla Drive Traffic Signal
design, plan preparation, and permitting with PEC, Inc, at a cost of $15,838.20,
CONSIDERA TIONS:
These design services are needed to proceed with the design of the traffic signal at
Vistawilla Drive and S,R. 434, We are proposing to piggyback off of Seminole County's
design contract for signalization (pS-555-00/BJC) with PEC, Inc, of Orlando. The City
Commission directed staff to proceed with the design and permitting ofthis signal in
anticipation of funding, PEe, Inc, is in the process of doing four other signals for the County
and is well versed in the Math Cad design required by FDOT,
The scope of work includes surveying, subsurface sampling and field testing,
signalization design, and permitting for the traffic signal at Vistawilla Drive and S.R. 434,
Bidding Services and Post Design Services are quoted separately and not part of this request.
The preliminary construction cost estimate is $140,000 for the signalization work which
includes the decorative mast arms,
FUNDING:
The funding source for the design cost of $15,838.20 is from the consulting line code
reserves of the Transportation Impact Fee Fund - (140-53180). The funds for this project will
March 26, 2001
Consent Agenda Item A
Page 2
be expended over the next 120 days,
RECOMMENDA nON:
It is recommended that authorization be given to Piggyback off of Seminole
County contract (PS-555-00IBJC) for the Vistawilla Drive Traffic Signal design, plan
preparation, and permitting with PEC, Inc. at a cost of$15,838.20 with PEC Inc, at.a
cost of$15,838.20 payable from the consulting services line code of the Transportation
Impact Fee Fund - (140-53180),
IMPLEMENTATION SCHEDULE:
The scope of services will be completed within 120 days of approval,
ATTACHMENTS:
1, PEC Inc, Proposal
COMMISSION ACTION:
A TT ACHMENT NO. 1
PEe
PROFESSIONAL ENGINEERING CONSUL TANTS, INC.
March 13, 2001
P-I055
MK-03
Mr. Kipton Lockcuff, P,E.
Public Works Director/ Utilities Engineer
City of Winter Springs
1126 E. State Road 434
Winter Springs, Florida 32708
RE: State Road 434 / Vistawilla Drive
Intersection Signalization Project
Proposal for Professional Engineering Services
Dear Mr, Lockcuff:
Professional Engineering Consultants, Inc. (PEC) is pleased to present this proposal for
professional engineering design, permitting, bidding, and post design services for the State Road
434/ Vistawilla Drive intersection signalization project. The terms of this proposal are consistent
with our continuous Seminole County Minor Roadway and MSBU Design contract (PS-555-
OO/BIC) terms and conditions, including manhours and hourly rates,
PEC staff has a great deal of experience in similar projects throughout Central Florida, This
experience includes the permitting process through (1) the Florida Department of Transportation
District 5 and (2) Seminole County (maintaining agency),
SCOPE OF SERVICES
. The scope of this project is broken into three major tasks. These tasks are (1) Signalization
design, construction plans preparation and permitting, (2) Bidding phase services, and (3) Post
design services,
Task 1: Si2:nalization Design. Construction Plans Preparation and Permitting.
This task includes the following:
Design topographic survey to include locating all improvements and utilities as evidenced
by above ground features or as marked by the designated utility company representative,
The coverage/limits of this survey will be sufficient to construct the proposed
improvements.
2.
Design right-of-way established based on existing right-of-way maps and monumentation.
3,
Execute a program of subsurface sampling and field testing, This includes performing
two Standard Penetration Test (SPT) borings to depth of35 feet.
engineers
planners
sUr/oyars
"Engineering Our COl11l71l1nilv
200 East Robinson Street' Suit") 1560 . Orl:moo. Florida 32801 . 407/422-8':)62 . Ff\X 4D7'849-9401
Mr, Kipton Lockcuff, P,E,
March 13, 2001
Page 2
4, Visually classify and stratify representative soil samples in the laboratory using the Unified
Soil Clasisification System.
5. Collect groundwater level measurements and estimate normal wet seasonal high
groundwater levels.
6, Prepare complete signalization plans in accordance with the latest design standards,
design manuals and policies adopted by FDOT and Seminole County as applicable, and
in accordance with the City of Winter Springs criteria and preferences,
7. Provide isolated intersection timings,
8, Prepare complete signing and pavement marking plans to include the addition of stop bars
and lane lines on State Road 434 and removal of the existing stop sign on Vistawilla
Drive,
9. Provide structural analysis and foundation design for the proposed mast arm structures
in accordance with the FDOT Mathcadd program based on the Seminole County pre-
approved Standard Mast Arm Design and Calculations,
10. Perform utility coordination,
11. Perform four (4) utility verification / vaccuum excavation test holes at the proposed mast
arm pole locations,
12, Submit the construction plans to FDOT and Seminole County for review and approval.
Task 2: Bidding Phase Services.
This phase includes providing bid tabulation sheets suitable for bidding purposes by the
contractors, transmitting bid packages to interested contractors, reviewing the received bids and
providing the City with a letter of "recommendation to award" letter. The City may elect to
utilize the existing Seminole County construction contract to construct these improvements
assuming all parties agree to such,
Task 3: Post Design Services,
1. Review mast arm poles shop drawings,
2, Review submittal data for the signalization hardware,
3. Respond to "request for information" during construction.
4, Assist in resolving any construction related issues.
5. Attend on-site meetings to discuss construction progress.
Mr. Kipton Lockcuff, P.E.
March 13, 2001
Page 3
SCHEDULE
A sixty (60) to ninety (90) day project schedule is anticipated to complete the construction
drawings, This time is exclusive of any review time by FDOT and Seminole County, Close
coordination will be required in order to minimize the review time by the various agencies,
GENERAL CONDITIONS
1. Signal Warrant Analysis is not included under this proposal.
2. The City will provide PEC with a copy of all the traffic reports including the signal
warrant analysis and the existing traffic volume counts at this intersection,
3. Interconnect plans and coordination timings are not included under this proposal.
PROFESSIONAL FEES
Task 1:
Task 2:
Task 3:
Signalization Design, Construction Plans Preparation and Permitting, , $15,838,20
Bidding Phase Services "",..",.".....,...........",.,., $1,809.60
Post Design Services . . , , , , . , , . , , . , , , , , . , . . , , , . , , , , , . . , . . . . , $3,665,60
The attached sheet provides a breakdown of the manhours and fees.
We appreciate the opportunity to submit this proposal and look forward to working with you.
If you have any questions, please contact me,
Very truly yours,
PROFESSIONAL ENGINEERING CONSULTANTS, INC,
:f ~cL
Fursan S, Munjed, P,E,
Project Manager/Associate Principal
Attachment
cc: Robert B. Zaitooni, P,E" Seminole County
Kenneth R. Hooper, v.p" PEC
G:lclerical\HIGHW A Y\PEC\MK-03Isr434\P-l OSS.ltr
City of Winter Springs
State Road 434 / Vistawilla Intersection Signalization
PEe Manhour and Fee Estimate
Signalization Design 6 46 34 4 90 $5,167,80
Structural Design 2 12 6 2 22 $776.00
Foundation Design 2 8 4 2 16 $916.40
Utility Coordination 5 10 6 3 24 $1,421.00
Coordination With FOOT 2 8 2 12 $696.00
Quality Control/Constructibility Review 2 2 4 $278.40
.. ":::50:
......
... ..
Survey/Right-of-Way (Southeastern Surveying & Mapping Corp,)
Utility VerificationNacuum Excavation
Geotech (Professional Services Industries, Inc.)
Direct Reimbursables
$3,000.00
$1,200.00
$1,500.00
$400.00
. ,
................,
Task 2: