HomeMy WebLinkAbout1991 05 13 Regular
90-91-16
REGULAR MEETING
CITY COMMISSION
CITY OF WINTER SPRINGS
MAY 13, 1991
The Regular Meeting of the City Commission of the City of Winter Springs, Florida,
was called to order by Mayor Philip A. Kulbes at 7:30 p.m.
Roll Call:
Mayor Philip A. Kulbes, present
Deputy Mayor Paul P. Partyka, present
City Manager Richard Rozansky, present
City Attorney Frank Kruppenbacher, present
Commissioners:
Cindy Kaehler, present
Don Jonas, present
John Langellotti, present
Terri Donnelly, present
For the invocation Commissioner Langellotti asked for a moment of silent prayer.
The pledge of allegiance to the flag was led by City Manager Richard Rozansky.
There were no additions or corrections to the minutes of April 22nd and April 29th.
The Minutes stand approved as presented.
Mayor Kulbes presented Tim Lallathin, Assistant Fire Chief, a service award for 15
years of service to the City of Winter Springs.
Public Comment:
John Ferring, Oak Forest, spoke about the City's Pension Plan.
Park Presentation-Mr. David Barth:
Mr. Barth of Glatting Lopez Karcher Anglin and Jim Van Ostran of Webb & Associates,
Civil Engineers, were present and spoke to the Commission about the Central Winds Park.
Mr. Barth said we are here to tell you that we are ready to go to bid for the first
phase of construction for Central Winds Park. Mr. Barth prepared a project update
that has three parts, an update of the documents themselves, an update of the budget
and an update of the schedule.
Mr. Barth explained the contract documents are between the City, Contractor and Glatting
Lopez which have been reviewed by Staff, and pending any additional comments by the
City Attorney, that part is complete. The second part of the Bidding Documents
is the set of Construction Plans. He explained the Commission has already seen the
Design Development set, and this is a refinement of those, and they have been
reviewed by Staff.
The third component are the technical specifications, Volumes 1 and 2, Volume 1 is
the Site Improvements and Volume 2 is the Architectural Improvements. These also have
been reviewed by Staff. Mr. Barth said the only issue regarding completion of the
documents under Item lis that we are still in the midst of discussion with Florida
Dept. of Transportation regarding improvements to State Road 434.
Mr. Barth said what they are proposing to do if the Commission is in agreement to
bid the project is to separate out the improvements on SR 434 as a separate bid package.
Jim Van Ostran, John B. Webb & Associates, spoke about their meetings with D.O.T. He
said basically what D.O.T. has done is lengthen the tapers, lengthen the turning lanes
and there is a tremendous cross section as far as the amount of asphalt they want on
the road. Mr. Van Ostran said we have talked a lot and the costs are higher than what
we want. He said they are trying to get the costs down because this will be bypassed
in about three years.