HomeMy WebLinkAbout2009 04 13 Informational 100 Community Development Planning ProjectsCOMMISSION AGENDA
ITEM 100
April 13, 2009
Meeting
CONSENT
INFORMATIONAL X
PUBLIC HEARING
REGULAR
MGR. /DEPT
Authors ation
REQUEST: Community Development Department is advising the City Commission of the
status of various current planning projects.
PURPOSE: This purpose of this agenda item is to update the Commission on the status of
current planning projects and any events/changes since the last City Commission meeting.
Those projects listed below are those with the latest activity. For a project maps and
information on the school generation rates in the City, please go to the
http://www.wintersprin sg fl.org/item100. The number to the left of the project name in this
report corresponds to the number on the City Map showing the location of the project. Items
listed below that have changed since the last update are shown in bold type.
(1) SJRWMD(formerly Minter) Site -Staff review was held on August 25, 2008. The
site plan was reviewed at the September 3, 2008 P&Z Board meeting and the
conditional use was reviewed at the September 4, 2008 BOA meeting. Both site plan
and first reading for the rezoning were approved at the September 22, 2008
Commission meeting. The Conditional Use Permit and second reading/adoption of the
rezoning (Ord. No. 2008-12) were held at the October 13, 2008 City Commission
meeting. Public Works provided an informational up-date of the status of the
Solary Canal Stormwater Treatment Area project to the Commission at its March
23, 2009 meeting.
• (3A) Mann Site -Preliminary engineering plans for the 7,500 S.F. Ladybird Academy
Daycare were submitted on September 4 and were addressed at the September 16, 2008
staff review meeting. The project received a unanimous vote for approval at the
October 7, 2008 P&Z Board meeting and was approved, subject to conditions, at the
October 27, 2008 City Commission meeting. The Applicant submitted for final
engineering approval on April 6, 2009.
• (S) Greenway Professional Plaza (East Coast Believer's Church Property) -First
reading of the annexation ordinance (Ord. No. 2008-17) was held on September 8,
April 13, 2009
Information Item 100
Page 2
2008. The second reading and adoption was held on September 22, 2008. The first
reading of the FLU amendment (Ord. No. 2008-18) to Commercial with a Conservation
Overlay and the first reading of the rezoning (Ord. No. 2008-19) to Greeneway were
held at the October 13, 2008 City Commission meeting and they were adopted at the
October 27, 2008 meeting.
(6) Jetta Point Park -The $9.5 million slated for construction of the Jetta Point Park
project was re-appropriated in the Seminole County budget to help cover general fund
shortfalls for the 08-09 fiscal year. There are on-going discussions about increasing the
County's Bed Tax by two cents to fund this project and the Solder's Creek project.
Seminole County staff contacted City staff to schedule apre-application meeting for
Tuesday, December 2, 2008. Staff held discussion with the project designer on
November 14, 2008 to review setback and buffering issues for the park. Staff
conducted apre-application meeting with the project's designers on December 2, 2008
to review the conceptual park master plan and provide direction to the County and its
design team. The meeting included representatives of both the City of Oviedo and
LYNX. Another meeting between PBS&J staff and City staff was conducted
December 10 to further address outstanding issues. The County Leisure Services staff
met on January 6, 2009 to review the 60% design plans with the project engineer.
(8) Oviedo Marketplace -The latest plan for Section B of Parcel 14 is comprised of a
77 unit condominium project. Staff met again with the applicant's team for this project
on September 4, 2008 to review the site plan proposal. A revised concept plan was
submitted on September 25 and was reviewed at the October 21, 2008 staff review.
Staff received correspondence on December 1, stating that the applicant is now
considering developing 58 residential units and using the southerly 2.5 acres (separated
from the rest of the site by wetlands) for self-storage. The applicant is currently
finalizing the site plan to incorporate the modifications necessitated by the addition of
the self-storage facility. The applicant anticipates a late second quarter/early third
quarter 2009 start on the self storage facility and a late first quarter/early second quarter
2010 start on the residential. The applicant has contacted staff to re-establish a
schedule for approval of the PUD Master Plan and final engineering. Closing on the
storage portion of the property is tentatively scheduled for July 30, 2009.
(8A)Tuscawilla Country Club(Tuskawilla Greens) -The PUD master plan
amendment, preliminary & final PUD, and site plan received recommendations of
approval at a special August 21, 2008 P&Z meeting and were approved (along with a
development agreement and 4`'' amended settlement agreement) at the September 8,
2008 Commission meeting. An aesthetic review package for the condominium
development was submitted on November 26 and was addressed at staff review on
December 16, 2008. Plans for the renovation /modification of the tennis courts and
country club parking area were received on August 1, 2008 and were reviewed at the
August 19, 2008 staff review. The applicant submitted a plan for the borrow pit along
Northern Way for the fill material to be used on this project. Both the tennis courts and
borrow pit were addressed at the October 21, 2008 staff review. The tennis court site
plan received a recommendation of approval at the November 5, 2008 P&Z Board
meeting and was approved, subject to conditions, at the November 24, 2008
April 13, 2009
Information Item 100
Page 3
Commission meeting. At its December 8, 2008 meeting, the Commission addressed its
condition of approval that the 4tn tennis court be provided before the first certificate of
occupancy, amending the condition to allow more than one half of the 60 units to be
occupied before the fourth tennis court is required. A preconstruction meeting was
held on December 10, 2008. The Aesthetic Review was approved at the City
Commission's January 26, 2009 meeting. The final engineering and landscape plans
for the proposed Northern Way Borrow Pit was denied at the February 9, 2009 meeting
because of the well to supply the pond. The revision, without the well or the pond
liner, was approved at the February 23, 2009 Commission. The applicant paid the
arbor fee and one percent construction permit fee.
• (11) JDC Calhoun I. Construction continues. City records indicate the following
businesses are locating or have located in the JDC Calhoun Town Center:
• Building 1 -work is proceeding on the Asian Fusion restaurant (at the corner of
Tuskawilla and SR 434); the contractor notified staff that the designer of record has
been replaced for the build-out and staff awaits the prescribed documentation; plans
have been reviewed for the Huey Magoo's Chicken Tenders restaurant (at the north
end of the building) and staff received a plan re-submittal. The applicant submitted
a sign permit package for the sign on the parking lot side of the business. Staff has
made several attempts to contact the applicant and the contractor on the E&O
Fusion project but, to date, have not received a response.
• Building 4 (combination 7,800 SF first floor retail and restaurant with second and
third floor residential condominiums with a fourth floor penthouse suite -15
residential units) received a certificate of occupancy for the residential units on
March 2, 2009.
• (13) Town Center Phase II -Staff met with IBEW and Stn / 3`a Bank representatives on
August 28, 2008 to discuss a possible lot split and the location of a branch bank on a
parcel located along the north side of SR 434, just east of the McDonald's. Staff met
Atwell-Hicks Development Consultants representatives on September 24, 2008 to
discuss lot split, infrastructure, and site design issues associated with the proposed
bank. A lay-out sketch was provided to staff on October 3, 2008. This sketch and
cursory staff comments have been forwarded to Dover Kohl and Partners for further
review. Staff met again with representatives of Stn/3`a Bank and the IBEW to look at
proposals for the site design. Another proposal was sent via a-mail to staff and has
been reviewed by staff. Comments were sent to the applicant on December 30, 2008.
The FDOT has denied the turn lane request of the Stn/3`a Bank team. City staff met
with the development team on February 2, 2009 to discuss the left turn lane issue.
Additional discussions with FDOT will be scheduled regarding the turn lane and
possible access from Tuscawilla Road, behind the McDonald's site. Staff met with
representatives of Cochrane Engineering and the IBEW's attorney on March 12, 2009
to discuss details of the Phase II Implementation Agreement. Staff is currently
reviewing the Implementation Agreement to consider the client's requests and also to
re-evaluate the City's position relative to the agreement.
April 13, 2009
Information Item 100
Page 4
(13-A)Town Parke Apartments -The 10.32 acre site is located on the south side of SR
434, between the Mobile station and the pedestrian bridge. A conceptual site plan for
201 (was 204) residential apartment units (1-4 BR) with 413 (was 388) parking spaces
was submitted to the City on March 3, 2009 and was addressed at staff review on
March 19. The City Arborist and the applicant's landscape architect conducted a site
inspection for March 4, 2009. Revised plans were submitted on March 27 and are
scheduled for staff review on Apri17, 2009.
(14) Artesian Park (formerly Lincoln Park) -The applicant is working to finalize the
Development Agreement language for this project. The Development Agreement is
undergoing review by the City Attorney.
(19) Grandeville at Town Center (f/k/a Villa Grande &. Grandville) - Staff is working
with the applicant to finalize revisions to the permit plans and to finalize the address
assignments for the units. Apre-construction meeting and permit issuance should be
forthcoming in the next few weeks. Staff met with the applicant on September 29,
2008 to finalize the methodology for building valuation to be used in assessing the
appropriate building permit fees. The applicant reports renegotiating materials prices
(in light of recent price declines) in preparation for submitting for a construction permit
to do the site/civil construction and obtaining building permits. The applicant met
again with staff on December 23, 2008 and announced that, due to the international
financial crisis, they were suspending the project indefinitely. The applicant has asked
for contact information for another developer who approached the City with a proposal
for an "independent living" facility for seniors. Staff met with the applicant on
February 27, 2009 to discuss options for modifying the proposal to 144 age-restricted
apartments utilizing a site plan similar to the one previously approved.
(20) Wagner's Curve Office/Retail (Pinch A-Penny) -The aesthetic review and final
engineering/site plan were approved, subject to working out details, at the September
22, 2008 Commission meeting. The building plans are currently being reviewed for the
design professional. Staff is awaiting submittal of a draft development agreement.
Staff understands that the financing for this project was "pulled". At its February 9,
2009 meeting, the Commission addressed the applicant's request to reevaluate the
Town Center Code. Per the Commission's direction, staff has met with the applicant to
review the proposed changes to the building. Staff received the revised design on
March 3, 2009 and is currently reviewing this proposal. Staff provided
correspondence to the applicant's representative on March 31, 2009, stating a
number of concerns.
• (21) HSP Office (1.6 acre Wagner's Curve Commercial site) -Staff is continuing to
work with the applicant on certain minor site layout modifications and the aesthetic
review for these buildings. Staff is working with the applicant to finalize the aesthetic
review and signage package submittals. The aesthetic review package and revised final
engineering plans were submitted on November 6, 2008. Staff met with the applicant
on November 18, 2008 for a final review of the site engineering and aesthetic review.
The final engineering and aesthetic review were approved at the December 8, 2008 City
Commission meeting (the development agreement and subdivision plan -with
April 13, 2009
Information Item 100
Page 5
subsequent plat - aze still out-standing issues). Staff is currently working with the
Developer on placement of real estate signage for this project.
• (23) Tabs Crossing Subdivision -The plat was approved, subject to the City Attorney'
review, at the August 25, 2008, Commission. Up-dated title work was provided to the
City Attorney on September 8, 2008. The plat was recorded on September 19, 2008.
(25) Bart Phillips/ 419 Auto & Metal -On September 8, 2008, the Commission
adopted Ord. No. 2008-11, which provided a restricted C-2 zoning for the 2 pazcels
containing approximately 9.04 acres along SR 434. Staff is working with the applicant
to clarify the land use actions and to get the Consent to Zoning Restrictions document
executed. Staff met with the applicant on October 7, 2008 to discuss staffls comments
on the aesthetic review, site plan, and Ginger Lane/Old Sanford Oviedo Road ROW
vacation request. A revised aesthetic review package was received December 19, 2008
and was approved at the January 26, 2009 City Commission meeting. Vacation of the
Ginger Lane and part of the Old Sanford-Oviedo Road rights-of--way was approved at
the February 9, 2009 City Commission meeting. Staff met with the applicant's team on
March 2, 2009 to discuss the wall permit. A meeting was held with staff and the City
Attorney on March 12, 2009 to discuss the Restrictive Rezoning and the Non-
conforming use. Staff is processing the building permit application for the wall
for approval, subject to conditions (e.g. recordation of easements and rezoning to
either C-2 or restricted C-2).
(25A) Altomere Estates - On November 26, 2007, the Florida Engineering Group, on
behalf of Dr. Altomere, submitted a preliminary engineering/subdivision plan for
dividing the northern 17+ acres of the Dr. Moseley's replat into 7 residential lots
(ranging in size from 1.16 to 1.71 acres), roadway, 2 storm-water ponds, and a
previously dedicated conservation area. The plans were discussed at the December 18
staff review. On February 12, staff met with Dr. Altomare and his design engineer to
address major subdivision issues (lot size, floodplain, and emergency access). Revised
plans were submitted on December 24, 2008 and were reviewed at the February 3, 2009
staff review meeting. Staff met on Apri12, 2009 with the City Attorney to
determine how best to address the lot size compatibility issue.
~ (26) Starlight Baptist Church -Staff met with the applicant for September 18, 2008 to
discuss building construction phasing. The applicant met with the Building Official on
October 14, 2008 to discuss modifications to the building plans necessary to implement
the phasing plan. Apre-construction conference was scheduled for December 2, 2008,
but was cancelled. The architect has been working with the Building Official on a
number of building design issues. The applicant has inquired about the initial phasing
of the project. The first portion of the construction would involve the enclosing of the
existing open basketball court building to serve as an interim meeting place during
construction of the new sanctuary.
• (27) Hayes Road Plaza -The City Attorney reported to the Commission on September
8, 2008 that the owner had conveyed property for the turn lane at the corner of SR 434
and Hayes Road. Building permit application is currently under review. The plans
April 13, 2009
Information Item 100
Page 6
were resubmitted within a week. The building permit plans are nearing the end of the
review process and are being prepared for issuance. The plans are ready for issuance
and the applicant is finalizing the finance package. The owner has been notified in
writing that the building permit is ready to be issued, but, on December 19, 2008,
applied for a conditional use fora 24-hour convenience store without gas pumps. This
request was heard by the Board of Adjustment on January 15, 2009 and is scheduled for
the January 26 Commission. The City Commission approved the conditional use for
the convenience store without gas pumps at its January 26, 2009 meeting. Staff has
reviewed and responded to the traffic analysis and awaits the applicant's revisions.
Staff met with the applicant's team on February 10, 2009 to address aesthetic features
for the 7-11 convenience store.
• (36) Lakeside Plaza - A conceptual site plan for 2 buildings comprising 64,614 S.F. of
combined office and retail space on an approximately 7 '/2 acre site abutting and
including part of Lake Talmo, was reviewed at the October 16, 2007 staff review. A
revision was reviewed at the December 10, 2007 staff review; another revision was
reviewed at the March 18, 2008 staff review. The concept plan scheduled for the April
14, 2008 Commission meeting was approved at the May 27, 2008 Commission. The
applicant prepared diagrams of the proposed cantilevered deck, for discussion with staff
regarding the restaurant and the minor buffer encroachment. Final engineering plans
were submitted on January 9, 2009 and were reviewed at the February 3, 2009 staff
review meeting. An aesthetic review package was submitted on March 26 and is
scheduled for the Apri121, 2009 staff review.
STAFF CONTACTS: Staff is in the process of discussing projects with the following
applicants/owners/projects. Updates will be provided as the status changes.
Town Parke Apartments -The 10.32 acre site is located on the south side of SR 434,
between the Mobile station and the pedestrian bridge. A conceptual site plan for 204
residential apartment units (1-4 BR) and was submitted to the City on March 3, 2009 and is
scheduled for staff review on March 19. The City Arborist and the applicant's landscape
architect conducted a site inspection for March 4, 2009. The applicant submitted for a
second staff review and that review will be help on Apri17, 2009 and the project is
tentatively scheduled to be on the City Commission's Apri127, 2009 agenda for the
Commission's consideration of the Concept Plan.
Calusa Cay - A revised concept plan was discussed and a submittal, featuring 250 dwelling
units and 830 parking spaces, was submitted March 18, 2009 and is scheduled for staff
review on Apri17, 2009.