HomeMy WebLinkAbout2008 10 13 Consent 207 Bid#ITB-011/08/GB North Orlando First Addition
COMMISSION AGENDA
ITEM 207
CONSENT X
INFORMATIONAL
PUBLIC HEARING
REGULAR
October 13, 2008
Meeting
MGR 1/ /DEPT
r
Authorization
//r
REQUEST: Utility/Public Works Department Requesting Approval to award bid #ITB-
Oll/08/GB and enter into a contract to replace and relocate the water mains
in North Orlando First Addition.
PURPOSE: The purpose of this Board item is to request authorization to enter into a
contractual agreement with Parthenon Construction, Inc. of Orlando in the amount
of $497,655.00 plus 10% contingency to construct new water mains, hydrants and
water services in North Orlando First Addition.
CONSIDERA nONS:
This project is needed to replace and upgrade the water distribution system to
provide improved access for maintenance, unrestricted access to meters, and enhanced
fire protection to North Orlando First Addition. This area is generally bounded by
Bombay Avenue on the west, Flamingo Avenue on the east, 3rd Street on the north and
SR 434 on the south.
'\
1\
0'
, ~ I
_ '~--ili \
~-:.\
W STATE RO.:U
/~'f ,,/f,Xt
,:~1 "~~,;!;' , "
~,j::;" "1"Jool'J(J_8"-<!''''')'~J
... ~~~~~;'X~;~"~3~~:l:""
. ',...".~ ,,,,,n"" - A A . /JOIHi 150!1' 1M I '"" 1J1V
i/~(';'~_/:'~ ;i,I~~2Vf'f~~c"" IJO;ff/JJ I-IUIi1~4;1I! J~60 "J - M/I 1:1'1 Fa.'
-':' t?..p/ "'It "... --"- "O~!'I' no ({, 1.1 '''' '1>1'
m \' ,.j;; 1,_,~:;,;~ ~~~i"" /~;,,/ II: / J~V t'C:31 ,;:~,I/I 13:'" ,::1
-,I, l/~""i1~;J. IIJ /'.'01- I2lj~1)I ,::~ Hi
~. '" ," ~:;;"'" ~~ ':~-- Jm Jut ' Ii" t! 111 III! 'l'" 171 I?O "I'" IJJ
'~" if/ _ "" . t", ~ u .
'" '. I 01- ~ 1"' "~I i fI"~1I1 Ic"~
,J/J '~I 00. 81~ lot O?-. /OJ_I,oo:" 11"1"
,,',,1 ) Ii ,", ~" 0I~1r1'~ ~ 1ST l
I w 01 :' ,,^/ .\iJ t:; i t-' ~ -----' ---~_i
~ M ~~; I~ ~; 'I :,: I~: 40! 41 ;I' 31, g I ,Ii .
'Ii 40 _. _ " JO:z 31 -"'-~" XI;l\. 'I : ~q'~\.> lORIMlMEUl'-
""f,"\ct 31 ~I IJ?o" 0." ~~ ~ ." ,II d' , n
,,\ JU ~:'1''11 ~ - ~ II III~ II I'
~ ~_- H In II! ~,J{~. III l-:~~- - 0 ~.- "- ,.
(j i. 5 - ;;. ,.-"~ ~ ~ ~ . "
. ~ 3 ~ '" Jm 3)<) -0-< ;;~~:a.tERO~P~~
_,,,!,,,,,,,, (jell [j_,,,'J,,-J.lJ
." \ i'" '"'
~'''' 'W
j ~
.",......1
..
"
l.
"'-
! ,~
''':
~ /'"
':'~C~(8 I,IV _
.,' _'()~'~1~~-~'!1I'
jS~'~,~ J3-'
-? f ~'UO&iLN
,
;1,
_,rli. \
~s:,.-"'TERO~43~
'." \
'IJI :0,
.~\"
"" ~ t, '~'2-~i k ~,;: .C,~, c_,
Consent Agenda Item 207
October 13,2008
Page 2 of4
The water distribution systems for the North Orlando and North Orlando First
Addition subdivisions were constructed in 1961. Most ofthe lines are located in
easements in the rear of the properties making repairs and meter reading difficult. In
addition, the water mains are 4" and 6" which is below the current standard of 6" and 8".
All new lines will be located in the public right of way. The scope of work includes the
contractor reconnecting the new service line to the house.
There 14 bids submitted for #ITB-Oll/08GB which were opened on August 14th.
The apparent low bidder was Parthenon Construction, Inc. of Orlando with a bid of
$497,655.00. The bid summary prepared by the Purchasing Coordinator is attached.
CPH Engineers reviewed the bids and reviewed information that was requested
relative to similar experience, current work load, resumes of key personnel, list of
subcontractors, and references. All information checked out and CPH had no objection to
Parthenon Construction. Their review letter is attached.
FUNDING:
This project was budgeted at $500,000 in FY 08/09 Utility Enterprise Fund. In
order to have a contingency, a supplemental appropriation of $50,000 is requested to
project line code #3600-62100-30129.
RECOMMENDATION:
It is recommended that authorization be given to enter into a contractual
agreement with Parthenon Construction, Inc. of Orlando in the amount of $497,655.00
plus 10% contingency ($49,765.50) payable from line code 311-65000-30037 with a
$50,000 supplemental appropriation from Utility Enterprise Fund balance.
IMPLEMENT A TION SCHEDULE:
The scope of work will be completed within approximately 180 days of issuance
of the Notice to Proceed.
ATTACHMENTS:
1. Bid # ITB 013/08/KL
2. CPH Review Letter
COMMISSION ACTION:
Consent Agenda Item 207
October 13,2008
Page 3 of 4
Attachment No.1
CITY OF WINTER SPRINGS, FL
1126 EAST STATE ROAD 434
WINTER SPRINGS, FL 32708
407-327-1800
ITB/Oll/08KL
North Orlando First Addition Water Main Replacement
Called By:
Nancy Vobornik-Purchasing Coordinator
ITB Opened:
ITB Closed:
3:00 PM
3:14 PM
Date:
August 14, 2008
Witness:
Terry Zaudtke- CPH Engineers
Kip Lockcuff- Public Works/Utility Director
Edan Site Development
115 W. Pine Avenue
Longwood, FL 32750
Phone: 407-265-1113
Base Bid: $ 599,904.00
Central Florida Environmental Corp.
910 Belle Avenue
Suite 1040
Winter Springs, FL 32708
Phone: 407-834-6115
Base Bid: $ 562,549.00
American Persian Engineers & Constructors, Inc.
4436 Old Winter Garden Road
Orlando, FL 32811
Phone: 407-522-0530
Base Bid: $ 684,947.07
Dimensional Contracting Inc
PO Box 10
Howey In The Hills, FL 34737
Phone: 352-324-3224
Base Bid: $808,409.26
CenState Contractors, Inc.
PO Drawer 552
Winter Haven, FL 33882-0552
Phone: 863-324-3882
Fax: 863-324-3648
donna(ll)censtatc.colII
Base Bid: $ 860,993.00
Wal-Rose, Inc.
PO Box 728
Sanford, FL 32772
407-328-9999
Base Bid: $ 661,312.00
Consent Agenda Item 207
October 13,2008
Page 4 of 4
Slaughter Construction Company, Inc.
5394 Hoffner Ave
Suite B
Orlando, FL 32812
Base Bid: 636,569.00
Cathcart Contracting Company
1056 Willa Springs Drive
Winter Springs, F132708
Base Bid: $ 597,435.50
ADJ Excavating of Florida Inc.
1540 Cornerstone Blvd
Suite 200
Daytona Beach, FL 32117
Phone: 386-255-0250
Fax: 386-255-0210
Base Bid: $714,512.00
Blue Ox Enterprises, LLC
235 N Longwood
PO Box 520986
Longwood, FL 32752
407-339-4800
Base Bid: $622,176.13
C & C Site Development Inc
680 N SR 415
Osteen, FL 32764
Phone: 407-688-2657
Base Bid: $ 835,044.00
Parthenon Construction Company
105 W Seventh Street
Orlando, FL 32824
Base Bid: $ 497,655.00
Maxwell Contracting, Inc
PO Box 820
Cocoa, FL 32923-0820
Phone: 321-632-8810
Fax: 321-632-8065
Base Bid: $ 591,000.00
Gulf Coast Utility Constructors, Inc
1363 nnd Street N
St Petersburg, FL 33713
Phone: 727-328-7882
Base Bid: $ 773,483.00
1117 East Robinson Street
Orlando, Horida 32801
September 15, 2008
Phone: 407.425.0452
I'ax: 407.648.1036
Kipton Lockcuff, P E
Public Works Director
City of Winter Springs
1126 East State Road 434
Winter Springs, FL 32708
'lVww.cpltengiueers.com
Subject:
North Orlando First Addition Water Main Replacement
CPH Project No. W04138
Dear Kip
We have reviewed the bid and the qualifications submittal for Parthenon Construction
Company as apparent low bidder on the subject project. As part of our review, we
prepared a bid tabulation which we have previously provided to your office. Upon our
review, we found no mathematical errors in the bid tabulation. There are no MIWBE
I'equirements for this project. Parthenon possesses a General Contractor's license. We
requested and were supplied a list of I'eferences for similar projects. We do have some
reservations on their qualifications.
Only three of the fourteen projects submitted contain underground water and sewer
utility work. The majority of the projects were "surficial" site work - driveways,
sidewalks, roadways, fencing, although some contained underground drainage systems.
On the three projects containing potable water lines, all the underground work was
subcontracted. On one of these projects, they subcontracted 95% of the work. The
Contract Documents do not contain a limitation on the percentage of subcontract work
allowed. On the other hand, however, the references were positive. Powertel, the
subcontractor on the abovementioned 95% subcontracted project (with positive
feedback from the City of Altamonte Springs) is one of the potential subcontractors listed
for this project. The contractor was cooperative and worked well with the community.
The projects were on schedule, with only owner or site-driven change orders.
In summary, Parthenon Construction meets all the requirements of the Contract
Documents and the references were all positive. CPH Engineers recommends award of
this project to Parthenon Construction Company in the amount of $497,655.00.
If you have any comments regarding the above and/or would like to meet to discuss
them, please contact Mr. Terry Zaudtke or myself. Thank you.
Sincerely,
CPH ENGINEERS, INC.
William C. Goucher, P E
Project Manager