REQUEST: Utility Department Updating the City Commission on the Status of the
Utility and Storl1l1water Rate Study.
PURPOSE: The purpose of this Board item is to provide the City Commission with a schedule
for completion and implementation of the Utility and Stormwater Rate Study.
CONSIDERA TIONS:
Staff met with PRMG on March 6th and to review the status of the Utility and
Stormwater Rate Study. The following schedule was agreed upon.
March 6,2001
March 13,2001
April 1, 2001
April 15,2001
May 1,2001
May 14,2001
June 1,2001
June 11,2001
June 25,2001
COMMISSION ACTION:
None required.
Provide PRMG Utility and Stormwater 20 year CIP's
PRMG meet with Accounting Manager and Meter Services
Manager to review proposed ordinance changes
PRMG provide staff initial output
Staff provide comments to .PRMG
Draft Rate Study
Review with City Commission
Notice to Customers if rate increase
First Reading of Rate Ordinance
Second Reading of Rate Ordinance