HomeMy WebLinkAbout2006 02 27 Informational Item 500 Planning Projects
COMMISSION AGENDA
ITEM 500
INFORMATIONAL X
February 27,2006
Meeting
MGR. /DEPT
Authorization
REQUEST: Community Development Department is advising the City Commission ofthe
status of various current planning projects.
PURPOSE: This agenda item is to update the Commission on the status of current planning
projects.
CONSIDERATION:
(1) Barclay Reserve (Previously Barclay Woods) - 88 Units. At its October 11,2004, meeting,
the City Commission approved a modification to the development agreement to expedite
provision of model home units. An aesthetic review of the town homes and entrance sign was
conducted at the October 25, November 8, and November 22, 2004, City Commission
meetings. The final plat and restrictive covenants were approved at the January 10 City
Commission meeting and recorded January 13, 2005. A location error in building the
retaining wall (measuring to the middle, instead ofthe outside edge of the 8 inch thick wall)
required a modification to the rear setback in the development agreement, which was approved
at the March 28, 2005, City Commission meeting. At its May 23, 2005, meeting the City
Commission accepted the potable water and sanitary sewer improvements that were dedicated
to the City and agreed to a development agreement modification addressing utility
reimbursement. Construction continues on the 2 buildings adjacent to the SR 434 ROW. One
of these buildings is close to completion. Inspections were conducted on both buildings
abutting SR 434 on February 10. per 02/27/06 agenda
(2) Vista Willa - A concept plan for two (2) 39,500 square foot office buildings (now 39,900
SF each) on 9.17 acres within the Tuscawilla PUD, located on the south side of SR 434,
between the Hess station and the Greeneway, was received June 8 and received a concept
approval on August 22,2005. On August 26, a substantially incomplete combined preliminary
and final engineering plan package was submitted to staff and was addressed at the September
6 staff review. Re-submittals were reviewed at the November 8 and December 20 staff
reviews. The plans for phase I and a development agreement were approved at the January 23
City Commission meeting. A preconstruction meeting was held February 8. The aesthetic
February 27, 2006
Information Item 500
Page 2
review package was received on January 13 and was held at the February 7 staff review. per
02/27/06 agenda
(3) Oviedo Marketplace - Notice was provided on April 1, 2005, of the Notice of a Proposed
Change (NOPC # 5386) for the Oviedo Marketplace [Mall] development of regional impact
(DR!). The 431.2 acre DR! is located among 3 jurisdictions (218.6 acres in Oviedo, 163 acres
in unincorporated Seminole County, and 49.6 acres in Winter Springs). The NOPC is
proposed to allow 180 town home units to replace 10,000 SF of retail in Parcel 13 (within
Oviedo, but adjacent to Winter Springs - Tuscawilla Units 7 & 13). The build-out date for the
entire DRI is being extended from 12/31/05 to 12/31/07. Pursuant to a May 9,2005, City
Commission directive to staff, notification was sent to the owners of 103 properties within the
City of Winter Springs. The NOPC for the Oviedo portion was approved by the Oviedo City
Commission on Monday, September 19,2005. Staff met with Oviedo Marketplace
representatives from Viera and their consultant, G1atting-Jackson on September 27,2005, to
discuss changing the permissible uses in the Winter Springs portion from retail/office to office
and 132 town-homes. The NOPC and an associated PUD master plan amendment for the
Winter Springs portion ofthe DR! were submitted to the City on November 8 and are
scheduled for the December 6 staff review and January 4,2006 P&Z/LPA meeting (the
applicant has requested the P & Z review be delayed). The recently submitted NOPC proposes
to change the Winter Spings portion of the DR! from 160,000 square feet of commercial to
131,000 square feet of office/commercial and 132 townhomes was heard at the February 1 P &
Z meeting (2-2 vote) and is scheduled for this Commission meeting. per 02/27/06 agenda
(4) Colonial Bank - On September 13, staff received a preliminary engineering/site plan
package for a Colonial Bank at the comer out-parcel of what had been the Kash-N-Karry
shopping center. This was reviewed at the October 18 staff review. A re-submittal was
received on December 21 and was reviewed at the January 17, 2006, staff review. Final
site/civil plans were submitted February 8 for the March 1 P&Z meeting. per 02/13/06
agenda
(5) ICI Homes - 480 condo units. 80,000 SF of office. A Large Scale Future Land Use change
was transmitted to DCA on October 25, 2004. The adoption hearing amending the Future
Land Use map was held January 24,2005. Staff met with ICI representative on August 4,
2005, to discuss rezoning, height, and site plan issues. per 08/22/05 agenda
(6) Tuscawilla Square - The final engineering/site plan was approved on February 28, 2005.
The aesthetic review was approved at the May 9 City Commission meeting and a pre-
construction was held on May 18. At its June 13,2005, meeting, the City Commission
approved funding $174,454.00 for the Gary Hillery Drive reconstruction. No funding was
approved for entrance features. Building plans have been submitted and are under review.
The crew has almost completed the on-site utility installation and has been working on the off-
site installation. On September 19, October 13, and November 7, staff estimated the on-site
site work (not including the road-work or off-site storm-water facility) to be 70 percent
complete. Permits have been issued for the temporary construction office trailer and for the
construction sign. Building permits have been issued for both of the buildings on this site. per
11/28/05 agenda
February 27, 2006
Information Item 500
Page 3
(7) Winter Springs Town homes (AKA Sonoma Pointe) - Preliminary plans for approximately
436 town-homes on 40 acres within the Town Center were received from Engle Homes on July
2 and were reviewed at the July 20 DRC. The City Commission approved a concept plan at its
August 9,2004, meeting and refined it at its September 27 meeting. The City Attorney noted
that the concept plan, as proposed, would require a development agreement or special
exception or both. Final engineering plans were submitted on November 15, and were
reviewed at Dec 16 DRC. The 40 acres has been acquired without platting. The project
engineer met with staff on February 1 for 3 hours to try to identify and work out conflicts
between the plan and the Town Center Code. Staff has noted the significant elevation
differences between the site and the adjacent trail for about 1,200 linear feet and expressed
concern that the site not be segregated from the trail, but instead interact positively with it.
The applicant has hired a new design team and met with staff on May 31 and July 8 to
summarize outstanding issues. Staff met with the applicant's traffic consultant on June 29 to
define the scope of the traffic study. The applicant's engineer has inquired of an early work
permit, but has not yet submitted preliminary or final engineering plans. On August 29, staff
received an aesthetic review package (it is now called Sonoma Pointe at Town Center). The
aesthetic review was addressed at the September 20 staff review. A meeting between the
applicant's team and staffwas held October 19. The state required a letter from the City's
Local Planning Agency, stating that crossing the Cross-Seminole Trail with underground
utility lines is consistent with the City's Comprehensive Plan (approved at the December 6
LP AlP &Z meeting). The aesthetic review was discussed at the December 20 staff review and
again informally on January 27. The incomplete combined preliminary and final engineering
plan submittal was reviewed at the February 7 staff review. 02/13/06 agenda
(8) JDC Calhoun/. Construction continues. Buildings 8, 9, 10, 11, 12, 13, and 14 have
received certificates of occupancy (COs). Building 1 has received its certificate of completion
- Tijuana Flats, Art Avenue, Barney's, Christiano's Wine Bar Cafe and Gian Carlo's have
received COso Building 2 received a certificate of completion" on the shell; the Marble Slab
Creamery and a video store on the first floor and the James Doran and Home Town Mortgage
offices on the second floor has received COso City records indicate the following businesses
are locating or have located in the JDC Calhoun Town Center:
Building 1 - Tijuana Flats, Art Studio, Cristiano's, Barnie's, and Giancarlo's;
Building 2 - Marble Slab Creamery, James Doran office, Home Town Mortgage, Dr. Herba's
Chiropractic office, and The Party Store;
Building 8 - Leslie Pool Supply, a dentist, and a tanning salon, Edward Jones; Century 21
offices.
Building 9 - Red Bug Cleaners, E-Nails, Great Clips, Famous Uncle AI's Hotdogs, and
Subway;
Building 10 - Washington Mutual;
Building 11 - State Farm, H & R Block, Rachel Nicole's Salon, Shape Xpress, and a dentist;
Building 12 - Publix;
Building 13 - Winter Springs Liquors, Mailboxes, Etc;
Building 14 - China Feast; and
Building 15 - Wendy's.
On January 24,2005, the City Commission approved final engineering plans from Lochraine
Engineering for the northeast portion ofthe JDC site (that area north of Tree Swallow Drive
February 27, 2006
Information Item 500
Page 4
and east of Cliffrose Drive including buildings 3, 4, & 16). A pre-construction meeting was
held on March 15 for the 2 acre portion of the approximately 15 acre site. On October 13, the
engineering inspector estimated site work on the 2 acres to be about 80 percent complete.
Revised final engineering plans for this 2 acres were approved at the April 25 City
Commission meeting. A third iteration of the final engineering plan was approved at the
September 26 Commission meeting.
Building elevations for Building 3 (2 story & 15,620 SF) were approved at the May 9, 2005,
City Commission meeting. Building plan issues regarding a fire riser room location and the
location ofthe 2 internal stairways were resolved at the October 10, 2005, Commission
meeting. Staffhas approved the building plans for building 3.
Building 4 (combination 7,800 SF first floor retail and restaurant with second and third floor
residential condominiums with a fourth floor penthouse suite - 15 residential units) was
approved for aesthetic review on September 12, although the Commission voted to have the
applicant corne back to show a combination of 2, 4, and 6 foot deep balconies.
Building elevations for Building 16 (11,095 SF) were approved with conditions at the June 13,
2005, City Commission meeting; revisions with a trellis at the west end and other minor
modifications were approved on September 12. Building plans have been approved for
Building 16.
The Commission approved a concept elevation of Building 17 (a 26 unit residential
condominium) at the September 12 meeting, noting that a number of site issues (e.g. parking,
access, and the space adjacent to the traffic circle) must be resolved with the site plan. The
concept site plan and a development agreement were approved at the October 10, 2005,
meeting. The Doran team advises that they have purchased the necessary portion of the
Kingsbury horne-site for the proposed Building 17. The parcel for building 17 and building 4
will be "formalized" in a development agreement and will be platted. per 02/27/06 agenda
(8 A) Town Center Phase II The Doran team met with staff on June 2, 2005, to outline their
plans for 331 apartment and condominium units, 43,000 square feet of retail, 354 structured
parking spaces (multi-level parking garage), and surface parking (on-street and parking lots) on
the east side of Tuskawilla Road. An updated projection by the development team on August
11 divided their proposed development east of Tuskawilla Road into Phase II A and rID, with
no vertical construction east of the Trail bridge, due to wetland issues. Phase II A plans were
submitted on February 7 for 33,452 square feet of retail and 292 residential units on 7.75
acres. The build-out for phases II A and rID totals 400,000 square feet ofretail, 300,000
square feet of office, and 700 residential units, with 2 and possibly 3 parking structures. A
Phase II development agreement was approved by the City Commission on October 17,2005.
New wetland lines have yielded as much as 25 percent less developable land than previously
expected, east of Tuskawilla Road. The Doran team states that this requires them to go
vertically, to try to get the same yield from less developable area. per 02/27/06 agenda
(9)Artesian Park (formerly Lincoln Park) - A concept plan for 106 (was 113) town homes on
the 8 acre site, located on the south side of Orange Avenue, between Jesup's Landing (185
February 27, 2006
Information Item 500
Page 5
units on 17.15 acres) and Tuskawilla Trace, was approved, subj ect to conditions by the City
Commission on March 14, 2005. The plan depicted roadway connections with Jesup's
Landing, use ofthe shared alley with Jesup's Landing, 2 boulevards with water features in the
medians, some town homes around a plaza, and some town homes with small back yards and
detached garages. On July 27, the applicant submitted a modified concept plan that included
only one boulevard with a median water feature. The revised concept plans were approved at
the October 10, 2005, meeting. Final engineering/subdivision plans were submitted on
November 21 and were reviewed at the December 6 staff review. Revised plans were
submitted on November 28 for Orange Avenue (both Artesian Park and Jesups' Landing are
dependent upon reconstruction of Orange Avenue to Town Center standards). Dover Kohl,
staff, and the applicant's team have been trying to best address the concept oflive-work units,
raised door-yards, and courtyards at grade (since the applicant has determined that the
Brownstone concept is financially impractical for this site, due to the amount of fill material
that would need to be imported). per 02/13/06 agenda.
(10) Jesup's Landing (previouslyBarclay II and then Jessup Reserve )185 Units. At its
October 11, 2004, meeting, the City Commission approved a concept plan for as many as 207
town house units with rear-loaded 2 car garages and 128 on-street parking spaces on 17.15
acres along the south side of Orange Avenue. A development agreement and revised concept
plan for 185 units were approved at the February 28 City Commission meeting. On May 9 the
City Commission approved the Town Center Phase I Site Development Permit Agreement.
The final engineering/subdivision plans were approved at the June 27 City Commission
meeting. The aesthetic review was approved at the September 26, 2005, City Commission
meeting. Revisions to the final engineering plans (addressing specimen trees, bus shelter, &
lift station) were approved at the October 10,2005, meeting. The final plat for Jesup's
Landing was approved at the 11/14/05 City Commission meeting. On November 30, staffmet
with both the Jesup's Landing and Artesian Park development teams, to discuss the shared
alley easement that both subdivisions will use. The Jesup's Landing final plat revision was
approved by the City Commission at the January 9 meeting, to incorporate minor
modifications, based on discussions and negotiations between the two developers and the City,
regarding an easement along the project's eastern property line. Crews have de-mobilized
from the proj ect until a decision is made regarding whether or not to surcharge or stabilize by
some other method. This is due to large quantities of deep muck. Soil borings are presently
being conducted to determine the extent of the muck and what to do about it. Revised plans
for Orange Avenue were submitted on November 28 (Jesup's Landing and Artesian Park are
both dependent upon reconstruction of Orange Avenue). per 02/13/06 agenda
(11) Highlander Property(aka Jesup Reserve and Barclay Town Center) -161 units. A
concept plan was approved on August 23, 2004, for as many as 170 town home units on 11
acres of what was then an unincorporated county enclave, located between Tuskawilla Trails
and SR 434. An Annexation and Pre-development Agreement was approved at the September
20, 2004, City Commission meeting. Reynolds, Smith and Hills (RSH) met with the staff
DRC on October 12 for a pre-application meeting. The property was annexed on October 25,
2004. The Future Land Use designation has been changed to Town Center. A revised concept
plan for 160 units was approved at the March 28 Commission meeting and must be added to
the existing agreement as a modification. Final engineering/subdivision plans were submitted
on March 21. As a result of discussion about the adjacent property to the west, the applicant
February 27,2006
Information Item 500
Page 6
has revised a plan for that northwest comer of the site to remove the frontage road (the City
Commission may waive the frontage road requirement of Subsection 20-325 (c) (8)). An
initial aesthetic review with staff occurred at the 05/17/05 staff review. Revised final
engineering/subdivision plans were approved on August 8, 2004, in conjunction with a
development agreement modification. Site work had begun prior to final engineering
approval, pursuant to the Site Development Permit Agreement approved by the City
Commission on May 9,2005. The aesthetic review was approved at the September 26,2005,
City Commission meeting. The final plat for Jesup's Reserve was approved at the 11/14/05
City Commission meeting. The plat and restrictive covenants have been recorded. Crews have
completed the potable, sanitary, and storm water system to include the offsite system along
Nature's Way and are constructing the stabilized road base and curbing. An application for
an on-site sales trailer was received February 13. per 02/27/06 agenda.
(12) Tuskawilla Office Park - Certificates of occupancy have been issued for buildings 4 - 8
and 11. Building inspection have worked with the contractor for Building 1 to rectify
electrical and mechanical issues. The orientation of Building 1 (designed to front on
Tuscawilla Road and built to front onto the parking lot) has been an issue. Building 1
continues to move toward completion. All framing inspections were completed on October 26,
2005. Insulation/energy inspections were completed and approved on October 28,2005.
Building 1 is being prepared for a final inspection (the last inspection was December 13).
Staff has reviewed building plans for Building 10. A new contractor has been hired for
Building 9. An applicant has been speaking to staff about combining the 2 empty lots along
Tuskawilla Road into one buildable lot and adding parking. They have met with Dover Kohl
and Partners and had a pre-application conference with staff on November 4. per 02/27/06
agenda
(13) Villa Grande - On September 12, the City Commission approved a concept plan for 152
residential condominiums (estimated to be 1,260 - 1,800 square feet each) on 4.75 acres within
the Town Center, between City Hall and Doran Drive. The project is comprised of 5
residential buildings, each with first floor parking and residences above. Two of the buildings
have 3 floors of residences above parking, two have 4 floors of residences above parking, and
one has 5 floors of residences above parking. A separate club-house is provided along Doran
Drive, at the terminal vista at the west end of Blumberg Boulevard. The applicant and staff
have been discussing allowing the site to drain into the City's storm-water pond in return for
design and reconstruction of a portion of Doran Drive to Town Center specifications. A final
engineering/site plan was submitted on October 17 and reviewed at the November 1 staff
review; a revision was submitted on December 16 and was reviewed at the January 17 staff
review. Additional discussions between staff and the developer have been on-going to finalize
roadway cross-sections, sidewalk widths, and proposed architectural changes. per 02/13/06
agenda
(14) Lake Jesup Shores - Preliminary engineering/subdivision plans for 68 (now 80 units)
townhomes on 8.7 acres within the Down Town, across SR 434 from Heritage Park, were
received on March 24 and were reviewed by staff on April 12, 2005. Revised preliminary
engineering plans were to be reviewed at a special May 19 staff review, was deferred at the
applicant's request. On June 16, the City Manager and staff met with the property owner, Tom
Daly, and the builder to discuss the outstanding issues. A meeting was then held in South
February 27,2006
Information Item 500
Page 7
Miami among the applicant, the City Manager, and Dover Kohl and Partners on July 15. On
August 29, Dover Kohl and Partners notified staff that a subsequent iteration that had recently
been provided to them was a major improvement over the earlier designs, but still had certain
front-back issues. Ryland Homes is the prospective builder and the subdivision is planned by
the Daly Design Group. A preliminary engineering re-submittal for 80 units was received on
October 3,2005, and was reviewed at the November 1 staff review (subsequent iteration was
provided to Dover Kohl and Partners). A February 7 resubmittal is scheduled for staff
review on the February 21. per 02/27/06 agenda
(15) Landings at Parkstone - 104 Town Home units. A PUD master plan amendment,
preliminary subdivision plan, and final subdivision plan were approved by the City
Commission at its July 26,2004, meeting. On September 1, a revised final engineering plan
was submitted, proposing to re-locate the entrance more southerly along Parkstone Boulevard
and lower the approved final grade. A revised Development Agreement (DA), PUD master
plan amendment, modified final engineering plans, and aesthetic review were discussed at the
December 13,2004, Commission meeting and were approved on January 10,2005. A pre-
construction meeting was held on Monday, February 7 and Blue Ox Construction has been
doing the site work. Water and sewer lines are in place, the roadways are paved, and staff
estimates that site work is approximately 98 percent complete (as of October 13). A request
by Morrison Homes to amend the DA to allow construction of model units before platting was
approved on May 23. A master file (no building permits) for at least some of the units was
released July 26 (to expedite permitting). Staffhas issued the building permits for the model
units, which will be located on lots 98 thru 101. The final plat and HOA documents were
approved on August 8, 2005, and have been recorded. Staff is currently working with the
developer on a final landscape design for the project's frontage with S.R. 434. The DA was
amended at the January 9 meeting, to accommodate the proposed back porches that face the SR
434 ROW. per 01123/06 agenda
(16) SR 434 Retail (a.k.a. Villagio) Construction of one of the unfinished out-buildings
appears suspended. The Flower Shop, Bicycle Shop, Spring Liquor Store, Curves Ladies
Fitness, Spring Nails, Trustco bank and a cellular telephone company office are the current
tenants. The City Commission validated that the project is built in substantial accordance with
the approved final engineering plans and accepted the water and sanitary sewer infrastructure
for ownership and maintenance at the April II , 2005, meeting. Staff spoke to the owner on
October 24, 2005, to inform him that the permit for Building "C" had expired and that the
contractor would need to renew the permit. The owner has advised staffthat he would have
the contractor of record pull a renewal permit (no new application has been received). per
02/13/06agenda
(17) Stonebridge Construction - A request for conditional use to construct multi-family
housing on 1.7 acre site in C-l zoning, located on south side of SR 434, just west of
intersection with SR 419, was postponed at the December 12 City Commission meeting. Staff
was directed to investigate the possibility that the unimproved Celery Avenue could connect to
Hayes Road, the traffic impacts of various types of development, the potential ramifications of
piecemeal development, and the fiscal impact on the City of converting commercially
designated property to multi-family residential. The conditional use was approved at the
January 23 City Commission meeting. per 02/13/06 agenda
February 27,2006
Information Item 500
Page 8
(17-A) Talis Crossing Subdivision - On December 13, 2005, staff received a subdivision plan
to create 4 lots from a vacant and treed 9.07 acre tract along Fisher Road (also abuts Tusca
Trail- a private roadways). The property abuts the southern edge of Dunmar Estates to the
north and unincorporated Seminole County to the east. A 175 foot wide Florida Power
Corporation easement extends generally north and south through the property. The plan was
reviewed at the January 17 staff review; revised plans were submitted on February 7 for the
February 21 staff review. per 02/27106 agenda.
(18) Dunlevy Lot Split - On November 22, David Dunlevy requested a lot split, to divide a
3.21 acre lot with an existing home at 235 E. Panama Road into 1.22 and 1.99 acre lots. The
request was approved at the January 23 City Commission meeting and the lot split resolution
was recorded on February 7. per 02/27/06 agenda
(19) Starlight Baptist Church - On November 1, Starlight Baptist Church submitted a
conditional use application to expand their existing facility on Hayes Road and a site plan for
the expansion. The site plan and conditional use applications were reviewed at the November
22 staff review. The Church was asked to provide additional information before being
scheduled for the Board of Adjustment. per 12/12/05 agenda
(20) Medallion Convenience Store - Final engineering/site plans were submitted for a
convenience store and car wash at the SW comer of SR 434 and Hayes Road, on March 24,
2004. This site is adjacent to the intersection that was demonstrated to need an east-bound
right-hand auxiliary turn lane. The applicant's team has been advised of City Commission
concerns about a car wash at that location. Staff (including the City Attorney) met with
applicant on November 22, 2004, to discuss application status. On August 10, 2005, another
potential applicant met with staff to discuss building a shopping center at this site. per
08/22/04 agenda
(21) Carnero Office Site - On October 15,2004, the final engineering plans to convert an
existing residence (approximately 1,400 SF) at the NW comer of Charles Street and SR 434
was received by the City. Final engineering/site plan and the associated waiver requests were
approved at the March 28, 2005, City Commission meeting. An aesthetic review was
approved at the Apri125 City Commission meeting. As of February 1, the parking lot permit
had been issued, but the wall permit and bathroom permit had not been issued. per 02/13/06
agenda
(22) Public Works Site Plan - Final engineering plans for the City Public Works complex on
Old Sanford-Oviedo Road were received on December 23,2004, and reviewed at the January
11,2005, DRC. A concept plan was provided to the City Commission as an informational
item at the January 10, 2005, City Commission meeting. A revised site plan was reviewed at
the July 5 staff review. A subsequent meeting was held between Public Works staff, CPH, and
the site engineer. The site plan was approved at the September 26, 2005, City Commission
meeting. At its January 23 meeting, the City Commission authorized a contract with Ruby
Builders for construction of the site and certain buildings. per 02/13/06 agenda
February 27,2006
Information Item 500
Page 9
(23) Miller School Supply - Final engineering/site plans were submitted January 27,2005 for
a 10,028 square foot retail building on approximately 1.25 acres of wooded vacant land along
the south side ofSR 434, immediately west of the Cumberland Farms and O'Stromboli's
Italian Restaurant (formerly Papa Tony's). Final engineering/site plans were approved at the
May 9 City Commission meeting. The applicant withdrew a request for a waiver from certain
SR 434 Redevelopment Overlay Zoning District sign regulations. An aesthetic review was
approved at the June 27 City Commission meeting. A development agreement to allow the
proposed building mounted sign with a 6' tall apple was approved at the July 11 City
Commission meeting. A pre-construction meeting was held on December 12. The site has
been cleared and the crew is "recovering" existing utilities that they will connect to. per
02/13/06 agenda
(24) Jordan Lot Split - On November 16, James and J acqueline Jordan requested a lot split, to
divide a 3.12 acre lot with an existing home at 125 E. Panama Road into 1.07 and 2.05 acre
lots. The request was heard at the January 3 staff review. per 01/23/06 agenda
(25) Rosu(Backus)Lot Split - On November 30, Paul Rosu requested a lot split, to divide a
vacant 3.6 acre parcel abutting both Moss Road and E. Panama Road into 2.03 and 1.57 acre
lots. The request was heard at the January 3 staff review. The lot split is scheduled for this
Commission meeting. per 02/27/06 agenda
(26) Venetian Village (formerly the Badcock Shopping Center) - The final site plan,
development agreement, and a general depiction of signage were approved at the June 28,
2004, City Commission meeting. The site plan expired on June 28, 2005. On August 8, 2005,
the City Commission approved two 6-month extensions, extending the site plan to June 28,
2006, for work to commence. A new tenant, BIG UGLY BBQ, is set to open in late February
(per applicant). per 02/13/06 agenda.
(27) Bonyadi Properties - Final engineering plans for a 7,101 SF, 2 story, office building on a
Y2. acre lot at the NE comer of Moss Road and Excelsior Parkway were submitted on May 21,
2004, and were reviewed at the June 8, 2004, DRC. A resubmittal was received on or about
February 28 and was reviewed at the March 29, 2005, DRC. Another applicant met with staff
to determine the potential for town homes on this site and property immediately to the east.
per 12/12/05 agenda
(28) Moss Road International Office Complex - Final engineering plans were submitted on
January 19 for the existing 2.5 acre former State Farm office site, at the SE comer of SR 434
and Moss Road, and the adjacent 0.65 acre vacant wooded lot. The plan is to use the existing
State Farm building and share the large parking area with 2 additional office buildings on what
is now the adjacent vacant property. Final engineering plans and a development agreement
were approved at the May 9 City Commission meeting. A plat to reconfigure the 2 lots was
approved on August 22,2005. A pre-construction conference was held on June 2 and clearing
began on June 29. The utility crew has returned to the site. The sanitary sewer has been
completed from the "tie in" to the City system to the last "man-hole." A building permit was
issued for the Omei Kung Fu Academy on September 15, 2005. An aesthetic review
for the signage was approved at the February 13 Commission meeting. per 02/27/06
agenda
February 27,2006
Information Item 500
Page 10
(29) Saratoga Condominiums (aka Moss Road Town homes) - 84 units. At its April 12,
2004, meeting, the City Commission approved the Metropolis Homes conditional use
application and concept plan to build as many as 84 condominiums and commercial
development on an "L" shaped 9.10 acre site fronting on both SR 434 and Moss Road, adjacent
to the Bank of America and Victorio's Pizza. On September 20, the City Commission
approved a 6 month extension for the conditional use. Ordinance No. 2004-49 extended the
initial approval of a conditional use from 6 months to 2 years. Preliminary site plans and a
draft development agreement (no fee was provided for the DA) were submitted to the City on
April 15 and reviewed at the May 3 staff review. On July 21, the BOA recommended
approval for a waiver ofthe 2 car garage requirement for condominiums at this site (proposing
1 covered space per unit). The waiver request was heard on August 22 and was approved at
the October 10 Commission meeting. On August 26, the applicant submitted final engineering
plans which were reviewed on September 20. Revised plans were submitted November 2 and
were reviewed at the November 22 staff review. A resubmittal is scheduled for the March 1
P&Z meeting. per 02/27/06 agenda
(31) Belle Avenue Warehouse - Plans for a 4 building (3 new buildings totaling 9,000 SF and
one existing 2,728 SF building) warehouse complex on 1.174 acres were approved on August
8,2005. The applicant met with staff on August 10 to discuss setting up a pre-construction
conference and subsequently decided to reconnect power to the residential units and at least
temporarily delay demolition and construction. per 08/22/05 agenda
(32) Highlands Apts., Phase II(a.k.a. Golf Point Apartments) - The 42 unit apartment (3
floor) final site plan was approved on March 8, 2004. There were delays, due to conflict with
the existing storm-water system at Seville on the Green. The FDEP water system clearance
lapsed, due to the contractor-related delay and still holds up the site. On November 7, staff
estimated the site work (not including the building) to be about 98 percent complete. On
September 16, the contractor and staff met to discuss the building and a proposed lighting plan
modification. Planning staff signed off on the revised lighting plan. The FDEP has recertified
the potable water supply system. per 01/23/06 agenda
(33) Harbor Winds (a.k.a. Big Cypress) - 62 Units. The conditional use for town-homes on
the 15 acres east ofthe Golf Terrace Apartments approved at the August 9,2004, City
Commission meeting for a maximum of94 unit (6.27 d.u.lacre). Ordinance No. 2004-49
extended the approval of a conditional use from 6 months to 2 years. Final engineering plans
were submitted January 25 for 90 units; revisions were submitted March 3 and were reviewed
at the March 15 DRC (a subsequent re-submitta1 was received on April 7 and had staff review
on April 19). Revised plans were submitted for 62 units were approved on August 22, 2005.
A pre-construction conference was held on August 31 and site clearing has commenced. The
site crew has finished clearing and removing the debris and is now importing fill, digging the
ponds, and balancing the site. A final subdivision plat submittal was received October 12 and
reviewed at the November 1 staff review. Staff's review of a resubmittal found that the plat
"lessed out" small areas along the northern site boundary, making the plat inconsistent with the
approved final engineering plans and the legal description in the development agreement. Site
crews have been importing fill to balance the site. Wall construction has been slow, due to the
water table and patches of unsuitable soil. per 02/13/06 agenda.
February 27, 2006
Information Item 500
Page 11
(34) Ditmer Large Scale Comprehensive Plan Amendment - The Keewan Real Property
Company has filed a large scale comprehensive plan amendment for 4 parcels totaling
approximately 47.27 acres, located south of Shepard Road and east of US 17-92, to change the
Future Land Use designation from Industrial to Medium Density Residential (3.6 - 9.0
d.u./acre). The properties have C-2 and PUD zoning (no development agreement). The City
Commission voted to transmit the amendment to DCA at the February 13 meeting. per
02/27/06 agenda
(35) Dlutz (Apex)Transmission ShoplWallace Plat - The final engineering/site plan and
aesthetic review were approved at the October 25, 2004, City Commission meeting. The
revised site plan was approved at the June 27, 2005, City Commission meeting. The final plat,
dividing the 0.95 acre transmission shop site from the rest of the 1.58 acre property was
approved at the August 8, 2005, City Commission meeting. per 08/22/05 agenda
(36) Nursery Road (Phil Reece) - The final engineering/site plan was approved at the March
8, 2004, City Commission meeting and a preconstruction meeting was held on March 30. The
City Commission approved the aesthetic review of the first new building at its July 12, 2004,
meeting. The City Commission validated staffs recommendation that the site was built in
substantial accord with the approved final plans and accepted the potable water and sanitary
sewer at its June 27, 2005, meeting. Staff met with Mr. Reece on November 7 to begin to
determine a signage plan for the site. The aesthetic review of building # 5 was approved at the
November 28 City Commission meeting. The new building slab has been poured. per
01/23/06 agenda
(37) Penez Auto Shop - A preliminary engineering/site plan was submitted on August 19,
2005, for a 2,100 square foot shop on a 0.29 acre undeveloped and treed site, located on the
south side ofSR 434, approximately 800 feet east of US 17-92. The site has C-2 zoning, a
Commercial FLU designation, and is located within the SR 434 Redevelopment Overlay
Zoning District. City of Winter Springs potable water and sanitary sewer do not appear to be
located within close proximity of the site. The site plan was reviewed at the September 6 staff
review. A re-submittal without the applicant's responses to staff comments was received on
October 3, 2005, and reviewed at the October 18 staff review. A resubmittal was received
on January 21 for staff review. per 02/13/06 agenda
TOWN CENTER (DOWNTOWN)
PROJECT DEVELOPER TYPE # OF UNITS ACRES
J esup' s Landing Levitt & Sons Townhomes 185 17.2
J esup Reserve Levitt & Sons Townhomes 161 11
Winter Springs Townhomes Engle Homes Townhomes 436 40
Lake J esup Shores Ryland Homes Townhomes 80 8.7
Artesian Park VHB Townhomes 106 8.0
Villa Grande LeCesse Condominiums 152 4.75
Doran (Bldgs. 4 & 17) JDC (Doran) Condominiums 41 0.81
Doran Phase II-A JDC (Doran) Condominiums 292 7.75
Total 1,453 98.21
February 27, 2006
Information Item 500
Page 12
REMAINDER
PROJECT DEVELOPER TYPE # OF UNITS ACRES
Barclay Reserve Ashton Woods Townhomes 88 7.4
To Be Named ICI Condo 480+/- 40
Heritage Park Centex Townhomes 158 14.5
Harbor Winds Morrison Homes Townhomes 62 15
Landings at Parkstone Morrison Homes Townhomes 104 12
Saratoga Condos Metropolis Condos 84+/- 9.1
KAI Reserve KAI Properties Townhomes 15 1.7
TOTAL 991 99.7
The City of Casselberry site was removed from the list, since remedial action has been
achieved.
Board of Adjustment
(19) On November 1, the Starlight Baptist Church filed an Conditional Use application to
expand the existing church (in the R-1AA zoning district, pursuant to Section 20-163), located
on 4.28 acres at the NW comer of Hayes and Bahama. The applicant was asked to provide
additional information before being scheduled for a BOA hearing. per 01109/06 agenda
FUNDING: None required
RECOMMENDATION: None required
ATTACHMENTS: Map Locations
COMMISSION ACTION:
January 2006
City of Winter Springs
City of Winter Springs
Town Center Master Plan
Status Update
October 2005