HomeMy WebLinkAbout2006 01 23 Informational Item 506 Status of Capital Improvement Projects
COMMISSION AGENDA
ITEM 506
INFORMATIONAL
January 23, 2006
Meeting
MGR/DEPT/
Authorization
REQUEST: Public Works Department is advising the City Commission of the status of
various Capital Improvement Projects
PURPOSE: This agenda item is to update the Commission on the status of current
Capital Improvement projects.
CONSIDERATION:
TRAFFIC/TRANSPORTATION IMPROVEMENT
SR 434 Improvements (Village Walk) -Liquidated damages are being tracked as contract time
has expired. Some portion of the contingency funding provided by the city will be required for
the CEI cost beyond the original contract period. Substantial Completion awarded on
December 10, 2005. Contractor has 30 days to complete all remaining Punch List items
before additional liquidated damages are accessed. A walkthrough with FDOT performed
January 12. Liquidated Damages have not at this time been resolved. CEI cost has
currently exceeded the contingency funds provided by the City from the 1999 One Cent
Sales Tax Agreements. (1/13/06)
SR 434 Town Center Corridor Analysis - City representatives met with FDOT Secretary
Stuttler on January 5th and expect a response to our median spacing request by the end of
the month. (1/23/2006)
SR 434/ Hayes Road Turn Lane - Design is complete and traffic accident information has been
forwarded to PEC for development of traffic study. Survey has been completed and city attorney
continues work for obtaining the needed Right of Way. (11/8/05)
SR 434 / Doran Drive Traffic Signal - Notice to Proceed has been issued to Traffic Control
Devices (TCD) to order the mast arm traffic signal and to Central Florida Environmental (CFE)
to begin the road work. A preconstruction meeting was held 1 November with all stakeholders
for the intersection improvements to be coordinated. Anticipate construction of turn lane on
Doran Drive to begin first week of January. Developer's contractor expects his portion of the
intersection improvements of McLeod's Way to be complete prior to the CFE beginning work
January 23, 2006
Information Item 506
Page 2
the first week of January to avoid conflict. Traffic Control Devices has completed the
installation of the mast arm foundations along with the pull boxes and conduit. TCD
expects delivery of the traffic signal mast arms mid to late January. CFE will be on site
mid January to allow more time of the offsite work to be completed. (1/13/06)
Cross Seminole Trail Connector (Wade Street to Wekiva Trail) - Staff is working with County
staff on evaluating the wetlands along the preferred route. The City Manager and Mayor are
working with Rep. Mealor on state and/or federal funding for this alternative. The wetlands have
been flagged and staff met with Seminole County and the consultant on May 25th.. Seminole
County is pursuing legislative funding in the coming session. (10/10/05)
Magnolia Park Phase II - Phase II of Magnolia Park consists of the construction of the
Amphitheater with restrooms and drinking fountains to act as a trail head for the Cross Seminole
Trail and an inter active water feature in this 0.67::1:: acres. Starmer Ranaldi Planning and
Architecture, Inc (SRI) was approved by the Commission on January 10, 2005, for the
architectural services. CPR Engineers, Inc has been authorized by the Commission under
Amendment 78 on June 9, 2003, for services related to the landscape and hardscape design in
conjunction with SRI. Both SRI and CPR Engineers are currently developing the plans for the
construction of Magnolia Park Phase II. Survey and assessment of wetlands northeast of the
Cross Seminole Trial being conducted to determine possible impacts and cost associated
with moving the trail to accommodate the amphitheater/trailhead design. (1/17/06)
Blumberg Boulevard Trail - The Blumberg Boulevard Trail consist of the construction of the
trail with amenities from Magnolia Park to the intersection of Blumberg Boulevard and Doran
Drive. The trail will have stone pavers with sitting arboretum and proposed sculpture gardens, to
include the Rotary Club sponsored Veterans Memorial. Starmer Ranaldi Planning and
Architecture, Inc (SRI) was approved by the Commission on January 10, 2005, for the
architectural services. CPR Engineers, Inc has been authorized by the Commission under
Amendment 78 on June 9, 2003, for services related to the landscape and hardscape design in
conjunction with SRI. Plans are 85% complete with comments being solicited from staff.
Easement application to the Department of Environmental Protection, Office of Greenways
and Trails submitted to allow for the proposed crossing of the state lands. (1/17/06)
Central Winds Park Way - Final road design ongoing by CPR. Additional right of way has
been requested from the Leerdam property and they will be submitting a conceptual site plan to
the City Commission. Final Plan review will incorporate their proposed site plan.(4/18/05)
Winter Springs Boulevard Reconstruction - Preliminary report was presented to the City
Commission on April 11th. Staff is evaluating the costs of all projects in the One Cent Sales Tax
to develop a schedule. The initial cost estimate for reconstruction is 2.4 million dollars. PEC
awaiting completion of survey to complete design work. (1/13/06)
Village Walk Beautification Phase II Trees - The project to install shade trees in the Right
of Way and Beautification Easements from Wade Street to Belle Avenue was estimated to
cost up to $90,000. The Urban Beautification Coordinator and City Forester have
investigated various options of trees sizes and have developed a plan to reduce the cost to
the city to only $35,000 with maintenance by city staff. (1/13/06)
January 23, 2006
Information Item 506
Page 3
SR 434 Beatification Trees and Curbing - Completing plan design by CPH pending funding
becoming available for plan to be submitted for FDOT Highway Beautification Grant
(1/13/06)
Orange Avenue Extension - Initial scope development under consideration by Staff.
(1/13/06)
UTILITY
Utility/Public Works Compound - Design is 100% complete. Payment to River Run, Inc for
wetland mitigation made on November 11. Easement forwarded to FDEP. Advertisement for
Invitation to Bid ran on Sunday, October 30th with Bid Opening on December 14. One bid
received from Ruby Builders. Initial bid exceed funding. Meeting held with Ruby Builders
to negotiate priced and project scope. Recommendation to be presented to Commission on
January 23. Permits from FDEP and ACOE received. (1/23/06)
Well #4 - Well development complete. Retesting various water quality samples as requested
by FDEP. Meeting with Sunshine pending for negotiation of contract cost adjustments due
to rising construction cost since initial contract in 2003. (1/19/06)
Reclaimed Water Augmentation - Final Draft was presented to the City Commission on 11/14.
Augmentation project has been submitted to SJRWMD for funding. (1/23/06)
Tuskawilla Road Stormwater Improvements - The scope of this project to install two 24" storm
pipes and fill the existing ditches along with a strainer/ trash collection box with spreader swale
to improve the quality of run off entering Lake Jesup from Tuskawilla Road North of St. Johns
Landing and Orange Avenue. The contract was awarded to Sunshine Building and Development
with a pre-construction meeting held on June 16th. . Construction is complete. (1/18/06)
Electrical Improvements WTP #3 - Project advertised for bid on December 18, 2005 with a
pre-bid meeting held on January 4, 2006. The bid opening is scheduled for January 18,
2006. (1/13/06)
Village Walk Overhead Utility Undergrounding - Cost received by Progress Energy on August
5, 2005, Progress Energy provided staff with the cost to convert Progress Energy's lines from
overhead to underground. The cost was $403,017.00. Additional cost may be incurred to provide
property owners that have parking lot lighting installed on the power poles with an alternative
lighting solution. The cost provided by Progress Energy does not include the cost to bury other
utility lines. The cost to bury these lines is usually 50% to 75% of the cost to convert the power
lines. There are up to four other utilities with lines on the Progress Energy poles. The estimated
cost to convert these lines is $806,032 to $1.2 million. Total cost to convert the overhead utility
lines to underground is $1.2 million to $1.6 million. (1/13/16)
PUBLIC BUILDINGS
January 23,2006
Information Item 506
Page 4
City Hall Expansion - The design of the expansion of City Hall was approved by the
Commission on February 28, 2005. Starmer Ranaldi Planning and Architecture, Inc (SRI)
provided the design of this 4,980 square foot addition to City Hall in the northwest corner of the
City Hall building. New layout presented to Commission at 8/1 workshop and direction
received. 40% Plans presented to staff for comments week of January 3. Comments due
back to SRI the week of January 23. (1/13/06)
PARKS AND RECREEATION
Senior Center Therapy Pool - Awaiting Statement outlining proposed cost from SRI to
begin initial design work.
FIRE DEPARTMENT
Fire Station House #28 - Initial conceptual site layout proposal requested from CPH.
(1/13/06)