REQUEST: Public Works Department is advising the City Commission of the status of
various Capital Improvement Projects
PURPOSE: This agenda item is to update the Commission on the status of current
Capital Improvement projects.
CONSIDERATION:
TRAFFICffRANSPORTATION IMPROVEMENT
SR 434 Improvements (Village Walk) - Some portion of the contingency funding provided by
the city will be required for the CEI cost beyond the original contract period. Substantial
Completion awarded on December 10, 2005. Contractor had 30 days to complete all remaining
Punch List items before additional liquidated damages are accessed. A walkthrough with FDOT
performed January 12. Liquidated Damages have not at this time been resolved. CEI cost has
currently exceeded the contingency funds provided by the City from the 1999 One Cent Sales
Tax Agreements. Asphalt Stamping repair to be completed the weekend of January 25,
2006. Final resolution of Liquidated Damages pending. (2/20/06)
SR 434 Town Center Corridor Analysis - City representatives met with FDOT Secretary
Stuttler on January 5th and expect a response to our median spacing request by the end of the
month. (1/23/2006)
SR 434/ Hayes Road Turn Lane - Design is complete and traffic accident information has been
forwarded to PEC for development of traffic study. Survey has been completed and city attorney
continues work for obtaining the needed Right of Way. (11/8/05)
SR 434 / Doran Drive Traffic Signal - Notice to Proceed has been issued to Traffic Control
Devices (TCD) to order the mast arm traffic signal and to Central Florida Environmental (CFE)
to begin the road work. A preconstruction meeting was held 1 November with all stakeholders
for the intersection improvements to be coordinated. Anticipate construction of turn lane on
Doran Drive to begin first week of January. Developer's contractor expects his portion of the
intersection improvements of McLeod's Way to be complete prior to the CFE beginning work
February 27, 2006
Information Item 502
Page 2
the first week of January to avoid conflict. Traffic Control Devices has completed the
installation of the mast arm foundations along with the pull boxes and conduit. TCD expects
delivery of the traffic signal mast arms mid to late January. CFE will be on site mid January to
allow more time of the off site work to be completed. CFE waiting on the moving of Phone
line and gas lines from new turn lane roadway. (2/20/06)
Cross Seminole Trail Connector (Wade Street to Wekiva Trail) - Staff is working with County
staff on evaluating the wetlands along the preferred route. The City Manager and Mayor are
working with Rep. Mealor on state and/or federal funding for this alternative. The wetlands have
been flagged and staff met with Seminole County and the consultant on May 25th.. Seminole
County is pursuing legislative funding in the coming session. (10/10/05)
Magnolia Park Phase II - Phase II of Magnolia Park consists of the construction of the
Amphitheater with restrooms and drinking fountains to act as a trail head for the Cross Seminole
Trail and an inter active water feature in this 0.67:l:: acres. Starmer Ranaldi Planning and
Architecture, Inc (SRI) was approved by the Commission on January 10, 2005, for the
architectural services. CPR Engineers, Inc has been authorized by the Commission under
Amendment 78 on June 9, 2003, for services related to the landscape and hardscape design in
conjunction with SRI. Both SRI and CPR Engineers are currently developing the plans for the
construction of Magnolia Park Phase II. Survey and assessment of wetlands northeast of the
Cross Seminole Trial being conducted to determine possible impacts and cost associated with
moving the trail to accommodate the amphitheater/trailhead design. (1/17/06)
Blumberg Boulevard Trail - The Blumberg Boulevard Trail consist of the construction of the
trail with amenities from Magnolia Park to the intersection of Blumberg Boulevard and Doran
Drive. The trail will have stone pavers with sitting arboretum and proposed sculpture gardens, to
include the Rotary Club sponsored Veterans Memorial. Starmer Ranaldi Planning and
Architecture, Inc (SRI) was approved by the Commission on January 10, 2005, for the
architectural services. CPR Engineers, Inc has been authorized by the Commission under
Amendment 78 on June 9, 2003, for services related to the landscape and hardscape design in
conjunction with SRI. Plans are 100% complete. Office of Greenways and Trails
application for easement to cross state lands submitted to allow for the proposed crossing
change. (2/20/06)
Central Winds Park Way - Final road design ongoing by CPR. Additional right of way has
been requested from the Leerdam property and they will be submitting a conceptual site plan to
the City Commission. Final Plan review will incorporate their proposed site plan.( 4/18/05)
Winter Springs Boulevard Reconstruction - Preliminary report was presented to the City
Commission on April!1, 2005. The initial cost estimate for reconstruction is 2.4 million dollars.
Survey is complete and PEC has 30% plans to be submitted to staff for review and
comment by the first of March. (2/21/06)
Village Walk Beautification Phase II Trees - The project to install shade trees in the Right
of Way and Beautification Easements from Wade Street to Belle Avenue has begun.
(2/20/06)
February 27,2006
Information Item 502
Page 3
SR 434 Beatification Trees and Curbing - Completing plan design by CPH pending funding
becoming available for plan to be submitted for FDOT Highway Beautification Grant (1/13/06)
Orange Avenue Extension - Initial scope development under consideration by Staff (1/13/06)
UTILITY
Utility/Public Works Compound - Design is 100% complete. Payment to River Run, Inc for
wetland mitigation made on November 11. Easement forwarded to FDEP. Pre-construction
meeting held on February 20, 2006. Notice to Proceed issued with expected start date of
Monday February 27 for land clearing. (2/20/06)
Well #4 - Well development complete. Meeting held with contractor to determine additional
cost to complete project due to increase in material and labor cost since award of original
contract. (2/20/06)
Reclaimed Water Augmentation - Final Draft was presented to the City Commission on 11/14.
Augmentation project has been submitted to SJRWMD for funding. (1/23/06)
Tuskawilla Road Stormwater Improvements - The scope of this project to install two 24" storm
pipes and fill the existing ditches along with a strainer/ trash collection box with spreader swale
to improve the quality of run off entering Lake Jesup from Tuskawilla Road North of St. Johns
Landing and Orange Avenue. The contract was awarded to Sunshine Building and Development
with a pre-construction meeting held on June 16th. Construction is complete. (1/18/06)
Electrical Improvements WTP #3 - Recommendation for contract award presented to
Commission on February 27, 2006 for award of contract to Florida Industrial Electric for
281240.00. (2/05/06)
Village Walk Overhead Utility Undergrounding - Cost received by Progress Energy on August
5, 2005, Progress Energy provided staff with the cost to convert Progress Energy's lines from
overhead to underground. The cost was $403,017.00. Additional cost may be incurred to provide
property owners that have parking lot lighting installed on the power poles with an alternative
lighting solution. The cost provided by Progress Energy does not include the cost to bury other
utility lines. The cost to bury these lines is usually 50% to 75% of the cost to convert the power
lines. There are up to four other utilities with lines on the Progress Energy poles. The estimated
cost to convert these lines is $806,032 to $1.2 million. Total cost to convert the overhead utility
lines to underground is $1.2 million to $1.6 million. (1/13/16)
PUBLIC BUILDINGS
City Hall Expansion - The design of the expansion of City Hall was approved by the
Commission on February 28, 2005. Starmer Ranaldi Planning and Architecture, Inc (SRI)
provided the design of this 4,980 square foot addition to City Hall in the northwest corner of the
City Hall building. New layout presented to Commission at 8/1 workshop and direction
received. 40% Plans presented to staff for comments week of January 3. (1/13/06)
February 27,2006
Information Item 502
Page 4
PARKS AND RECREATION
Senior Center Therapy Pool - Awaiting Statement outlining proposed cost from SRI to begin
initial design work.
FIRE DEPARTMENT
Fire Station House #28 - Initial conceptual site layout proposal requested from CPR. (1/13/06)