REQUEST: City Mamlger requesting the Commission to receive the report of
the Information's Systems Director relative to the status of the development of
the City's information system and to authorize additional funding in the amount
of $42,000 to expedite certain activities.
PURPOSE: The purpose of this agenda item is to update the Commission on the
status of the development of the City's voice and data communication systems and to
request additional funding for activities that need to be undertaken in the current fiscal
year.
DISCUSSION:
In 1996 the City adopted a Five Year Master Plan for development for the City's Data
Programming System.
All activities included in the Master Plan are on, or ahead of schedule.
The scope of work activlities in the Master Plan and in the current year work plan has
changed due to the following reasons:
1. Additional activities:
a) Telephone system developments.
b) Commission Chamber audio visual system.
2. Emergency Activities
a) Police Department CADD and Records Management System
incomp,9tible with new infrastructure system and year 2000
complialnce problem.
b) Utility Billing conversion incompatible with new window N.T.lUNIX
operating platform and not year 2000 compliant.
c) Police Department voice and data infrastructure system not provided
for in original design of police department.
3. Expedited Activities
a) Compl1etion of Fire, Police, Public Work sub area network.
b) Compl1etion of City Hall, Building, Police network system.
c) UpdatEl Police, Fire, Public Works, hardware systems
incompatibilities.
Additional spending autihority of $42,000 is being required for the expedited items as
follows:
Complete Fire, Police, Public Works Sub area network.
Complete City Hall Building data network system.
The expedited update of the Police, Fire, Public Works hardware system was
absorbed in the current year budget.
Considerable interest has been expressed in E-mail services. E-mail services are not
scheduled for implementation until FY 99, since E-mail service are dependent upon
net- working compatibiliRy not currently available but scheduled for completion this
year.
Internal E-mail services will be available inside the two sub area networks in FY 98 if
the Commission awards the additional $42,000 request.
Internal E-mail service between the two sub area networks is not scheduled and
cannot be provided until FY 99.
Internet E-mail between the City and the public is scheduled to be available in FY 99
and cannot be made available in FY 98.
FUNDING:
Funding for this n3quest would be taken from General Fund Reserves.
RECOMMENDATION:
1. Review and accept report of the Information Systems Director.
2. Authorize $42,000 in additional expenditures from General Fund Reserves
for expediting system development needs.
ATTACHMENT:
A) Master Plan
B) Man-hour chart by function.
C) Data processing work load chart
D. Internal/external allocations chart
COMMISSION ACTION,:
INFORMATION SERVICES
SYSTEMS DEVELOPMENT UPDATE
Attachment "A"
Development Goals Sz Objectives FY 1996 FY 1997 FY 1998 FY 1999 FY 2000 Comments
Master Plan Development
Hardware upgrades to run software (temporary) XX completed on schedule
Hardware upgrades & Standardization to Pentium class machines _ X* X will be completed ahead of schedule if funded
Software upgrades and Standardization to Microsoft Office XX completed on schedule
Software training for Microsoft Office
XX ___
completed on schedule
Phase out of old desktop software
XX _ _ __
will be completed on schedule
Software license review and document
XX _
completed on schedule
Intemal email within each subarea network _ X* X will be completed ahead of schedule, if funded
Internal email between both subarea networks
X ___
will be completed on schedule
Internet email
X _
will be completed on schedule
Network Infrastructure Development __
Internal Intra-buildins~ networks:
Police Department XX completed on schedule
Fire Department (#24) X X completed ahead of schedule
Public Works
X
X _
completed ahead of schedule
City Hall X* X will be completed ahead of schedule, if funded
Parks & Recreation X* X will be completed ahead of schedule, if funded
Sub-area networks: ---
Fire-Police-Public Works (subnetwork #1) X* X will be completed ahead of schedule, if funded
City Hall (part of subnetwork #2) X* X will be completed ahead of schedule, if funde
d
Wide Area network: __
__
Subnetworks 1 & 2 connected X dependent upon what we complete in FY 98
Miscellaneous remote sites connected to Wide area network X will be completed on schedule
Additional, unscheduled, unplanned items for Information Services
Utility Billing Conversion X will be completed in May 199
8
Utility Billing handheld conversion
X _
_
will be completed in May 1998
Commission Chambers Audio Visual Project
X _
will be completed in June 1998
Voice/Data cabling infrastructure at Public Safety Building X completed in FY 97 before move-in
Telephone System, city-wide X will be completed by Aug '98
L
d
b
d
t
t _
an
-
ase
managemen
sys
em X X This implementation must be moved to FY 2000
Police CAD & RMS system replacement _ X Emergency priority for FY 99
Legend: _
X =scheduled completion
=completion date
* =completion date with additional fundin requested
The above chart shows projects, both planned and unplanned, that Information Services was either involved with or totally completed.
INFORMATION SERVICES
Man-hour distribution by Function
Department Adr
10%
Misc.
10%
Attachment "B"
slephone Systems
40%
Comps
systems
40%
INFORMATION SERVICES
Data Processing
Systems Management
Workload Distribution
Systems Planning & Design
25%
Systems Operations
45%
Systems Development
30%
Attachment "C"
Forty-five percent (45%) of the I.S. Department's time is consumed by day to day operations of existing systems
demonstrating a lack of time to concentrate further on systems development desired by everyone.
INFORMATION SERVICES
Man-hour Resource Allocation
spent by I.S. personnel
35%
Time spent by outsourced perso
65%
Attachment "D"
Sixty-five percent (65%) of I.S. Department functions are being performed by outside contractors resulting in maximum
efficiencies and less personnel on the City payroll.