REQUEST: Public Works Department is requesting City Commission authorization to
construct a 5-foot wide sidewalk on Northern Way at the Fairway Oaks
subdivision and to increase the project contingency of the Dyson Drive Sidewalk
Project by $25,000.
PURPOSE: The purpose of this agenda item is to request City Commission authorization to
construct a 5-foot wide sidewalk on Northern Way at the Fairway Oaks subdivision
and to increase the project contingency of the Dyson Drive Sidewalk Project by
$25,000.
CONSIDERATIONS:
. At the January 22,2007 City Commission meeting, the Commission approved a construction
contract with Southland Construction in the amount of$506,743.30 plus a 10% contingency
of$50,674 to construct 5-foot wide sidewalks on both sides of Dyson Drive, piggybacking
off of Seminole County's 2007 Public Works Construction Contract CC-1075-061.
. This agenda item proposes to increase the project contingency by $25,000 to a total of
$75,674 and authorize construct a 5-foot wide sidewalk on Northern Way along the Fairway
Oaks subdivision frontage (see Exhibit 1). The total length of the proposed Northern Way
sidewalk segment is approximately 1,200 LF, and it connects to existing sidewalks at both
ends.
. Preliminary pricing from Southland Construction indicates the proposed Northern Way
sidewalk segment will cost approximately $50,000. Final pricing is subject to City and
Seminole County approval per the terms of the lnterlocal Agreement with the County. The
additional $25,000 is requested to ensure that the additional sidewalk segment does not
consume the entire project contingency.
. The entire sidewalk segment is located in the Northern Way right-of-way. A block wall
separates the right-of-way from the Fairway Oaks lots along the entire sidewalk route. A
crosswalk will be provided where the sidewalk crosses the Fairway Oaks main entrance.
051407 _COMM_Consent_201_Northem Way Sidewalks at Fairway Oaks
Consent Agenda Item 201
May 14,2007
Page 2 of2
· Staff has contacted the Fairway Oaks Homeowner's Association to inform them about the
project and provide contact information ifthere are any questions or concerns.
· The proposed Northern Way sidewalk segment in front of Fairway Oaks is funded entirely
by Seminole County through the City's Interlocal Agreement with the County that provides
funding up to $1,000,000 for sidewalks at various locations in the City. The Interlocal
Agreement was approved by the City Commission at the July 24, 2006 Commission
meeting.
· This agenda item does not request approval for sidewalks on Shetland A venue or for the
Northern Way segment from Howell Creek to Shetland Avenue.
FUNDING:
Funding is being provided by Seminole County through the Interlocal Agreement
after their approval of the contract amendment. Per the Interlocal Agreement, Seminole
County will make funds available up front after approval with no cost to the City.
RECOMMENDATION:
Staff recommends the Commission authorize construction of a 5- foot wide sidewalk
on Northern Way at the Fairway Oaks subdivision and increase the project contingency of
the Dyson Drive Sidewalk Project by $25,000.
IMPLEMENTATION SCHEDULE:
After County approval, construction is expected to begin in about 30 days, or soon
after substantial completion of the Dyson Drive sidewalks.