HomeMy WebLinkAbout2006 08 02 Informational Item 500 Current Planning Projects
r
PLANNING & ZONING BOARD
AGENDA
...."
ITEM 500
Consent
Information X
Public Hearinl!:
Rel!:ular
August 2. 2006
Meeting
REQUEST: Community Development Department is advising the Planning & Zoning Board
of the status of various current planning projects.
PURPOSE: This agenda item is to update the Board on the status of current planning
projects.
CONSIDERATION:
PLEASE NOTE: For future reference, this information is updated for the Commission at each
meeting and is available on-line, under Commission Agenda Items, as Regular Item 500.
....,
(1) Don King Concrete - Revised final engineering plans for a new 10,000 SF office
building behind the existing office (a converted home) on the 2.5 acre site, along the north side of
SR 434, between Barrington and the Barkley Reserve, were submitted on February 27 and
reviewed at the March 21 staff review (re-submittal reviewed at May 16 staff review). The
remaining issues relate primarily to the small pond and its role in the storm-water management
for the site. per 06/12/06 agenda.
(2) Vista Willa - A concept plan for two (2)39,500 square foot office buildings (now 39,900
SF each) on 9.17 acres within the Tuscawilla PUD, located on the south side of SR 434, between
the Hess station and the Greeneway, was received June 8 and received a concept approval on
August 22, 2005. The plans for phase I and a development agreement were approved at the
January 23 City Commission meeting. A preconstruction meeting was held February 8. A
groundbreaking ceremony was held on March 8. The aesthetic review was approved at the April
24 Commission meeting. Phase II final engineering plans were reviewed at the May 2 staff
review; revised plans were submitted on May 18 for phase II and ill, to be reviewed at the June 6
staff review. The power company had not provided a lighting plan, so RSH, the project design
engineers, have submitted an overall site lighting plan. At its June 12 meeting, the City
Commission amended the DA to allow the building permit to be issued prior to submittal of the
...."
August 2, 2006
Information Item 500
Page 2
lighting plan (lights to be operational before CO). The Phase I building permit is ready to be -....IfI/I
issued. per 07/l 0/06 agenda
(3) Oviedo Marketplace - Notice was provided on April 1, 2005, of the Notice ofa
Proposed Change (NOPC # 5386) for the Oviedo Marketplace [Mall] development of regional
impact (DRI). The 431.2 acre DRI is located among 3 jurisdictions (218.6 acres in Oviedo, 163
acres in unincorporated Seminole County, and 49.6 acres in Winter Springs). The NOPC is
proposed to allow 180 town home units to replace 10,000 SF of retail in Parcel 13 (within
Oviedo, but adjacent to Winter Springs - Tuscawilla Units 7 & 13). The build-out date for the
entire DRI is being extended from 12/31/05 to 12/31/07. Pursuant to a May 9,2005, City
Commission directive to staff, notification was sent to the owners of 103 properties within the
City of Winter Springs. The NOPC for the Oviedo portion was approved by the Oviedo City
Commission on Monday, September 19,2005. The NOPC to change the Winter Spings portion
of the DRI from 160,000 square feet of commercial to 131,000 square feet of office/commercial
and 132 townhomes was heard at the February 1 P & Z meeting (2-2 vote) and was approved for
100 townhome units at the March 27 Commission meeting. per 04/24/06 agenda
(4) Colonial Bank - On September 13, staff received a preliminary engineering/site plan
package for a Colonial Bank at the comer out-parcel of what had been the Kash-N-Karry
shopping center. This was reviewed at the October 18 staff review. A re-submittal was received
on December 21 and was reviewed at the January 17, 2006, staff review. Final site/civil plans
were approved at the March 13 Commission meeting. The City Attorney is preparing a
development agreement to address the monument sign that must be relocated to accommodate """'"
the right-turn lane onto Vistawilla Drive from east-bound SR 434. A pre-construction meeting
was held on March 16. An aesthetic review package was approved at the April 24 Commission
meeting. Utilities have been installed, the slab has been poured, and vertical construction has
commenced. The contractor is waiting on the provision of storm and sanitary structures. On
June 12, the Commission approved a development agreement modification addressing signage.
per 06/26/06 agenda
(4A) Seminole Trail Animal H ospital- Dr. Williams, DVM, submitted a combined
preliminary and final engineering/site plan along with a lot split application on December 1,
2005. The site plan was reviewed at the December 20 staff review. The final engineering/site
plan and aesthetic review were approved at the April 24 City Commission meeting. A
preconstruction conference was held on April 25. The lot split was reviewed at the April 4 staff
review. The building plans have been reviewed and staff awaits revised plans. The proposed
lot split is scheduled for the July 24 Commission meeting. per 07/24/06
(5) ICI Homes - 480 condo units. 80,000 SF of office. A Large Scale Future Land Use change
was transmitted to DCA on October 25,2004. The adoption hearing amending the Future Land
Use map was held January 24,2005. Staff met with ICI representative on August 4,2005, to
discuss rezoning, height, and site plan issues. per 08/22/05 agenda
......,
August 2, 2006
Information Item 500
Page 3
(6) Tuscawilla Square - The final engineering/site plan was approved on February 28,2005.
The aesthetic review was approved at the May 9 City Commission meeting and a pre-
construction was held on May 18. At its June 13,2005, meeting, the City Commission approved
funding $174,454.00 for the Gary Hillery Drive reconstruction. No funding was approved for
entrance features. Permits have been issued for the temporary construction office trailer and for
the construction sign. Both of the buildings are in the rough stages of construction. Proposed
modifications were approved at the June 12 Commission meeting. Gary Hillary Drive is now
paved. Staff is working with the developer to resolve the issue of the large wall-oriented
electrical meter banks, visible from Winter Springs Boulevard and Gary Hillery Drive. per
06/26/06 agenda
(7) Winter Springs Town homes (AKA Sonoma Pointe or Sonesta Pointe) -
Preliminary plans for approximately 436 town-homes on 40 acres within the Town Center were
received from Engle Homes on July 2 and were reviewed at the July 20 DRC. The City
Commission approved a concept plan at its August 9, 2004, meeting and refined it at its
September 27 meeting. The City Attorney noted that the concept plan, as proposed, would
require a development agreement or special exception or both. The 40 acres has been acquired
without platting. The applicant has hired a new design team and met with staff on May 31 and
July 8 to summarize outstanding issues. On August 29, staff received an aesthetic review
package (it is now called Sonoma Pointe at Town Center). The aesthetic review was addressed at
the September 20 staff review. A meeting between the applicant's team and staff was held
October 19. The state required a letter from the City's Local Planning Agency, stating that
crossing the Cross-Seminole Trail with underground utility lines is consistent with the City's
Comprehensive Plan (approved at the December 6 LP A/P&Z meeting). The aesthetic review
was discussed at the December 20 staff review and again informally on January 27. The
incomplete combined preliminary and final engineering plan submittal was reviewed at the
February 7 staffreview. An aesthetic review package was reviewed at the April 24 and May 8
Commission meetings, but a decision was deferred. Concern was expressed regarding diversity
of units as well as the alley sides of the units. Staffis working with the applicant to address the
unit mix and various other aesthetic review items. A new aesthetic review package, featuring
a British Colonial theme, was submitted on July 3 for 408 units. 07/24/06 agenda
(8) JDC Calhoun 1. Construction continues. City records indicate the following businesses
are locating or have located in the IDC Calhoun Town Center:
Building 1 - Tijuana Flats, an insurance agency, Cristiano's, Barnie's, and Giancarlo's;
Building 2 - Marble Slab Creamery, James Doran office, Home Town Mortgage, Dr. Herba's
Chiropractic office, and The Party Store;
Building 8 - Leslie Pool Supply, a dentist, and a tanning salon, Edward Jones; Century 21
offices;
Building 9 - Red Bug Cleaners, E-Nails, Great Clips, Famous Uncle AI's Hotdogs, and
Subway;
....",
...."
....-I
August 2, 2006
Information Item 500
Page 4
Building 10 - Washington Mutual;
Building 11 - State Farm, H & R Block, Rachel Nicole's Salon, Shape Xpress, and a dentist;
Building 12 - Publix;
Building 13 - Winter Springs Liquors, Mailboxes, Etc;
Building 14 - China Feast and a sushi restaurant; and
Building 15 - Wendy's.
....,
On January 24,2005, the City Commission approved final engineering plans from Lochraine
Engineering for the northeast portion of the JDC site (that area north of Tree Swallow Drive and
east of Cliffrose Drive including buildings 3, 4, & 16). A pre-construction meeting was held on
March 15, 2005, for the 2 acre portion of the approximately 15 acre site. Revised final
engineering plans for this 2 acres were approved at the April 25 City Commission meeting. A
third iteration of the final engineering plan was approved at the September 26 Commission
meeting.
Building elevations for Building 3 (2 story & 15,620 SF) were approved at the May 9,2005, City
Commission meeting. Building plan issues regarding a fire riser room location and the location
of the 2 internal stairways were resolved at the October 10,2005, Commission meeting. Staff
has approved the building plans for building 3. Water line location has held up construction of
Building 3. A meeting on May 11, 2006, determined the water main relocation schedule;
relocation is completed and vertical construction of Building 3 resumed. On May 25, crews ...."
punctured an active water line, disrupting construction on Building 3.
Building 4 (combination 7,800 SF first floor retail and restaurant with second and third floor
residential condominiums with a fourth floor penthouse suite - 15 residential units) was approved
for aesthetic review on September 12, although the Commission voted to have the applicant
come back to show a combination of 2, 4, and 6 foot deep balconies. The applicant has been
advised to submit condominium documents concurrent with the building permit application.
Building elevations for Building 16 (11,095 SF) were approved with conditions at the June 13,
2005, City Commission meeting; revisions with a trellis at the west end and other minor
modifications were approved on September 12. Vertical construction continues. A major
restaurant is considering locating in the east end ofthe building (closest to Tuskawilla Road).
On July 10,2006, the Commission approved a minor modification to the west end of Building
16, to remove one door and move another door at the west end of the building (adjacent to the
circle).
The Commission approved a concept elevation of Building 17 (a 26 unit residential
condominium) at the September 12 meeting, noting that a number of site issues (e.g. parking,
access, and the space adjacent to the traffic circle) must be resolved with the site plan. An
aesthetic review package for a pergola (along with a dumpster enclosure for Building 16), located
on the Building 17 site, adjacent to the circle, has been submitted. The concept site plan and a
""""
August 2, 2006
Information Item 500
Page 5
development agreement were approved at the October 10, 2005, meeting. A third modification
ofthe applicable development agreement was received without a fee on March 2. Both the re-
plat and modification were addressed at the March 7 staff review. The re-plat was approved at
the April 10 Commission meeting and has been recorded. A revised Building 17 site plan was
reviewed at the April 18 staff review. At the May 25 meeting between City staff and the
development team, during a discussion regarding building permit submittal and review for
buildings 4 and 17, staff noted that the Building 17 site plan needs revision and City Commission
approval. per 06/26/06 agenda
(8 A) Town Center Phase II The Doran team met with staff on June 2, 2005, to outline their
plans for 331 apartment and condominium units, 43,000 square feet of retail, 354 structured
parking spaces (multi-level parking garage), and surface parking (on-street and parking lots) on
the east side of Tuskawilla Road. An updated projection by the development team on August 11
divided their proposed development east of Tuskawilla Road into Phase II A and IIB, with no
vertical construction east of the trail bridge, due to wetland issues. Phase II A plans were
submitted on February 7 for 33,452 square feet of retail and 292 residential units on 7.75 acres.
The plans were reviewed at the March 7 staff review. The build-out for phases II A and IIB
totals 400,000 square feet of retail, 300,000 square feet of office, and 700 residential units, with 2
and possibly 3 parking structures. A Phase II development agreement (DA) was approved by the
City Commission on October 17,2005, requiring the buildings in Phase II to be 6 stories high.
The DA has conflicting language on building height. Staff is working to resolve the conflict and
the DA will be amended to include language allowing building heights UP to 6 stories. The site
plan and aesthetic review package were reviewed at a special April 11 staff review. A site
development permit agreement to clear the Phase II A site was approved at the April 24
Commission meeting. A first round of aesthetic review comments has been submitted to the
applicant. The aesthetic review for Phase ITA was approved at the June 12 Commission meeting.
The Phase IIA final engineering was approved at the July 10 Commission meeting, subject
to conditions and the up-coming implementation agreement. per 07/24/06 agenda
" "
(9)Artesian Park (formerly Lincoln Park) - A concept plan for 106 (was 113) town homes on
the 8 acre site, located on the south side of Orange Avenue, between Jesup's Landing (185 units
on 17.15 acres) and Tuskawilla Trace, was approved, subject to conditions by the City
Commission on March 14,2005. The plan depicted roadway connections with Jesup's Landing,
use ofthe shared alley with Jesup's Landing, 2 boulevards with water features in the medians,
some town homes around a plaza, and some town homes with small back yards and detached
garages. On July 27, the applicant submitted a modified concept plan that included only one
boulevard with a median water feature. The revised concept plans were approved at the October
10,2005, meeting. Final engineering/subdivision plans were submitted on November 21 and
were reviewed at the December 6 staff review. Dover Kohl, staff, and the applicant's team have
been trying to best address the concept of live-work units, raised door-yards, and courtyards at
grade (since the applicant has determined that the Brownstone concept is financially impractical
for this site, due to the amount of fill material that would need to be imported). Revised final
engineering plans, a traffic analysis, a stormwater report, a geo-technical report, revised potable
....."
..,J
....."
August 2, 2006
Information Item 500
Page 6
water calculations, by-laws, articles of incorporation, and an ecological report were submitted on
March 20 and were addressed at the May 2 staff review. The applicant's team met with
engineering staff on June 9 to discuss the adjacent deep muck issue and other pertinent
construction issues. The final engineering plans were approved at the June 12 Commission
meeting, subject to staff conditions and a development agreement. per 06/26/06 agenda.
....."
(10) J esup's Landing (previouslyBarclay II and then Jessup Reserve) - 185 Units. At its
October 11, 2004, meeting, the City Commission approved a concept plan for as many as 207
town house units with rear-loaded 2 car garages and 128 on-street parking spaces on 17.15 acres
along the south side of Orange Avenue. A development agreement and revised concept plan for
185 units were approved at the February 28 City Commission meeting. On May 9 the City
Commission approved the Town Center Phase I Site Development Permit Agreement. The final
engineering/subdivision plans were approved at the June 27 City Commission meeting. The
aesthetic review was approved at the September 26, 2005, City Commission meeting. Revisions
to the final engineering plans (addressing specimen trees, bus shelter, & lift station) were
approved at the October 10,2005, meeting. The final plat for Jesup's Landing was approved at
the 11/14/05 City Commission meeting. On November 30, staffmet with both the Jesup's
Landing and Artesian Park development teams, to discuss the shared alley easement that both
subdivisions will use. The Jesup's Landing final plat revision was approved by the City
Commission at the January 9 meeting, to incorporate minor modifications, based on discussions
and negotiations between the two developers and the City, regarding an easement along the
project's eastern property line. Porch and stoop encroachments into common areas may require
another re-plat, as in Jesup's Reserve. Crews had de-mobilized from the project until a decision
is made regarding whether or not to surcharge or stabilize by some other method. This is due to
large quantities of deep muck. Levitt cancelled a June 6 staff review meeting discussion
regarding a proposed grade change and its effects upon the project, but met with staff on June 8
to address the deep muck issue and the proposed structural engineering solutions. At its July 10
meeting, the Commission reviewed information on the proposed use of "geo-foam" underneath
four buildings to address the muck situation. The Commission voted to defer the matter until
additional information could be obtained.
,..."",
On March 27,2006, the Commission voted to appropriate $821,382 for the design and
construction of Orange Avenue, from Tuskawilla Road to Central Winds Park (Jesup's Landing
and Artesian Park are both dependent upon reconstruction of Orange Avenue - a preconstruction
conference for Orange Avenue was held on May 3 and work has commenced; a construction
trailer has been located on the unimproved portion of the Tuskawilla Road ROW. Construction
presently consists of earthwork, utilities, and stormwater facilities. Paving is at least several
weeks away. At its July 10 meeting, the Commission denied a request to extend the Orange
Avenue reconstruction approximately 145 feet west of the approved western bounds of
construction. per 07/24/06 agenda
(11) Highlander Property (aka Jesup's Reserve and Barclay Town Center) -161
units. A concept plan was approved on August 23, 2004, for as many as 170 town home units on
11 acres of what was then an unincorporated county enclave, located between Tuskawilla Trails
..",;
August 2, 2006
Information Item 500
Page 7
and SR 434. An Annexation and Pre-development Agreement was approved at the September
20,2004, City Commission meeting. Reynolds, Smith and Hills (RSH) met with the staffDRC
on October 12 for a pre-application meeting. The property was annexed on October 25, 2004.
The Future Land Use designation has been changed to Town Center. A revised concept plan for
160 units was approved at the March 28 Commission meeting and must be added to the existing
agreement as a modification. Final engineering/subdivision plans were submitted on March 21.
As a result of discussion about the adjacent property to the west, the applicant has revised a plan
for that northwest comer of the site to remove the frontage road (the City Commission may
waive the frontage road requirement of Subsection 20-325 (c) (8)). An initial aesthetic review
with staff occurred at the 05/17/05 staff review. Revised final engineering/subdivision plans
were approved on August 8, 2004, in conjunction with a development agreement modification.
Site work had begun prior to final engineering approval, pursuant to the Site Development
Permit Agreement approved by the City Commission on May 9, 2005. The aesthetic review was
approved at the September 26,2005, City Commission meeting. The final plat for Jesup's
Reserve was approved at the 11/14/05 City Commission meeting. The plat and restrictive
covenants have been recorded. Crews have completed the potable, sanitary, and storm water
system to include the offsite system along Nature's Way and are constructing the stabilized road
base and curbing. Vertical construction to the upper floor level is under way on the building that
will temporarily serve as a model center. The temporary sales trailer has been moved into place
at the northeast comer of the site. Road paving was scheduled for the week of June 19. A
development agreement modification was approved at the April 10 Commission meeting. per
04/24/06 agenda.
...",
...",
(1J-A) West End Professional Center - A concept plan for the West End Center was
approved by the Commission on February 27,2006. The applicant proposes 2 nearly identical 3-
floor office bui.ldings (separate phases), totaling 48,780 SF, on 2.37 acres located within the
Town Center, on the south side ofSR 434, between Jesup's Reserve and the entrance to
Tuskawilla Trails. The aesthetic review package was submitted on March 14 and the site plan
was submitted on March 17. The aesthetic review was held at the April 4 staff review (site plan
on April 18). The aesthetic was approved by the City Commission on June 26. At the July 10
meeting, the Commission voted to reconsider the aesthetic review at the July 24 meeting. per
07/24/06 agenda
(12) Tuskawilla Office Park - Certificates of occupancy have been issued for buildings 4 -
8 and 11. The orientation of Building 1 (designed to front on Tuscawilla Road and built to front
onto the parking lot) has been an issue. Building 1 is being prepared for a final inspection. A
meeting has been scheduled between the builder and staff, to bring Building 1 into compliance
with the approved plans and rendering. A new contractor has been hired for Building 10 and a
new building permit was issued March 13, 2006. A final engineering/site plan and aesthetic
review for a 10,798 SF 2 story office building with 4 garaged parking spaces and 9 exterior on-
site parking spaces was approved at the April 24 Commission meeting. per 07/24/06 agenda
...",
August 2, 2006
Information Item 500
Page 8
(13) Villa Grande - On September 12, the City Commission approved a concept plan for 152
residential condominiums (estimated to be 1,260 - 1,800 square feet each) on 4.75 acres within
the Town Center, between City Hall and Doran Drive. The project is comprised of 5 residential
buildings, each with first floor parking and residences above. Two of the buildings have 3 floors
of residences above parking, two have 4 floors of residences above parking, and one has 5 floors
of residences above parking. A separate club-house is provided along Doran Drive, at the
terminal vista at the west end of Blumberg Boulevard. The applicant and staff have been
discussing allowing the site to drain into the City's storm-water pond in return for design and
reconstruction of a portion of Doran Drive to Town Center specifications. A final
engineering/site plan was submitted on October 17 and reviewed at the November I staff review;
a revision was submitted on December 16 and was reviewed at the January 17 staff review.
Additional discussions between staff and the developer have been on-going to finalize roadway
cross-sections, sidewalk widths, and proposed architectural changes. A preliminary
engineering/site plan was approved at the April 10 Commission meeting. A development
agreement and the final engineering plan are scheduled for the July 24 Commission meeting.
per 07/24/06 agenda
(14) Lake Jesup Shores - Preliminary engineering/subdivision plans for 68 (now 80 units)
townhomes on 8.7 acres within the Down Town, across SR 434 from Heritage Park, were
received on March 24 and were reviewed by staff on April 12, 2005. Revised preliminary
engineering plans were to be reviewed at a special May 19 staff review, was deferred at the
applicant's request. On June 16, the City Manager and staff met with the property owner, Tom
Daly, and the builder to discuss the outstanding issues. A meeting was then held in South Miami
among the applicant, the City Manager, and Dover Kohl and Partners on July 15. On August 29,
Dover Kohl and Partners notified staff that a subsequent iteration that had recently been provided
to them was a major improvement over the earlier designs, but still had certain front-back issues.
Ryland Homes is the prospective builder and the subdivision is planned by the Daly Design
Group. A preliminary engineering re-submittal for 80 units was received on October 3, 2005,
and was reviewed at the November I staffreview (subsequent iteration was provided to Dover
Kohl and Partners). A revised plan was approved at the April 10 Commission meeting. No
development agreement has been provided to address the inconsistencies between the plans and
the Town Center Code. Staff met with the applicant's team on April 25 to address architectural
embellishment requirements; staff met again with the applicant, an aesthetic review package was
provided and reviewed, and comments have been provided back to the applicant on June 9.
Staff met with Pete Leerdam (Euro-Capital Partners) and a Ryland Homes representative on June
22, discussing the provision and timing of the adjacent Central Winds Parkway and Old SR 434
reconstruction, as it relates to Lake Jesup Shores. per 07/10/06 agenda
(15) Landings at Parkstone - 104 Town Home units. A PUD master plan amendment,
preliminary subdivision plan, and final subdivision plan were approved by the City Commission
at its July 26,2004, meeting. On September I, a revised final engineering plan was submitted,
proposing to re-Iocate the entrance more southerly along Parkstone Boulevard and lower the
approved final grade. A revised Development Agreement (DA), PUD master plan amendment,
....."
....,
..J
August 2, 2006
Information Item 500
Page 9
modified final engineering plans, and aesthetic review were discussed at the December 13, 2004,
Commission meeting and were approved on January 10, 2005. A pre-construction meeting was
held on Monday, February 7 and Blue Ox Construction has been doing the site work. Water and
sewer lines are in place, the roadways are paved, and staff estimates that site work is
approximately 98 percent complete (as of October 13). A request by Morrison Homes to amend
the DA to allow construction of model units before platting was approved on May 23. A master
file (no building permits) for at least some of the units was released July 26 (to expedite
permitting). The final plat and HOA documents were approved on August 8, 2005, and have
been recorded. The DA was amended at the January 9 meeting, to accommodate the proposed
back porches that face the SR 434 ROW. The roadways are scheduled to receive another (final)
layer of asphalt when the buildings are largely completed, to provide the purchasers with
unblemished roadway surfaces. Engineering staff estimates the site work at about 98% complete.
per 06/26/06 agenda
..."",
(16) SR 434 Retail (a.k.a. ViI/agio) Construction of the unfinished out-building has
commenced. The Flower Shop, Bicycle Shop, Spring Liquor Store, Curves Ladies Fitness,
Spring Nails, Trustco bank and a cellular telephone company office are the current tenants. The
City Commission validated that the project is built in substantial accordance with the approved
final engineering plans and accepted the water and sanitary sewer infrastructure for ownership
and maintenance at the April 11, 2005, meeting. Construction continues on the second out-
building. The "rough-in" (e.g. plumbing, electrical, AlC retrofit, and grease trap) is being
installed for the 6,000 SF restaurant in the NW end of the main building. per 06/26/06 agenda
'WIllI
(17) Stonehridge Construction(a.k.a. KAI Reserve) - A request for conditional use to construct
muIti- family housing on 1.7 acre site in C-l zoning, located on south side of SR 434, just west of
intersection with SR 419, was postponed at the December 12 City Commission meeting. Staff
was directed to investigate the possibility that the unimproved Celery Avenue could connect to
Hayes Road, the traffic impacts of various types of development, the potential ramifications of
piecemeal development, and the fiscal impact on the City of converting commercially designated
property to multi-family residential. The conditional use was approved at the January 23 City
Commission meeting. The applicant's request to modify the existing conditional use was denied
at the April 24 Commission meeting. Preliminary plans were submitted May 16 and reviewed at
the staff review on June 6. per 06/26/06 agenda
(17-A) Talis Crossing Subdivision - On December 13,2005, staff received a subdivision
plan to create 4 lots from a vacant and treed 9.07 acre tract along Fisher Road (also abuts Tusca
Trail- a private roadways). The property abuts the southern edge ofDunmar Estates to the
north and unincorporated Seminole County, to the east. A 175 foot wide Florida Power
Corporation easement extends generally north and south through the property. The plan was
approved at the April 24 Commission meeting. per 05/08/06 agenda.
(18) Bledsoe Lot Split - On February 27, William Wheaton and Elsie Bledsoe requested a
lot split, to divide a 2.7 acre lot with an existing home at 180 E. Panama Road into 1.15 and 1.55 ...",I
August 2, 2006
Information Item 500
Page 10
acre lots. The request was discussed at the March 21 staffreview. Staff met again with the""'"
applicants' attorney on April 13 and May 17. The lot split was denied at the July 24 Commission
meeting. per 08/02/06 agenda
(19) Starlight Baptist Church - On November 1, Starlight Baptist Church submitted a
conditional use application to expand their existing facility on Hayes Road and a site plan for the
expansion. The site plan and conditional use applications were reviewed at the November 22
staff review. The Church was asked to provide additional information before being scheduled for
the Board of Adjustment. Revisions were submitted on March 16 and discussed at the April 4
staff review. Comprehensive plan issues (e.g. provision of sidewalks), stabilized grass parking,
bus parking, and overnight lodging of visiting ministers in campers, buses, or RVs are being
addressed with the City Attorney. A variance application and fee to allow grassed parking was
received on May 12. The conditional use and variance requests were heard at a special June 15
BOA meeting and approved at the July 10 City Commission meeting, subject to conditions.
per 07/24/06 agenda
(20) Medallion Convenience Store - Final engineering/site plans were submitted for a
convenience store and car wash at the SW comer of SR 434 and Hayes Road, on March 24,
2004. This site is adjacent to the intersection that was demonstrated to need an east-bound right-
hand auxiliary turn lane. The applicant's team has been advised of City Commission concerns
about a car wash at that location. Staff (including the City Attorney) met with applicant on
November 22, 2004, to discuss application status. On August 10, 2005, another potential ....",
applicant met with staffto discuss building a shopping center at this site. On February 22, a
concept plan for a 20,100 SF strip center on the 1.99 acre site was submitted and addressed at the
March 7 staff review. per 03/27/04 agenda
(21) Carnero Office Site - On October 15,2004, the final engineering plans to convert an
existing residence (approximately 1,400 SF) at the NW comer of Charles Street and SR 434 was
received by the City. Final engineering/site plan and the associated waiver requests were
approved at the March 28, 2005, City Commission meeting. An aesthetic review was approved
at the April 25 City Commission meeting. As of February 1, the parking lot permit had been
issued, but the wall permit and bathroom permit had not been issued. per 02/13/06 agenda
(22) Public Works Site Plan - Final engineering plans for the City Public Works complex
on Old Sanford-Oviedo Road were received on December 23,2004, and reviewed at the January
11,2005, DRC. A concept plan was provided to the City Commission as an informational item
at the January 10, 2005, City Commission meeting. A revised site plan was reviewed at the July
5 staff review. A subsequent meeting was held between Public Works staff, CPH, and the site
engineer. The site plan was approved at the September 26, 2005, City Commission meeting. At
its January 23 meeting, the City Commission authorized a contract with Ruby Builders for
construction of the site and certain buildings. Site work continues. Clearing and grading are
completed. Storm sewer installation is scheduled to begin May 15. The water line installation is
...."
August 2, 2006
Information Item 500
Page 11
estimated to be 40 % complete. Building permit applications for 4 buildings have been
reviewed. One building permit is ready to be issued. per 07/l 0/06 agenda
....."
(23) Miller School Supply - Final engineering/site plans were submitted January 27,2005
for a 10,028 square foot retail building on approximately 1.25 acres of wooded vacant land along
the south side ofSR 434, immediately west of the Cumberland Farms and the G-Man Restaurant
(formerly Papa Tony's). Final engineering/site plans were approved at the May 9 City
Commission meeting. An aesthetic review was approved at the June 27 City Commission
meeting. A development agreement to allow the proposed building mounted sign with a 6' tall
apple was approved at the July 11 City Commission meeting. A pre-construction meeting was
held on December 12. Water and sanitary connections have been completed. Vertical
construction continues. per 06/26/06 agenda
(24) Jordan Lot Split - On November 16, James and Jacqueline Jordan requested a lot split,
to divide a 3.12 acre lot with an existing home at 125 E. Panama Road into 1.07 and 2.05 acre
lots. The request was heard at the January 3 staff review. The Jordans have subsequently (July
12) met with staff to discuss moving forward with the lot split. per 07/24/06 agenda
(25) Venetian Village (formerly the Badcock Shopping Center) - The final site plan,
development agreement, and a general depiction of signage were approved at the June 28, 2004,
City Commission meeting. The site plan expired on June 28, 2005. On August 8, 2005, the City
Commission approved two 6-month extensions, extending the site plan. The development .....,
agreement was amended to extend approval to July 28,2006, for work to commence. A pre-
construction conference was held on July 11 and the applicant met with staff and the City
Manager for 2 hours on July 12. An extension was granted to the Applicant at the July 24, 2006
City Commission Meeting. per 08/02/06 agenda.
(26) Bonyadi Properties - Final engineering plans for a 7,101 SF,2 story, office building
on a Yz acre lot at the NE comer of Moss Road and Excelsior Parkway were submitted on May
21,2004, and were reviewed at the June 8, 2004, DRC. A resubmittal was received on or about
February 28 and was reviewed at the March 29, 2005, DRC. American Civil Engineering has
met again on February 21 with staff to discuss the potential provision of 5 small office buildings
along the north side of Excelsior Parkway. per 03/13/06 agenda
(27) Moss Road International Office Complex - Final engineering plans were
submitted on January 19 for the existing 2.5 acre former State Farm office site, at the SE comer
of SR 434 and Moss Road, and the adjacent 0.65 acre vacant wooded lot. The plan is to use the
existing State Farm building and share the large parking area with 2 additional office buildings
on what is now the adjacent vacant property. Final engineering plans and a development
agreement were approved at the May 9 City Commission meeting. A plat to reconfigure the 2
lots was approved on August 22, 2005. A pre-construction conference was held on June 2 and
clearing began on June 29. The utility crew has returned to the site. The sanitary sewer has
been completed from the "tie in" to the City system to the last "man-hole." A building permit ....",
August 2, 2006
Information Item 500
Page 12
was issued for the Omei Kung Fu Academy on September 15,2005. An aesthetic review of the ~
signage was approved at the February 13 Commission meeting. The City Commission resolved
the inconsistencies between the development agreement and the aesthetic review at the March 13
City Commission meeting. A second modification to the development agreement was approved
at the April 24 Commission meeting. per 05/08/06 agenda
(28) Saratoga Condominiums (aka Moss Road Town homes) - 84 units. At its April 12,
2004, meeting, the City Commission approved the Metropolis Homes conditional use application
and concept plan to build as many as 84 condominiums and commercial development on an "L"
shaped 9.10 acre site fronting on both SR 434 and Moss Road, adjacent to the Bank of America
and Victorio's Pizza. On September 20, the City Commission approved a 6 month extension for
the conditional use. Ordinance No. 2004-49 extended the initial approval of a conditional use
from 6 months to 2 years. Preliminary site plans and a draft development agreement were
submitted to the City on April15 and reviewed at the May 3 staff review. On July 21, the BOA
recommended approval for a waiver of the 2 car garage requirement for condominiums at this
site (proposing 1 covered space per unit). The waiver request was heard on August 22 and was
approved at the October 10 Commission meeting. On August 26, the applicant submitted final
engineering plans which were reviewed on September 20. Revised plans were submitted
November 2 and were reviewed at the November 22 staff review. Final engineering plans and a
6 month extension of the conditional use were both approved at the April 24 Commission
meeting. per 05/08/06 agenda
..""
(30) Belle Avenue Warehouse - Plans for a 4 building (3 new buildings totaling 9,000 SF
and one existing 2,728 SF building) warehouse complex on 1.174 acres were approved on
August 8, 2005. The applicant met with staff on August 10 to discuss setting up a pre-
construction conference and subsequently decided to reconnect power to the residential units and
at least temporarily delay demolition and construction. per 08/22/05 agenda
(31) Highlands Apts., Phase II(a.k.a. Golf Point Apartments) - The 42 unit
apartment (3 floor) final site plan was approved on March 8, 2004. There were delays, due to
conflict with the existing storm-water system at Seville on the Green. The FDEP water system
clearance lapsed, due to the contractor-related delay and still holds up the site. On November 7,
staff estimated the site work (not including the building) to be about 98 percent complete. On
September 16, the contractor and staff met to discuss the building and a proposed lighting plan
modification. Planning staff signed off on the revised lighting plan. The FDEP has recertified
the potable water supply system. The required certifications and documentations are being
gathered to close out the site. The Building Division reports that the applicant is completing the
drywall and rated assemblies and has requested pre-power, in order to perform necessary
equipment tests (as part of preparing for a final inspection). per 06/26/06 agenda
(32) Harbor Winds (a.k.a. Big Cypress) - 62 Units. The conditional use for town-homes
on the 15 acres east of the Golf Terrace Apartments approved at the August 9, 2004, City
Commission meeting for a maximum of94 unit (6.27 d.u.lacre). Ordinance No. 2004-49 ...."
August 2, 2006
Information Item 500
Page 13
extended the approval of a conditional use from 6 months to 2 years. Final engineering plans ...."
were submitted January 25,2005, for 90 units; revisions were submitted March 3 and were
reviewed at the March 15 DRC (a subsequent re-submittal was received on April 7 and had staff
review on April 19). Revised plans were submitted for 62 units were approved on August 22,
2005. A pre-construction conference was held on August 31. The plat and restrictive covenants
were approved, subject to conditions at the April 10 Commission meeting. A performance bond
was received on April 17. A modification to add a 10' easement across the front of each lot was
approved at the May 8 Commission meeting and the plat and HOA documents were recorded on
May 9. The sanitary, storm, and potable water systems have been installed. The roadway base
has been installed. Engineering staff estimated the site work to be approximately 89% complete.
A permit was issued for a sales trailer at the east end of the site and 9 building permits have been
issued (another 35 permits are being processed). per 06/26/06 agenda.
(33) Ditmer Large Scale Comprehensive Plan Amendment - The Keewan Real
Property Company has filed a large scale comprehensive plan amendment for 4 parcels totaling
approximately 47.27 acres, located south of Shepard Road and east of US 17-92, to change the
Future Land Use designation from Industrial to Medium Density Residential (3.6 - 9.0 d.u.lacre).
The properties have C-2 and PUD zoning (no development agreement). The City Commission
voted to transmit the amendment to DCA at the February 13 meeting. The proposed amendment
(Winter Springs 06-1) was transmitted to the Florida Department of Community Affairs (DCA)
on February 17 (received on February 20). The DCA's ORC report was received on April 24.
The City Commission adopted the amendment at its June 12 meeting. The applicant proposes to ....",
construct 334 townhomes on the site (tentatively named Winter Place). Two associated FLU
amendments (3 parcels) were adopted (with the effective date to be concurrent with Ordinance
2005-29) by the City Commission on July 24, 2006. per 08/02/06 agenda
(34) Nursery Road (Phil Reece) - The final engineering/site plan was approved at the
March 8, 2004, City Commission meeting and a preconstruction meeting was held on March 30.
The City Commission approved the aesthetic review of the first new building at its July 12, 2004,
meeting. The City Commission validated staffs recommendation that the site was built in
substantial accord with the approved final plans and accepted the potable water and sanitary
sewer at its June 27, 2005, meeting. Staff met with Mr. Reece on November 7 to begin to
determine a signage plan for the site. The aesthetic review of building # 5 was approved at the
November 28 City Commission meeting and the building is under construction and nearing a
Certificate of Occupancy. At its July 10, 2006, meeting, the Commission validated the findings
that the Phase lIB-I improvements are constructed in substantial accord with the final
engineering plans. The applicant is preparing to replace the building where Hub Cap Daddy is
presently located and update signage. per 07/24/06 agenda
(35) Penev Auto Shop - A preliminary engineering/site plan was submitted on August 19,
2005, for a 2,100 square foot shop on a 0.29 acre undeveloped and treed site, located on the south
side ofSR 434, approximately 800 feet east of US 17-92. The site has C-2 zoning, a
Commercial FLU designation, and is located within the SR 434 Redevelopment Overlay Zoning
....",
August 2, 2006
Information Item 500
Page 14
District. City of Winter Springs potable water and sanitary sewer do not appear to be located ,..""
within close proximity of the site. The site plan was reviewed at the September 6 staff review. A
re-submittal without the applicant's responses to staff comments was received on October 3,
2005, and reviewed at the October 18 staff review. A resubmittal was received on January 21
for staff review. per 02/13/06 agenda
TOWN CENTER
. PROJECT . DEVELOPER . TYPE . #OF . ACRES
UNITS
. J esup' s Landing . Levitt & Sons . Townhomes . 185 . 17.2
. J esup Reserve . Levitt & Sons . Townhomes . 161 . 11
. Sonesta Pointe . Engle Homes . Townhomes . 408 . 40
. Lake J esup . Ryland Homes . Townhomes . 80 . 8.7
Shores
. Artesian Park . VHB . Townhomes . 103 . 8.0
. Villa Grande . LeCesse . Condominiums . 152 . 4.75
. Doran (Bldgs. 4 . IDC (Doran) . Condominiums . 41 . 0.81
& 17)
. Doran Phase II - A . JDC (Doran) . Condominiums . 312 . 7.75
. Total . . . 1,442 . 98.21
REMAINDER ....."
. PROJECT . DEVELOPER . TYPE . #OF . ACRES
UNITS
. Barclay Reserve . Ashton Woods . Townhomes . 88 . 7.4
. To Be Named . ICI . Condo . 480+/- . 40
. Heritage Park . Centex . Townhomes . 158 . 14.5 *
. Harbor Winds . Morrison Homes . Townhomes . 62 . 15
. Landings at . Morrison Homes . Townhomes . 104 . 12
Parkstone
. Saratoga Condos . Metropolis . Condos . 84 . 9.1
. KAI Reserve . KAI Properties . Townhomes . 15 . 1.7
. Winter Place . Keewin . Townhomes . 334 . 47.3
Properties
. Total . . . 1,325 . 147.00
* Future Land Use Amendment only. No site or subdivision plan submitted for either the ICI or
Keewin projects. Although as many as 100 residential units could be constructed at the Winter
Springs portion of the Oviedo Marketplace, no concept plan, site plan, or subdivision plan has
been provided.
.....",
CI)
(!)
2:
g:
CI)
~~
~~
~
"3~
u..
o
~
(3
..."
...",
"
~
s ~
.. ..
.j< -g
ct :J en II) ~
",.gi~~
3:~.!:e~
~ C) a:l en a:
III 0 II
z.oo
~
~
....."
c
~~
co..
'i: l-
e.. S .2P~
VltlllUO
I-IU-UO
S ~ 0.. N
C I- :J I-
>Stll~
:> c ::J 0
4-Qj.6Jt)
OU,JgO
~CVl
,- ~
U 0
I-
! ~
1
!
~
f
i
"'0 j
c: .
QI !
000
~
I
I
j
..
.
p
}
P
<if
it
~i
I~
~t
d
11
~l
~
~+~
~
~
~