HomeMy WebLinkAbout2008 11 10 Consent 200 Bid for North Orlando First Addition Water Main ReplacementCOMMISSION AGENDA
ITEM 200
CONSENT
X
November 10, 2008
Meeting
INFORMATIONAL
PUBLIC HEARING
REGULAR
MGR ~~~ /DEPT ~/
Authorization
REQUEST: Utility/Public Works Department Requesting Approval to correct the
funding line code for Bid #ITB-011/08/GB -North Orlando First Addition
Water Main Replacement.
PURPOSE: The purpose of this Board item is to correct the line code for funding the North
Orlando First Addition Water Main Replacement that was approved in consent
Agenda Item 207 on October 13, 2008.
CONSIDERATIONS:
This agenda item is needed to correct the line project for funding the North
Orlando First Addition Water Main Replacement that was approved in Consent Agenda
Item 207 on October 13, 2008. Line code #311-65000-30037 was listed in the
recommendation as the funding source but it should have been #3600-65000-30129.
RECOMMENDATION:
It is recommended that the funding and supplemental appropriation line code for
Consent 207 on October 13, 2008 be approved as follows: "It is recommended that
authorization be given to enter into a contractual agreement with Parthenon Construction,
Inc. of Orlando in the amount of $497,655.00 plus 10% contingency ($49,765.50) payable
from line code 3600-65000-30129 with a $50,000 supplemental
appropriation from Utility Enterprise Fund balance."
ATTACHMENTS:
None
COMMISSION ACTION: