HomeMy WebLinkAbout2007 09 24 Consent 202 DK Properties
COMMISSION AGENDA
September 24,2007
Meeting
Consent
Information
Public Hearin
Re ular
MGR. ~ lDept. ~
x
ITEM 202
REQUEST: The Public Works Department requests the City Commission validate the staff
recommendation finding the DK Properties site to be built in substantial
accordance with the Final Engineering plans and to accept the potable water
infrastructure for ownership and maintenance.
PURPOSE: The purpose of this Agenda Item is to request the City Commission validate the staff
recommendation finding the DK Properties site to be built in substantial accordance
with the Final Engineering plans and to accept the potable water infrastructure for
ownership and maintenance per Section 9-178 in order for Certificates of Occupancy
to be issued. The site is located on the north side ofS.R. 434, east ofSR 417,
between Barclay Reserve and Barrington Estates. The project consists of a new
10,000 SF office building and related site infrastructure and landscaping
improvements.
APPLICABLE CODE:
Section 9-178. Required Improvements to be completed prior to building on lots;
exceptions.
(c) Where the building official has an authoritative method of assurance that the
improvements will be completed in accordance with approved plans, such as withholding
occupancy, the building official may issue building permits upon advising the developer that
all or partial occupancy will be restricted until satisfactory completion of the improvements
has be accomplished.
(d) ... CertifIcates of occupancy will not be issued until all improvements are accepted by
the city commission.
092407_ COMM _ Consent_ 202 _ DK Properties Site Acceptance
September 24, 2007
Consent Agenda Item #202
Page 2
FINDINGS:
1) The site has been constructed in substantial accordance with the Final Engineering plans
approved by the City Commission at the November 27,2006 City Commission meeting,
except as noted below.
2) All City agencies have found the work to be acceptable.
3) The engineer-of-record has certified the sitework.
RECOMMENDED CONDITIONS OF APPROVAL:
The following items are necessary to complete prior to a Certificate of Occupancy:
1) Record drawings shall be revised to comply with City requirements
2) The letter of credit for the portion ofthe onsite water main being conveyed to the City
shall be re-issued to cover a two-year period instead of one-year as submitted
3) The berm at the stormwater pond shall be finish graded and sodded per the approved
plans.
RECOMMENDATION:
Staff recommends that the City Commission validate the staff recommendation
finding the DK Properties site to be built in substantial accordance with the Final
Engineering plans and to accept the potable water infrastructure for ownership and
maintenance, subject to the conditions of approval listed above.
IMPLEMENT A TION:
The Certificate of Occupancy can be issued after Commission approval and
satisfaction ofthe conditions of approval.
ATTACHMENTS: None
CITY COMMISSION ACTION:
092407_ COMM _ Consent_ 202 _ DK Properties Site Acceptance