HomeMy WebLinkAbout2010 01 25 Informational 100 Status of Various Current Planning Projects COMMISSION AGENDA
CONSENT
INFORMATIONAL X
ITEM 100 PUBLIC HEARING
REGULAR
January 25, 2010
Meeting
4�,�
MGR. /DEP T
Authorization
REQUEST: Community Development Department is advising the City Commission of the
status of various current planning projects.
SYNOPSIS: The city Commission has been asked to be kept informed of all projects at all
stages of development in the City. This agenda item is an update to the Commission on the
status of current planning projects and any events /changes since the last City Commission
meeting.
CONSIDERATIONS:
Those projects listed below are those with some consistent activity, although not every project
has additional activity for every update report. For a project maps and information on the
school generation rates in the City, please go to the http:// www.winterspringsfl.org /iteml00.
The number to the left of the project name in this report corresponds to the number on the City
Map showing the location of the project. Items listed below that have changed since the last
updates are shown in bold type.
(1) SJRWMD (formerly Minter) Site Staff review was held on August 25, 2008. The
site plan was reviewed at the September 3, 2008 P &Z Board meeting and the
conditional use was reviewed at the September 4, 2008 BOA meeting. Both site plan
and first reading for the rezoning were approved at the September 22, 2008
Commission meeting. The Conditional Use Permit and second reading /adoption of the
rezoning (Ord. No. 2008 -12) were held at the October 13, 2008 City Commission
meeting. Public Works provided an informational up -date of the status of the Solary
Canal Stormwater Treatment Area project to the Commission at its March 23, 2009
meeting. A pre -bid was held April 16, 2009 with bids due April 29, 2009. The low
bidder was Briar Corporation at $1.23 million. Additional agreements were expected
to be brought to Commission in October for review. Briar Corporation backed out of
the process because they were unwilling to hold their price for 90 days. Negotiations
are underway with the next low bidder. An update on this project was at the December
14, 2009 City Commission meeting. A contract has been awarded to the 2 lowest
bidder, Wal -Rose. Construction start is awaiting receipt of an Army Corps of
Engineers permit.
(3A) Mann Site (Ladybird Academy) Preliminary engineering plans for the 7,500
S.F. Ladybird Academy Daycare were submitted on September 4 and were addressed
at the September 16, 2008 staff review meeting. The project received a unanimous vote
for approval at the October 7, 2008 P &Z Board meeting and was approved, subject to
conditions, at the October 27, 2008 City Commission meeting. The Applicant
submitted for final engineering approval on April 6, 2009. The item was addressed at
the May 5, 2009 staff review. The revised engineering plans and aesthetic package
were reviewed at the June 16, 2009 staff review. The applicant's preliminary building
plans have been reviewed for sufficiency. The final engineering/site plan and aesthetic
revisions were approved at the August 10, 2009 Commission, along with a
Development Agreement/Notice of Zoning Restriction modification. The building
plans are being reviewed for a building permit and a pre- construction meeting was held
on September 1. The building plans have been reviewed and have been ready for
issuance as of September 3, 2009. A pre construction meeting was held on October 15,
2009. Site work is proposed to start during the week of November 2, 2009. Site work
has started on the project and staff is currently reviewing an architectural change to the
building plans. Staff is working with the residents located to the north of the site to
provide additional trees on their properties as a buffer. The properties will be
designated as recipient site for trees donated in fulfillment of arbor permit obligations.
The building permit has been paid in full and should be issued on or around January 4,
2010. Site work is on -going and the building permit was issued on January 4,
2010.
(6) Jetta Point Park The $9.5 million slated for construction of the Jetta Point Park
project was re- appropriated in the Seminole County budget to help cover general fund
shortfalls for the 08 -09 fiscal year. There are on -going discussions about increasing the
County's Bed Tax by two cents to fund this project and the Solder's Creek project.
Seminole County staff contacted City staff to schedule a pre application meeting for
Tuesday, December 2, 2008. Staff held discussion with the project designer on
November 14, 2008 to review setback and buffering issues for the park. Staff
conducted a pre application meeting with the project's designers on December 2, 2008
to review the conceptual park master plan and provide direction to the County and its
design team. The meeting included representatives of both the City of Oviedo and
LYNX. Another meeting between PBS &J staff and City staff was conducted
December 10 to further address outstanding issues. The County Leisure Services staff
met on January 6, 2009 to review the 60% design plans with the project engineer.
Planning staff have attempted to initiate a series of meetings to expedite design, review,
approvals, and construction. A meeting has been requested by the County's design
engineer (PBS &J). This meeting will enable City Staff to discuss any outstanding
coordination issues on the park. Urban Beautification/Arbor staff met with the design
team on -site on May 19, 2006 to discuss tree quantification procedures and mitigation
options. Staff is currently working with the design professional to prepare for a
submittal to the City for Preliminary /final site plan approval. Staff has been contacted
relative to the submittal of both the geotechnical report and the traffic study for the
park. Staff received an aesthetic review package for the park on July 30, 2009 and
addressed it with the applicant at the August 18, 2009 staff review. The complete site
plan application package was received on August 21 and was addressed at staff review
on September 15. Staff has reviewed and, at the September 1, 2009 staff review,
provided comments to representatives of the adjacent Vistawilla site, regarding access
to the park through the Vistawilla site. Staff and PBS &J held a conference call on
October 1 to address final comments and to craft a schedule for public hearings, P &Z
and Commission meetings for the aesthetic review, site plan/final engineering, and
developer's agreement. Staff is expecting a resubmittal from the project engineer in
late November of December 2009. Staff will be meeting with the applicant during the
week of December 7, 2009 to discuss the City's littoral planting requirements for the
retention ponds. Staff has been advised by the consultant that a resubmittal should be
forthcoming in January 2010. The consultant has submitted the Florida
Department of Environmental Protection (FDEP) water and sewer permits
applications to the City. Review of the applications is complete and staff is waiting
on the fee submittal.
(8) Oviedo Marketplace —The latest plan for Section B of Parcel 14 is comprised of a
77 unit condominium project. Staff met again with the applicant's team for this project
on September 4, 2008 to review the site plan proposal. A revised concept plan was
submitted on September 25 and was reviewed at the October 21, 2008 staff review.
Staff received correspondence on December 1, stating that the applicant is now
considering developing 58 residential units and using the southerly 2.5 acres (separated
from the rest of the site by wetlands) for self storage. The applicant is currently
finalizing the site plan to incorporate the modifications necessitated by the addition of
the self storage facility. The applicant anticipates a late second quarter /early third
quarter 2009 start on the self storage facility and a late first quarter /early second quarter
2010 start on the residential. The applicant has contacted staff to re- establish a
schedule for approval of the PUD Master Plan and final engineering. Closing on the
storage portion of the property is tentatively scheduled for July 30, 2009. Discussions
with the applicant on June 15, 2009 indicated that they are now working with two
storage companies. One of those companies seems to be able to raise the required
equity capital required by the lender. The applicant will be back in touch with staff by
the end of June with a status update. The applicant has informed staff that the initial
storage company has experienced some financing concerns and discussions are now
open with a second storage company for the commercial section of this development.
On August 10, 2009, the Commission agreed with the applicant's request to allow a
100,000 SF storage facility within the DRI /PUD, which must be followed up by a
modification to the Development Order and /or NOPC. Staff is currently reviewing a
proposed change to the binding development agreement for this project to facilitate the
storage facility as well as the remaining portions of Parcel 14. Staff held a conference
call on October 2, 2009 to negotiate the final conversion n umbers for the requested
usage change from 100 townhomes to an ACLF /Independent Living Facility in addition
to the recently approved indoor storage facility. At its October 12, 2009 meeting the
Commission approved an implementation agreement authorizing the indoor personal
storage and approved the concept of substituting either 184 independent living units,
318 assisted living facility beds, or some combination of these on the remaining portion
of Parcel 14. Staff is working with the applicant to determine the final composition of
the project proposal and to determine the proper implementation strategy to facilitate
the project. Staff is also working with the City Attorney to craft language for an
Implementation Agreement. Revisions to the Implementation Agreement language
are scheduled to be completed during the week of January 18, 2010.
(8A) Tuskawilla Greens (Tuscawilla Country Club) —The PUD master plan
amendment, preliminary final PUD, and site plan received recommendations of
approval at a special August 21, 2008 P &Z meeting and were approved (along with a
development agreement and 4 amended settlement agreement) at the September 8,
2008 Commission meeting. An aesthetic review package for the condominium
development was submitted on November 26 and was addressed at staff review on
December 16, 2008. Plans for the renovation /modification of the tennis courts and
country club parking area were received on August 1, 2008 and were reviewed at the
August 19, 2008 staff review. The applicant submitted a plan for the borrow pit along
Northern Way for the fill material to be used on this project. Both the tennis courts and
borrow pit were addressed at the October 21, 2008 staff review. The tennis court site
plan received a recommendation of approval at the November 5, 2008 P &Z Boaid
meeting and was approved, subject to conditions, at the November 24, 2008
Commission meeting. At its December 8, 2008 meeting, the Commission addressed its
condition of approval that the 4 tennis court be provided before the first certificate of
occupancy, amending the condition to allow more than one half of the 60 units to be
occupied before the fourth tennis court is required. A preconstruction meeting was
held on December 10, 2008. The Aesthetic Review was approved at the City
Commission's January 26, 2009 meeting. The final engineering and landscape plans
for the proposed Northern Way Borrow Pit was denied at the February 9, 2009 meeting
because of the well to supply the pond. The revision, without the well or the pond
liner, was approved at the February 23, 2009 Commission. The applicant paid the
arbor fee and one percent construction permit fee. Construction has begun on the tennis
court relocation. Site work has also started on the condominium site and silt fences
have been installed at the borrow area. Architectural plans have been reviewed by the
Building Division. Congressional Homes met with staff regarding the future
replacement (on Golf Course property) of a large equipment storage shed. The
applicant proposes to eliminate the decorative faux chimneys from the architectural
design, since the units were designed without fireplaces. The aesthetic review
modification to remove the faux chimneys was approved at the July 13 Commission
meeting. Preliminary discussions have taken place regarding the need for a second
borrow area on the golf course property. Staff has yet to see any drawings depicting
this area and will update the Commission as information becomes available. The
applicant has submitted engineering drawings for the proposed second borrow area
located along Northern Way, just westward of the first borrow area. Staff review for
these plans was held on July 21, 2009. The applicant has received staff's comments on
the borrow area and is revising the plans accordingly and will be contacting the
homeowners located across Northern Way from the proposed project to discuss their
concerns. The borrow area concept utilized on the east side of Wicklow Way has been
modified to become a "depressional area" with 4:1 side slopes and a grass surface.
Consideration of the final engineering and landscape plans for the golf course feature
with dry retention was postponed from the August 10 Commission meeting to the
August 24, 2009 meeting. At the August 24 meeting it was announced that the
applicant has withdrawn plans for this excavation from consideration. The City's
Building Official met with the applicant on October 1, 2009 to discuss the permit and
impact fees for this project. The site superintendent has met with staff regarding
provision of the fourth tennis court. Staff met with a Taylor Morrison representative on
October 29 and December 1, to discuss entitlements, obligations, and other issues
associated with the development. Taylor Morrison is considering taking over the
building construction on the project. Meetings have be held on December 10 and 14,
2009 to discuss site acceptance, bonding requirements, landscape/hardscape
modification proposals, and the Settlement Agreement condition (and subsequent
Commission action) regarding provision of a 4th tennis court. Taylor Morrison has
indicated that they are not moving forward with the deal on the vertical
construction at this time because the appraisals for the condominiums did not
meet their financial requirements. The property owner has indicated that Taylor
Morrison is continuing to review the appraisal situation.
(11) JDC Calhoun I. City records indicate the following businesses are locating or
have located in the JDC Calhoun Town Center:
City staff is currently compiling an ownership map for Phase I of the Town Center.
This map will be made available electronically for reference purposes. Staff is
arranging a meeting with the new management company to discuss landscape and
hardscape maintenance, irrigation system repair and maintenance as well as overall
site maintenance. Staff met with two of the management /leasing companies on
December 8, 2009 to discuss the current status of the Town center /lease
amounts /recent tenant losses, and plans for moving the Town Center forward. Staff
just received an e -mail list from the tenant meeting and will be updating the tenants
on all relevant information regarding the management and final ownership of the
various section of the Town Center. Staff is working with Transwestern
(management company) to locate Verizon Wireless Services at the western end
of Building 11. Staff has a meeting scheduled for January 19, 2010 with a
representative of Business Capital Solutions Group regarding marketing of the
Town Center. This representative is also contacting the management
companies for the Town Center properties. It is staffs understanding that the
receivership should be settled by the end of January 2010.
(13) Town Center Phase II Staff met with IBEW and 5 3` Bank representatives on
August 28, 2008 to discuss a possible lot split and the location of a branch bank on a
parcel located along the north side of SR 434, just east of the McDonald's. Staff met
Atwell -Hicks Development Consultants representatives on September 24, 2008 to
discuss lot split, infrastructure, and site design issues associated with the proposed
bank. A lay -out sketch was provided to staff on October 3, 2008. This sketch and
cursory staff comments have been forwarded to Dover Kohl and Partners for further
review. Staff met again with representatives of 5 /3 Bank and the IBEW to look at
proposals for the site design. Another proposal was sent via e -mail to staff and has
been reviewed by staff. Comments were sent to the applicant on December 30, 2008.
The FDOT has denied the turn lane request of the 5 rd Bank team. City staff met
with the development team on February 2, 2009 to discuss the left turn lane issue.
Additional discussions with FDOT will be scheduled regarding the turn lane and
possible access from Tuskawilla Road, behind the McDonald's site. Staff met with
representatives of Lochrane Engineering and the IBEW's attorney on March 12, 2009
to discuss details of the Phase II Implementation Agreement. Staff is currently
reviewing the Implementation Agreement to consider the client's requests and also to
re- evaluate the City's position relative to the agreement. A meeting was held with a
representative of Phase II -A on April 24, 2009 to discuss the access options for the
5 /3` bank site proposed at S.R. 434 and Loop Road. The City Attorney and the new
owner are negotiating a revision to the implementation agreement. Staff is currently
reviewing a first draft of this agreement modification. Staff has met to consider the
applicant's draft of a revised implementation agreement. The outcome of this meeting
is that staff is concerned about some of the proposed language and is opposed to any
changes to the agreement at this time. A meeting with the property owner is scheduled
for November 16, 2009 to discuss the Phase II implementation agreement. Staff and
the City Attorney met with representatives of the IBEW on December 7, 2009 about
possible modifications to the Implementation Agreement. Agenda Item 601 on the
January 25, 2010 City Commission Meeting will be addressing the proposed
changes to the Phase 2 Implementation Agreement.
(13- A)Town Parke Apartments The 10.32 acre site is located on the south side of
SR 434, between the Mobile station and the pedestrian bridge. A conceptual site plan
for 201 (was 204) residential apartment units (1 -4 BR) with 413 (was 388) parking
spaces was submitted to the City on March 3, 2009 and was addressed at staff review
on March 19. The City Arborist and the applicant's landscape architect conducted a
site inspection for March 4, 2009. Revised plans were submitted on March 27 and
were addressed at staff review on April 7, 2009. Further revised plans were received
on April 10 and were approved as a concept review by the Commission on April 27,
2009. The concept approval was re -heard at a May 18, 2009 special meeting and was
approved subject to a negotiated Development Agreement with specific stipulations.
Further discussion ensued at the special May 26, 2009 Commission meeting regarding
crime statistics for high density housing areas. Staff has had no recent
communications with the applicant for this development.
(14-A) Magnolia Park Staff met with the design team on April 14, 2009 to provide
initial comments on the trail land swap, site, and building design, for the amphitheater
with its changing rooms and rest rooms, in preparation for formal submittals. Staff met
with the consultants on May 14, 2009 to discuss the landscaping, lighting, and sound
components of the design. Additional discussions were held on May 29, 2009
regarding the lighting and sound designs. Staff has received the 60% plans on July 31,
2009 and addressed these plans at the September 1, 2009 staff review. Aesthetic
Review of this project was conducted as part of the October 6, 2009 staff review
meeting. Staff is awaiting the resubmittal of the aesthetic review documents in
response to the October 6, 2009 review. Final staff review of the aesthetics and final
engineering was held on December 8, 2009. Staff is waiting on the final engineering
and aesthetic review drawings for submittal to the City Commission. Also, the
trail swap is being delayed because the State wants to bundle the Magnolia Park
Trailhead and the Bart Phillips trail right -of -way dedication along SR 419
together. Staff is working to resolve these items.
(19) Grandeville at Town Center (f/k/a Villa Grande Grandville) Staff is working
with the applicant to finalize revisions to the permit plans and to finalize the address
assignments for the units. A pre construction meeting and permit issuance should be
forthcoming in the next few weeks. Staff met with the applicant on September 29,
2008 to finalize the methodology for building valuation to be used in assessing the
appropriate building permit fees. The applicant reports renegotiating materials prices
(in light of recent price declines) in preparation for submitting for a construction permit
to do the site /civil construction and obtaining building permits. The applicant met
again with staff on December 23, 2008 and announced that, due to the international
financial crisis, they were suspending the project indefinitely. The applicant has asked
for contact information for another developer who approached the City with a proposal
for an "independent living" facility for seniors. Staff met with the applicant on
February 27 and again on April 16, 2009 to discuss options for modifying the proposal
to 144 age- restricted apartments utilizing a site plan similar to the one previously
approved. Further discussions relative to the final design and economic development
incentives for this project were scheduled for June 9, 2009, but were re- scheduled for
June 16, 2009. The applicant is currently working on financing for this project and the
City is continuing consideration of potential economic development incentives. Staff is
working with the applicant to finalize the financial package and to finish the write up to
be used in marketing the project. Staff provided a letter on September 28, 2009
detailing the existing project status. This letter will be used as part of the financial
package for the project. Staff met with the project representative on October 19, 2009
to discuss the schedule for consideration/approval of the project modifications as
related to the conversion of the project to age- restricted apartments. Staff left a
message for the applicant on January 15, 2010 and is awaiting an update.
(20) Wagner's Curve Office /Retail (Pinch -A-Penny) The aesthetic review and final
engineering /site plan were approved, subject to working out details, at the September
22, 2008 Commission meeting. The building plans are currently being reviewed for the
design professional. Staff is awaiting submittal of a draft development agreement.
Staff understands that the financing for this project was "pulled At its February 9,
2009 meeting, the Commission addressed the applicant's request to reevaluate the
Town Center Code. Per the Commission's direction, staff has met with the applicant to
review the proposed changes to the building. Staff received the revised design on
March 3, 2009 and is currently reviewing this proposal. Staff provided correspondence
to the applicant's representative on March 31, 2009, stating a number of concerns. At
the October 26, 2009 Commission meeting, the applicant requested the Commission
consider changes to the Town Center Code to accommodate this site. Staff met with
the applicant on October 29, 2009 to discuss options for implementation of this project
and possible code modifications. Staff is working on possible text amendments for
the Town Center District to address small, irregularly- shaped lots and a possible
"transition area" for the periphery of the Town Center District. Staff is trying to
move this proposed text amendment to the Planning and Zoning Board at their
February 2010 meeting.
(21) HSP Office (1.6 acre Wagner's Curve Commercial site) Staff is continuing to
work with the applicant on certain minor site layout modifications and the aesthetic
review for these buildings. Staff is working with the applicant to finalize the aesthetic
review and signage package submittals. The aesthetic review package and revised final
engineering plans were submitted on November 6, 2008. Staff met with the applicant
on November 18, 2008 for a final review of the site engineering and aesthetic review.
The final engineering and aesthetic review were approved at the December 8, 2008 City
Commission meeting (the development agreement and subdivision plan with
subsequent plat are still out standing issues). Staff is currently working with the
Developer on placement of real estate signage for this project. Permits for the real
estate signage have been issued. Conversations with the owners indicate that they are
still seeking financing as well as placing the lots on the open market for sale and,
preferably, development in accordance with the entitlements that they currently have
from the City. On November 17, 2009, staff met with representatives of The Primrose
School to discuss a proposed concept plan for this property. The owner has indicated
that there are on -going discussions with the realtor of the Primrose Academy and
they are actively working toward a sale of the property to the Primrose Academy.
(25) Bart Phillips /419 Auto Metal —On September 8, 2008, the Commission
adopted Ord. No. 2008 -11, which provided a restricted C -2 zoning for the 2 parcels
containing approximately 9.04 acres along SR 434. Staff is working with the applicant
to clarify the land use actions and to get the Consent to Zoning Restrictions document
executed. Staff met with the applicant on October 7, 2008 to discuss staff's comments
on the aesthetic review, site plan, and Ginger Lane /Old Sanford Oviedo Road ROW
vacation request. A revised aesthetic review package was received December 19, 2008
and was approved at the January 26, 2009 City Commission meeting. Vacation of the
Ginger Lane and part of the Old Sanford Oviedo Road rights -of -way was approved at
the February 9, 2009 City Commission meeting. Staff met with the applicant's team on
March 2, 2009 to discuss the wall permit. A meeting was held with staff and the City
Attorney on March 12, 2009 to discuss the Restrictive Rezoning and the Non-
conforming use. Staff is processing the building permit application for the wall for
approval, subject to conditions (e.g. recordation of easements and rezoning to either C-
2 or restricted C -2). The applicant has made application to rezone the C -1 property
along SR 419 to a non restricted C -2 zoning in place of the restricted C -2 previously
approved by the City Commission. The new rezoning request received a
recommendation for approval at the June 3, 2009 Planning and Zoning Board meeting
and Ordinance No. 2009 -10 is scheduled for first reading at the June 22, 2009
Commission meeting. Second and final reading for the rezoning of the property along
SR 419 was approved on July 13, 2009. The Building permit for the first phase of the
screen wall along the property's eastern boundary was issued on September 28, 2009.
Staff has received a request for a waiver of the front setback along S.R. 419, behind the
screen wall. Staff will be processing the waiver request during the December /January
meeting cycles. Staff is also working with the City Attorney's office to finalize code
language to address the existing metal recycling operation in the Light Industrial zoning
district. A waiver for the front setback along SR 419, behind the 10 -foot wall will
be taken to the Board of Adjustment on January 21, 2010 and should come to the
City Commission on the second meeting in January. The City Attorney and staff
are taking an ordinance to the Planning and Zoning Board in February 2010 with
proposed text amendments regarding permitted uses in the City's I -1 Zoning
District.
(25A) Altomere Estates On November 26, 2007, the Florida Engineering Group, on
behalf of Dr. Altomere, submitted a preliminary engineering/subdivision plan for
dividing the northern 17+ acres of the Dr. Moseley's replat into 7 residential lots
(ranging in size from 1.16 to 1.71 acres), roadway, 2 storm -water ponds, and a
previously dedicated conservation area. The plans were discussed at the December 18
staff review. On February 12, staff met with Dr. Altomare and his design engineer to
address major subdivision issues (lot size, floodplain, and emergency access). Revised
plans were submitted on December 24, 2008 and were reviewed at the February 3, 2009
staff review meeting. Staff met on April 2, 2009 with the City Attorney to determine
how best to address the lot size compatibility issue. The subdivision variance requests
were heard at a special May 21, 2009 BOA meeting, to address lot size and maximum
cul -de -sac length variances. The applicant met on May28 with the neighbors in
Dunmar, to ascertain their concerns. The variances were addressed at a public hearing
at the June 8, 2009 Commission meeting and postponed until the emergency access
issue is resolved. Access documentation from the applicant was sent to the City
Attorney on October 21, 2009 for his review and comments. Staff met with the City
Attorney on January 14, 2010 to discuss the emergency access location for this
property. Staff is working with the Fire Marshal and the developer to finalize an
acceptable emergency access for this project.
(26) Starlight Baptist Church Staff met with the applicant for September 18, 2008 to
discuss building construction phasing. The applicant met with the Building Official on
October 14, 2008 to discuss modifications to the building plans necessary to implement
the phasing plan. A pre construction conference was scheduled for December 2, 2008,
but was cancelled. The architect has been working with the Building Official on a
number of building design issues. The applicant has inquired about the initial phasing
of the project. The first portion of the construction would involve the enclosing of the
existing open basketball court building to serve as an interim meeting place during
construction of the new sanctuary. The contractor and site engineer have renewed
efforts to coordinate limited site work and enclosure of the covered basketball court
with staff. A very limited plan was addressed at the October 20, 2009 staff review.
Staff met with the consultant for this project on January 14, 2010. They are
proposing to enclose the basketball court for an overflow facility as phase 1 of the
development. Staff is working with the developer on Development Agreement
language requiring sidewalks on Bahama when the City paves that Road. The
consultant indicated that the Church may be in a position to begin the
construction on the first part of the new sanctuary by the summer of 2010.
(27) Hayes Road Plaza —The City Attorney reported to the Commission on September
8, 2008 that the owner had conveyed property for the turn lane at the corner of SR 434
and Hayes Road. Building permit application is currently under review. The plans
were resubmitted within a week. The building permit plans are nearing the end of the
review process and are being prepared for issuance. The plans are ready for issuance
and the applicant is finalizing the finance package. The owner has been notified in
writing that the building permit is ready to be issued, but, on December 19, 2008,
applied for a conditional use for a 24 -hour convenience store without gas pumps. This
request was heard by the Board of Adjustment on January 15, 2009 and is scheduled for
the January 26 Commission. The City Commission approved the conditional use for
the convenience store without gas pumps at its January 26, 2009 meeting. Staff has
reviewed and responded to the traffic analysis and awaits the applicant's revisions.
Staff met with the applicant's team on February 10, 2009 to address aesthetic features
for the 7 -11 convenience store. City staff has approved the revisions to the traffic
study. The Building Official has been working with the owner to prevent the building
permit application from expiring, as the applicant continues to seek financing. The
project representative contacted City Staff on October 19, 2009 to let us know that they
are almost finished with modification of the architectural plans to comply with the 2007
Florida Building Code. Updated construction plans were delivered for review on
October 29, 2009. These plans are currently under review by the building division. A
contract has been awarded for the turn lane on east -bound SR 434 and construction
should begin after the first of the year. At its December 14, 2009 meeting, the
Commission directed the City Engineer to address access options for this and the
adjacent commercial site (to the west) to the January 11, 2010 Commission meeting.
Construction has been initiated with most of the current work centering on utility
relocations.
(28) Park Manor Academy Having obtained a conditional use and a waiver from the
building setback requirements, the applicant has submitted a combined preliminary and
final engineering plan submittal for the proposed 3,459 SF day care /pre- school facility
with 13 parking spaces, located at the SE end of Excelsior Parkway. The project was
addressed at the May 5, 2009 staff review. A plan resubmittal was received July 17,
2009 and has been reviewed by applicable staff. Staff awaits revised plans from the
design engineer. A response to staffs comments was received on December 30, 2009.
Staff is currently finalizing their review of the final engineering.
(36) Lakeside Plaza A conceptual site plan for 2 buildings comprising 64,614 S.F. of
combined office and retail space on an approximately 7 '/2 acre site abutting and
including part of Lake Talmo, was reviewed at the October 16, 2007 staff review. A
revision was reviewed at the December 10, 2007 staff review; another revision was
reviewed at the March 18, 2008 staff review. The concept plan scheduled for the April
14, 2008 Commission meeting was approved at the May 27, 2008 Commission. The
applicant prepared diagrams of the proposed cantilevered deck, for discussion with staff
regarding the restaurant and the minor buffer encroachment. Final engineering plans
were submitted on January 9, 2009 and were reviewed at the February 3, 2009 staff
review meeting. An aesthetic review package was submitted on March 26 and was
addressed at the April 21, 2009 staff review. Staff has reviewed and provided
comments on the traffic analysis (the traffic engineer's response and revisions were
received on June 11). The revised traffic analysis was approved by staff on July 16,
2009. Staff has addressed the final engineering /site plans and aesthetic review material
at the August 18, 2009 staff review. At the same meeting, 17 -92 CRA Program
Manager John Metsopoulos addressed the applicant and staff regarding potential CRA
funding for this project. Staff provided information on an alternative point of
connection to the public sewer system in the Harbor Winds Development.
The following item(s) will be removed from the next report:
(23) Talis Crossing Subdivision —The plat was approved, subject to the City Attorney'
review, at the August 25, 2008, Commission. Up -dated title work was provided to the
City Attorney on September 8, 2008. The plat was recorded on September 19, 2008.
FISCAL IMPACT: There is no fiscal impact associated with this agenda item.
COMMUNICATION EFFORTS: No communication efforts beyond the advertising of the
Commission agenda are necessary in conjunction with this agenda item.
RECOMMENDATION: The City Commission is being asked to review and accept the
information in this agenda item.