HomeMy WebLinkAbout2007 07 10 Regular 600 Inwood Office Building Final Engineering/Site Plan
P & Z AGENDA
ITEM 600
Regular X
July 10, 2007
Meeting
MGR.
IDEPT
Authorization
REQUEST:
The Community Development Department - Planning Division requests the P&Z Board review the
final engineering/site plan for the 30,000 S.F 2-story Inwood office building on 3.86 acres within the
Oviedo Marketplace DR! parcel 14. This is Phase I of a 2-phase 45,000 S.F. building.
PURPOSE: To review the proposed final engineering plan, for phase I of a 2-phase
development, for consistency with the Comprehensive Plan, the City Code, and the approved
development of regional impact (DR!) and then make a recommendation to the City Commission.
APPLICABLE LAW AND PUBLIC POLICY:
Chapter 5. Tree Protection and Preservation
Chapter 9. Land Development
Chapter 20. Zoning
Approved DR! Development Order
PUD Master Plan
CHRONOLOGY:
November 15. 2006 - Inwood Group submitted concept plan.
December 12. 2006 - Staff review 0 f concept plans.
January 22. 2007 - Notice of Proposed Change (NOPC # 5386) & lot split approved .
February 14.2007- Aesthetic review package submitted.
March 13. 2007 - Aesthetic and preliminary engineering at staff review.
May 2. 2007 - Revised aesthetic package submitted.
May 15. 2007 - Aesthetic review with staff.
Mav 18. 2007 - Revised aesthetic package submitted.
May 29, 2007 - Commission approved aesthetic review
CONSIDERATIONS:
Inwood is a consulting engineering firm specializing primarily in utility and transportation
infrastructure. The 30,000 SF 2-story moderriist style office building on 3.86-acre site within Oviedo
Marketplace parcel14A is being considered, here, for site plan review. A second phase is depicted
July 10, 2007
ITEM 600
Page 2 of3
on the site plan, with an additional 15,000 SF of office and additional parking. The second phase is
not being considered for site plan review, since it is not anticipated to occur in the near future (it will
require a separate site plan).
The site plan also includes at least a portion ofthe entrance road into parcel 14. The final proposal
for the rest ofthe developable portion of parcel 14 is unknown, although there have been inquiries
into providing as many as 100 dwelling units (15.1 acres - 3.86 = 11.24 remaining developable acres).
The first phase is designed with 117 regular parking spaces and 6 handicap accessible spaces (a
parking ratio of 1 space to 244 SF building, or 4.1 spaces per 1,000 SF). Phase II, when it occurs,
will incorporate an additional 106 regular spaces and one additional HC space (230 total parking
spaces: 45,000 SF/230 spaces = 1 space per 196 SF building, or 5.1 spaces per 1,000 SF).
Subsection 9-277 (24) requires a minimum of 1 space per 400 SF of office. The number of parking
spaces provided exceeds the minimum required by City Code, both in Phase I and at the completion
of Phase II.
The applicable building setbacks are 25' front, 15' rear, and 15' side. The maximum allowable
building height, at the proposed distance from Tuscawilla, is 65 feet.
Stormwater management has been master planned for the DR!. The site drains to one of the existing
wet detention ponds located behind the proposed building. This pond has been designed to
accommodate the proposed site development.
A traffic study was prepared demonstrating that the project complies with the previously approved
Oviedo Marketplace DR! master traffic study. All transportation mitigation requirements for the
approval of parcel 14 are in place or programmed for construction. At buildout, the 45,000 SF office
building is estimated to generate 721 average daily trips, including 99 AM peak hour trips and 129
PM peak hour trips. The traffic study demonstrated that the surrounding roads have sufficient
capacity to accommodate the project's traffic.
The project includes two connections to Dovera Drive. The first is the primary site entrance road
connection, which runs along the south boundary ofthe site and will be extended to serve the
remainder of parcel 14 when it is developed. This site entrance road will require minor modifications
to the existing median opening in Dovera Drive. The second Dovera Drive connection is a right-in /
right-out driveway connection exclusively serving the Inwood office building.
Parcel 14 is in the City's water and sewer service area and all properties developed on parcel 14 will
be City water and sewer customers. Seminole County currently provides water and sewer service to
the majority ofthe Oviedo Marketplace, and the closest points of connection to parcel 14 for both
water and sewer are to existing Seminole County water and sewer mains in Dovera Drive. The City
and County are currently in the process of finalizing a utility service agreement that will maintain
parcel 14 as City utility customers but allow the project to connect to the existing adjacent Seminole
County water and sewer mains.
Glatting-Jackson, a land planning consultant working for the developer, provided a map that depicts a
July 10, 2007
ITEM 600
Page 3 on
small on-site wetland. The City Attorney opined that the DR! approvals, which included both upland
and wetland mitigation areas on the entire DR! site, "grandfathered" the wetland lines, and areas
approved for development. This 3.86 acre site is within the 15.1 acres of parcel 14 that were
approved in the DR! for development (before the property was annexed into the City).
The Oviedo Marketplace Mall incorporates new modernist design. The proposed architecture is
consistent with the new modernist theme, incorporating concrete tilt up walls and large glass panels.
Its embellishments include primarily the metal spire, aluminum panel crown, and spandrel glass above
the entrance. The design draws the viewers focus to the entrance area. These issues were addressed
with the City Commission during the aesthetic review.
Site lighting is proposed by downward directed show box lights. A lighting plan depicting the
location, height, pole type, base, and photometries must be provided with the final engineering.
Site lighting should be coordinated with the landscape plan to avoid long-term conflicts between
trees, pipes, and light poles.
FINDINGS:
. The proposed project is consistent established DR! and PUD master plan for the Oviedo
Marketplace.
. Except for the wetland issues, which are grandfathered, and provision of a site lighting plan (no
off-site spillage beyond 0.5 foot candles), the site plan is consistent with the Comprehensive Plan.
STAFF RECOMMENDATION:
Staff recommends approval, subject to the applicant providing an acceptable lighting plan.
A TT ACHMENTS:
Final Engineering plans
P & ZACTION:
INWOOD OFFICE BUILDING
PRELIMINARY FINAL CONSTRUCTION
CITY OF WINTER SPRINGS
SEMINOLE COUNTY FLORIDA
COVER
INWOOD
C001 SURVEY
INWOOD OFFICE BUILDING
C100 SITE PLAN
INWOOD OFFICE BUILDING
C101 ACCESS ROAD
INWOOD OFFICE BUILDING
C200 DEMOLITION AND EROSION CONTROL PLAN
INWOOD OFFICE BUILDING
C300 PAVING GRADING AND DRAINAGE PLAN
INWOOD OFFICE BUILDING
C400 UTILITY PLAN
INWOOD OFFICE BUILDING
C500 GEOMETRY AND STRIPING PLAN
INWOOD OFFICE BUILDING
C600 SITE DETAILS
INWOOD OFFICE BUILDING
C700 PAVING GRADING DETAILS
INWOOD OFFICE BUILDING
C800 UTILITY DETAILS
INWOOD OFFICE BUILDING
C801 UTILITY DETAILS
INWOOD OFFICE BUILDING
I100 IRRIGATION PLAN
INWOOD OFFICE BUILDING
I200 IRRIGATION DETAILS
INWOOD OFFICE BUILDING
L 100 LANDSCAPE PLAN
INWOOD OFFICE BUILDING
L200 LANDSCAPE DETAILS