REQUEST: The Community Development Department requests that the City Commission and
Local Planning Agency (LPA) conduct a special meeting to review the
recommendations of Land Design Innovations (LDI) for the Evaluation and Appraisal
Report (EAR) based amendments to the Capital Improvements, Intergovernmental
Coordination, Housing, Recreation and Open Space, and Future Land Use
elements/sub elements of the City of Winter Springs Comprehensive Plan.
PURPOSE: The purpose of this item is to solicit comments and recommendations for the EAR
Based Amendments to the Comprehensive Plan from the City Commission and LP A,
prior to formal consideration and transmittal to the Department of Community Affairs
(DCA).
CONSIDERATIONS:
The Comprehensive Plan is the guiding document that identifies the future
development patterns in the City and the services that will be necessary to meet the
demands of future growth. The City's Comprehensive Plan was adopted in 1992 and
was based primarily on data available as of 1990. The City is required by State
Statutes to prepare an evaluation of the Comprehensive Plan and update the
Comprehensive Plan with current data every seven (7) years. The City successfully
completed the evaluation of the Comprehensive Plan, which was determined sufficient
by DCA.
The City originally had until September 26, 2000 to complete the update of the entire
Comprehensive Plan, which afforded the Comprehensive Planning Coordinator
eighteen (18) months to complete the task. The Comprehensive Planning Coordinator
subsequently requested a six (6) month extension to complete the amendments by
March 26, 2001, and the request was granted by the State. However, the
Comprehensive Planning Coordinator left the City on March 26, 2001 without having
completed any of the required updates to the plan. The Community Development
Director reviewed the situation and immediately requested another six (6) month
extension from the State to complete the EAR Based Amendments. In response, the
October 4,2001
Regular Agenda Item A
Page 2
State extended the deadline to September 26, 2001 in a letter dated May 4, 2001; the
State has no authority to issue additional extensions. Therefore, if the Comprehensive
Plan updates are not completed by September 26, 2001, the State will no longer allow
the City to process large scale comprehensive plan amendments.
The Evaluation and Appraisal Report for the Comprehensive Plan identified that the
entire document was poorly written and should be completely re-written as part of the
EAR Based Amendments. This was an enormous undertaking that was further
complicated by the resignations of both the Comprehensive Planning Coordinator and
Current Planning Coordinator in March 2001. Consequently, a supplemental
appropriation of $46,310 from the General Fund was approved to hire LDI to prepare
the EAR Based Amendments to the Comprehensive Plan.
STATUS REPORT AND ADOPTION SCHEDULE:
A complete copy of the comprehensive plan, containing second drafts of all elements
was distributed on September 11,2001. This submittal addressed and/or included the
comments and recommendations of the City Commission, LP A and staff.
Based on discussions by the City Commission and LPA, specific elements of the
comprehensive plan were planned for discussion over a series four (4) special
meetings, as shown below:
Special Date Comprehensive Plan Elements Discussion Status
Meetine:s
1 09-l3-01 Population, and Transportation Complete
2 09-25-01 Conservation, and Solid Waste Complete
3 10-01-0 I Water, Sewer, Drainage, and Complete
Aquifer Recharge,
4 10-04-0 I Capital Improvements, Incomplete
Intergovernmental Coordination,
Housing, Recreation and Open
Space, and Future Land Use
Following the completion of the scheduled special meetings, the plan adoption
schedule is projected as follows:
. October 23,2001
. November 7,2001
. November 26,2001
. December 10,2001
. April 2002
Submittal of Final Plan Draft by LDI for LP A Hearing
LP A Hearing on Plan (regular meeting)
City Commission Transmittal Hearing (regular meeting)
Deadline to Transmit Plan to DCA
DCA Deadline to Issue ORC (Objections,
Recommendations & Comments Report)
LP A Adoption Hearing
City Commission Adoption Hearing
. May 2002
. May 2002
October 4, 200 I
Regular Agenda Item A
Page 3
RECOMMENDATION:
Staff recommends that the City Commission and LPA REVIEW, RETAIN, AND
BRING the complete draft of the Comprehensive Plan to the special meeting for
discussion, in order to provide direction to LDI.
COMMISSION ACTION: