HomeMy WebLinkAbout2007 12 10 Consent 207 Contract J Raymond ConstructionCOMMISSION AGENDA
ITEM 207
ADD-ON
December 10, 2007
Meeting
Consent X
Information
Public Hearin
Re ular
MGR. /De t. ;~
REQUEST: Community Development Department, Urban Beautification Division,
requesting permission from the City Commission for the City Manager to enter into a
contract with J. Raymond Construction for the construction of sidewalk improvements in
front of Building 4 in the Town Center at a cost of $73,552.
PURPOSE: This agenda item is needed for the City to enter into a contract agreement for
public sidewalk improvements in front of Building 4 of the Town Center to coincide with
the completion of building construction.
CONSIDERATIONS:
• Town Center Building 4 is currently under construction at Tuskawilla Road, north
of Tree Swallow Drive, directly adjacent to Building 3. Construction of Building 4
is expected to be complete within the next 45 to 65 days.
The original design plans for Building 4 maintained the existing angled on-street
parking in front of the building along Tuskawilla Road. The City desires to have
the on-street parking in front of Building 4 converted to parallel parking to create
wider sidewalks along Tuskawilla Road, similar to the existing sidewalks in front of
Buildings 1, 2 and 3. In addition, the Building 4 finished floor elevation has been
set based on the planned conversion to parallel parking; therefore, it would be
difficult to maintain the existing diagonal parking and still meet sidewalk design
standards.
• The sidewalk in front of Building 4 must be complete before a certificate of
occupancy can be granted and tenants can occupy the building.
121007 COMM Consent 207_Building_4_Sidewalk Add-On
121007_COMM_Consent_207_Building_4_Sidewalk_Add-On
Page 2 of 2
The City solicited proposals from the following companies pursuant to construction
of this project with the following results.
Construction Firm Result
Southland Construction, Inc. Declined bid
R.A. Rogers Construction Company Declined bid
J. Raymond Construction $73,552
Southeast Enviroscape, Inc. Declined bid
JDC/Isis Construction Declined bid
FUNDING:
Funding for this project will come from the Road Improvements Fund Line Code (11 S-
65000-3011A) in the amount of $73,552, payable to J. Raymond Construction, as outlined
in the construction cost estimate provided to the City on October 15, 2007.
RECOMMENDATIONS:
It is recommended the Commission authorize the City Manager to enter into a contract
agreement with J. Raymond Construction for the construction of sidewalk improvements
in front of Building 4, as per plans provided by Starmer Ranaldi Architecture, Inc., in the
amount of $73,552.
ATTACHMENTS:
A) J. Raymond Construction Cost Estimate (October 15, 2007)
B) Building 4 Sidewalk Project Design - Starmer Ranaldi Architecture, Inc.
(August 21, 2006)
COMMISSION ACTION:
Town Center Building 4 Sidewalk Redesign
J Raymond Construction
Construction cost estimate 465 West Warren Avenue
Longwood Florida 32750
15-Oct-07 Contact: Scott Bryan
Plan Sheet Al & A2 dated 6/1/06 407-948-3384 J. R A Y M Q N
Architect: Starmer Ranaldi ecMSYwucT~oN
Demolition and rework of all pavers along Tuskawilla Rd. at Bldg. 4
Descri tion Quantit unit cost Subtotal Total
Demolition
remove curb 150 If $10.00 $1,500.00
Repair/compactsubgrade 1 EA $1,500.00 $1,500.00
Remove existing planter & structure 1 ea $1,500.00 $1,500.00
remove pavers 1750 sf $1.50 $2,625.00
dumpsters for debris 5 ea $500.00 $2,500.00
remove striping 1 ea $750.00 $750.00
Relay existing Pavers 1100 sf $2.00 $2,200.00
Concrete
surveying 1 EA $1,000.00 $1,000.00
new curb and gutter 140 If $23.00 $3,220.00
planter foundations 3 cy $500.00 $1,500.00
ribbon cuffing 250 If $22.00 $5,500.00
Handicap Ramp (block out for ADA pavers) 1 EA $1,000.00 $1,000.00
Masonry
8" CMU 180 blk $12.00 $2,160.00
filled cells 10 cy $150.00 $1,500.00
precast wall cap 72 If $30.00 $2,160.00
New pedestrian concrete pavers 3000 sf $6.00 $18,000.00
Seal new pavers 3000 sf $0.50 $1,500.00
ADA Handicap Pavers 50 sf $10.00 $500.00
Miscellaneous
Trash Receptacle 1 EA $500.00 $500.00
Keystone Ridge Benches (2) 2 EA $750.00 $1,500.00
Arcustone on Planter walls 150 sf $10.00 $1,500.00
Stucco inside of planter walls 150 sf $7.00 $1,050.00
Landscaping by city $0.00
Irrigation 1 Is $1,200.00 $1,200.00
Empty Conduit for speakers 1 Is $1,000.00 $1,000.00
Light Pole relocate by City $0.00
Electric in planters 1 Is $2,000.00 $2,000.00
Tree grates by City
$0.00
General Contractor supervision 3wks $1,500.00 $4,500.00
General Contractor general conditions 3wks $1,000.00 $3,000.00
Construction subtotal $66,865
Overhead and profit 10 % $6,687
Project total x73,552
A+}~~~M~+ ~~~
~~
~~~~r~a ~~~~~~
~~~~~~~ IaQ~~~
9
~ Q6~9 ~~
~;
~fda
404 ~~
.~
A 4
a ~
~~~ ~°
a,b~
~ '~ ~~ #
~....
~ ~ W.S. Town Center
[ ~ F a a ~ ~ &~, 3 nd 4 8Ma-Waft Re-0eelyn
'r whtar SprYgs, FlorWa
~ Plan
~~
~ ~~
.~
~g
I
I
1
A~~~~ ~~~~ ~~
R ~#; ~ ~
5~i
~~~~
~~
~~
a
~~
~;; ~~ ~~
~~~ ~_~~
~~~ ~~~~
~~ i~ r
~~€~
• = ~ a$~
~~
~~
~~ ~ ~
~~ ~
~_~
~t~ ~~ ~ ~
~~ g~~
~ ~ ~~
~~~
~~~
f
$I
~~
~~
~ _~_ .
g
~z
~r
~ c 4
I I ~,1~ '
C E~ ~ o o C~J c`~--" -1R ~,1
E~ ~ ~ o o a o -1rc ~f, ~f~~ ~f ~
~ ~ ~ ~~ ~ a~ ~€a 5~~ ~~ ~ ~~
~ ~~ ~ ~~g~e ' ~~~ t~~~ I 9
'~ ~r aka g~.a ~~ ~3 ~
~ f ~,_L ~3~;?~
s ,
~ I r,
~ ~ ~ ~t ~ ~ ~~`~~~ ~ ~~ ~~~~ ~~~ ~~~~
~ ~!~ ~~~~ # ~i
I o~. ~ ~~#
.,
.~_
~ ~ W.S. Town Center
i ~ s • ~ r BWId~4sS aW 4 &d~-Wrc RrD~elpn
Sprtp~, F7orid~
~ Plan and Details
a
w
~~
~~
~~
!~
°~~~ #~~ ~
a~~ ~iS~ltr\~ .~ ~~~ E
~{
~ g~
~a ~~
€S ~~
e
~~~~;
~~~~
~~
i
R ~~; ~ ~
4~i ~ i