HomeMy WebLinkAbout1996 10 28 Regular Item B
('.
C.OMMISSION AGENDA
ITEM B
REGULAR X
CONSENT
INFORMATIONAL
October 28. 1996
Meeting
MG~if /DEFT jL V
uthorization
REQUEST: Utility Department Requesting Authorization to Increase the Contract
Amount for Well #6 and to Execute Supplement #2 to Amendment 32 for
Consulting Engineering Services
PURPOSE: The purpose ofthis Board item is to request additional construction funds for the
Potable Water Supply Well #6 Contract with American Drilling, Inc. and to also
authorize the execution of Supplement #2 to Amendment 32 - Construction
Administration Services for Well #6 with Conklin, Porter & Holmes Engineers,
Inc.
CONSIDERATIONS:
Approval of the additional construction fund monies and additional engineering
services is needed to complete the construction of Potable Water Supply Well #6. The
construction contract for Well #6 was awarded to American Drilling, Inc. in the amount of
$130,000 as authorized by Consent Agenda Item B ofthe February 12, 1996 City
Commission meeting agenda. The approval included a 10% contingency for a total
authorized expenditure of$143,000.
There have been many modifications to the bid quantities based on difficulties
encountered during construction with the geology in the area. To date we have
authorized two change orders totaling $9,269.10 which we thought would be sufficient to
complete the well. However, during the final pump test, a subsidence occurred adjacent
to the well which indicates an unacceptable connection between the surface sand layer and
October 28, 1996
Regular Agenda Item B
Page .1
well production zone. A detailed report from the hydrogeologist is attached which
summarizes the project to date and lists our options. A proposed change order #3 is
attached for modification to the well (Option #3 ofthe report) so the well can be
completed and put in service. The total estimated cost including previous authorized
change orders and proposed change order #3 is $161,882.10.
Supplement #2 to Amendment 32 for Conklin, Porter and Holmes - Engineers, Inc
authorizes an additional $8,855.00 which is for the increased cost of full time inspection
during the completion of the well and for costs incurred that exceeded the original scope
of work. Amendment 32 was for the design ofthe well at a cost of$15,000. Supplement
#1 to Amendment 32 was for Construction Administration and Inspection Services at a
cost of$11,840.
Original Contract
Change Order #1
Change Order #2
Proposed Change Order #3
Total
$130,000.00
$7,805.70
$1,463.40
$22.553.00
$161,822.10
ALTERNATIVES:
The City has three options to choose from for Well #6.
1. Well Abandonment and New Well Construction. This option is the most
expensive because we have already close to $100,000 invested in this well.
2. Well Cavving. This option is the least expensive because we would be
stopping where were at and incurring only minor additional expenses. However, we
would not have gained our objective which is to provide a backup potable water supply
well for WTP#2.
3. Well Modifications. This option entails temporarily backfilling, pressure
grouting, and telescoping a 10" casing inside the existing 16" casing. The additional costs
are estimated at $31,882.10 over the bid costs. While there is a slight chance that this
option could fail the need for a second well makes this the most cost effective option.
October 28, 1996
Regular Agenda Item B
Page3.
FUNDING:
The cost for change order #3 to the construction contract with American
Drilling,Inc. is $22,553.00 for a total estimated construction cost of$161,822.10. The
cost for Supplement #2 to Amendment 32 for consulting engineering services with
Conklin, Porter and Holmes - Engineers, Inc. is $8,885.00 all of which is for the
hydrogeologist subconsultant. Funds are available from the Utility Enterprise Account
fund balance. Funds for the contract change order and engineering supplement will be
expended by January 15, 1997.
RECOMMENDA TION:
It is recommended that additional funds be authorized for the Well #6 construction
contract with American Drilling, Inc. for a total estimated contract cost of$161,822.10 plus a 5%
contingency. It is also recommended that authorization be given to execute Supplement 2 to
Amendment 32 for consulting engineering services with Conklin, Porter and Holmes Engineers,
Inc. for a cost of$8,885. The source of funds for both items will be the Utility Enterprise Fund.
IMPLEMENTATION SCHEDULE:
The contractor is tentatively scheduled for remobilization on November 18, 1996.
All work should be completed by January 15, 1997.
ATTACHMENTS:
1. Supplement #2 to Amendment 32
2. Hydrogeologist Report
3. Change Order #3 to Well #6 Contract with American Drilling, Inc.
COMMISSION ACTION:
Attachment No. 1
AMENDMENT No. 32
SUPPLEMENT No.2
CONSULTING ENGINEERING SERVICES
This supplement is made and entered into this day of
1996, by and between the City of Winter Springs and Conklin,
Porter and Holmes - Engineers, Inc.
WHEREAS, the CITY and ENGINEER have previously entered into an Agreement for
the ENGINEER's professional services (Amendment No. 32); and
WHEREAS, the CITY and the ENGINEER shall refer to Amendment No. 32 herein,
and desire to have it incorporated by reference; and
WHEREAS, the CITY and the ENGINEER now wish to modify and add specific items
to Amendment 32.
NOW THEREFORE, in consideration of the mutual promises and covenants contained
herein and given one to the other, the sufficiency of which is hereby acknowledged, the parties
agree as follows:
I. SCOPE OF WORK
The scope of work has been agreed to by the parties, and is attached hereto and
incorporated herein, by reference, as Exhibit 1. Terry M. Zaudtke, P .E.,
Senior Vice President, has been designated as Project Manager for this project,
by the ENGINEER.
II. EEE
The fee has been agreed to by the parties, and as attached hereto and
incorporated herein, by reference, as EXHIBIT II. .
ID. TERM
The term of this. Supplement shall be for four (4) months from the date of final
execution by the City.
fJ
IV. ENTIRE AGREEMENT
This supplement supersedes all previous authorizations, agreements, or
representations, either verbal or written, heretofore in effect between the CITY
and the ENGINEER that may have concerned the matters covered herein,
except that this Supplement shall in no way supersede or amend Amendment 32
or other authorizations except as specifically provided herein. No additions,
alterations, or variations to the terms of this Supplement shall be valid, nor can
the provisions of this supplement be waived by either party, unless such
additions, alterations, or waivers are expressly set forth in writing in a
document of import equal to Amendment 32 or the Supplement, and duly
executed.
IN WITNESS WHEREOF, the parties hereto have executed this Supplement No.2 on
the day and year first written above.
CITY OF WINTER SPRINGS, FLORIDA
BY:
DATE:
ATTEST AND SEAL:
City Clerk
!trOtKJAS,c ~/YI MlI~/I'tf,
~~I /o/f1l~"'-t '~l/f~
&'~/d4rdhJ..~~
CONKLIN, PORTER AND HOLMES
ENGINEERS, INC.
BY: 7J:;~ $" V,P-
DATE: j. f(; .
A~~_
---.....
.. .~. ...,........... .- .-.~....~,....:...~........l~'.JJ~... ..I..:",,,,~\L.'"
ExmBIT I
SUPPLEMENT No.2
ENGINEERING SCOPE OF SERVICES
1) Retain the services of a Geologist to provide the inspection services required for the
modification of the well. These services are described in the attached letter from L J.
Nodarse and Associates,
,... .. ".., ..~, .... , ~,u..~ ,j r... .;'.'.~ ,.~. .. ;,:, ~.. ~'_,' , '..,~..:.',' '~,..., l.. ..,:\: ..::,: L'~t..~.: G-:':~j',';,~"
RECEIVED
If Nodarse
&.. Associates} Inc.
s j:" 0 '1 n I,I".~....
..... ....... \,; c::130
(OMUII!I ',"",~,., . . ~,
..(\i., t.. J', '" ~ .1'( :- 1:, A....S
. ~.,' ,,\ t.'; L;;&""il~
ORLMiDJ, FWf@:\
September 27, 1996
Project No. 95-E-0384
TO: CPR Engineers
1104 East Robinson Street
Orlando, Florida 32801
Attn: Mr. Terry Zaudtke
RE: Additional Consulting Services
Winter Springs Well #6
Winter Springs, Seminole County, Florida
Dear Mr. Zaudtke:
In accordance with your request, L.J. Nodarse & Associates, Inc. (UN) is pleased to present for your review
our scope of services and estimated costs to complete monitoring of the installation of the City of Winter Springs
Water Supply Well #6. .
Based on our understanding of the required scope, the following is our recommended scope of services:
1. Oversee drilling of new 15 inch hole to a depth of 250 feet.
2. Oversee installation of 10 inch liner including installation and grouting.
3. Oversee drilling of 9 7/8 inch open hole from 250 to 400 feet.
4. Oversee well development.
5. Review pump test procedures prior to initiation of pwnp test and pump test final data.
Attachment A is a breakdown of our estimated cost to complete these tasks. In addition, we have also included
a breakdown of costs incurred in Attachment A that were over and above our initial scope of services contained
in our originaL proposal.
CLOSURE
UN appreciates the opportunity to submit this proposal and we look forward to working with you on this project.
If you have any questions or if we can provide any additional information, please feel free to call us at your
convenience.
Sincerely,
al Nodarse, P.E.
L.J. NODARSE & ASSOCIATES, INC.
V ( ~ -rT~,ty
~vid B. Twedell
Principal Scientist
DBT/UN:cah 5-384.dd.sv.
Geotechnical, Environmental. &. Materials Engineers
807 South Orlando Avenue + Suite A + Winter Park. Florida 32789 + Telephone 407.740.6110 + Facsimile 407.740.6112
7.
ATTACH~rENT A
ESTLvlATED COSTS
CITY OF WINTER SPRINGS
WELL #6
f
1.
Oversight of 15 inch hole to 250 feet
Senior Geologist
]2 hrs @ S95.00/hr
$1,140.00
2.
Oversee 10 inch liner lnstllilation and grouting
Senior Geologist
12 hrs @ $95.00/hr
1,140.00
3.
Oversee drilling of 9 7/8 inch hole to 400 feet
Senior Geologist
24 hrs @ $95.00/hr
2,280.00
4.
\Vell. development oversight
Senior Geologist
8 hrs @ $95.00/hr
760.00
5.
Pump test proce.dures a'1d data revic,\'/
Senior Geologist
4 hrs @ $95.00ihr
380.00
6.
Oversight of 3 inch monitoring weU pump test including data
logger, four hour pump test and data review
Senior E:1Vironmcntal Technician
7 hrs @ $45.00/hr
Senior Geologist.
2 hrs @ $95.00/hr
Data Logger Rental
190.00
275.00
315.00
MeeUngs, additional ol~-site well construction monitoring
Senior Ge(llogist
25 hrs @ $95.ODihr
-L.3.liOO
TOTAL ESTL\lA TED PROJECT COSTS
$8,855.00
.. ....' H'......' "." I." .."'.. ..u~1 .\. ,,,."" ...... ',W'" ',." ..;.-,;,,,..;;.""';.......~..:j.:.....,n.;~:.:~.t
EXHIBIT II
SUPPLEMENT NO.2
COST ANALYSIS
Inspection Services - L. J. Nodarse
SUBTOTAL (Supplement No.2)
$ 8,855.00
$8,855.00
Original Authorization Amendment
32 (Design and Permitting) $15,000.00
Supplement No. 1 - Construction
Administration 11,840.00
Supplement No.2 - Inspection Services 8,855.00
TOTAL AUTHORIZATION $35,695.00
h. __...._.......,._.'.... ...~.._",......~u......L...,;,.. ......,..,......~ .,....
. ....:.....'....."..J
Attachment No. 2
MEMORANDUM
TO:
Mr. Kipton D. Lockcuff, P.E., City Of Winter Springs, Director Of Utilities
THROUGH: Terry Zaudtke, P.E. - Conklin Porter and Holmes, Engineers
FROM: David B. Twedell, L.J. Nodarse & Associates, Inc.
David H. Kincaid, P.G. - Kincaid Environmental Services, Inc.
DATE: October 8, 1996
SUBJECT: Winter Springs Potable Water Supply Well No.6
This memo will serve as an update with regard to the project statUs of municipal supply well No.
6, for the City of Winter Springs. In accordance with your request, this memo will summarize
the well completion status, problems encountered during well installation and proposed options
which may eliminate the problems.
As you are aware, two wells exist at the site located at the eastern end of Clearn Court. The first
well is a 3-inch diameter test well and the other is a 16-inch diameter production well. The wells
are approximately 50 feet from each other. During the installation of the wells, unstable geologic
strata were encountered at both locations. The drilling contractor has taken appropriate steps to
minimize the difficulities associated with the unstable zones. However, the 16-inch diameter
production well is unfinished at this time due to the difficulties encountered and this well
requires additional work for completion.
Construction at both wells includes outer steel surface casings. Surface casings are typically
installed to stabilize unconsolidated (uncemented), unstable geologic strata such as sand, silt,
clayey sand, etc. Stabilization is necessary to prevent borehole collapse and the possible
forma.tion of collapse features. The inner, 3-inch diameter casing of the first well was installed
to a depth of 250 feet, with the lower-most 180 feet consisting of uncased open-hole section
within limestone strata. The well was installed to provide stratigraphic information, water quality
data and to monitor aquifer hydraulic characteristics during testing of the production well.
However, due to unstable downhole geologic conditions, it became necessary to case the hole
to stabilize it. Based on review of the driller's log, sandy clay was encountered down to a depth
of 20 feet. Below this unit, a layer of clay (with a little sand) was encountered from 20 feet
down to the top of the limestone which was encountered at a depth of 52 feet below land
surface. Limestone continued from this depth down to a depth of 220 feet, where a 25-foot thick
layer of silica sand was encountered down to a depth of 245 feet. Once through this sand zone,
the 3-inch diameter steel casing was set and grouted into limestone at a depth of 250 feet to
eliminate the sand and stabilize the hole. Following the casing set and grouting, the test hole was
continued. Limestone was encountered from 245 feet and continued down to the termination
depth of 430 feet. A cavity zone was encountered at a depth of 340 feet, as evidenced by the
100% loss of drilling fluid. Typically, cavity zones may provide much of the water production
for a well. A water quality sample was collected after well installation. Based on water quality
. 'I
2
results, water quality is good within the 250-430 foot zone.
Prior to the installation of the production well, a 6-inch diameter test hole was completed to a
depth of 298 feet to collect stratigraphic data. The surface casing had been previously installed
prior to drilling activities at this location. The 6-inch diameter test hole was advanced through
the unconsolidated sand, and clayey sediments down to limestone. Limestone was encountered
at a depth of 58 feet. The test hole was continued down to the termination depth of 298 feet. At
a depth of 100 feet, a loss of drilling fluid occured, indicating a cavity zone. Below this cavity
zone, limestone was encountered down to 298 feet. Based on the occurrence of sand in the first
test well within the 220-245 foot zone, drill cuttings were closely inspected to observe for the
occurrence of silica sand. No silica sand was encountered below the top of limestone (52 feet)
in the 6-inch diameter test hole.
Following completion of the test hole, a 23-inch diameter drill bit was used to enlarge the hole
in order to set the 16-inch diameter well casing into position. The 23-inch hole was advanced
to a depth of approximately 147 feet, when a small area subsided approximately 6 feet southeast
of the well. The area was approximately 6 feet in diameter and 5 feet deep. The following day,
it was observed that the borehole had been filled with silica sand up to a depth of 123 feet.
During drilling, sand from overlying zone(s) had apparently raveled downward and allowed
overlying sediments to collapse. The subsided area was backfilled with sand and no further
collapse at that location has occurred. To eliminate this unstable condition, a decision was made
to set the 16-inch casing and pressure grout it into position, as deep as possible withinin this
unstable zone. Casing sections were welded together and lowered downhole. A header plate with
a pipe connector was welded on the top of the uppermost casing section. The intent was to pump
grout under high pressure, down the center of the casing while slightly raising and lowering the
casing, to wash the casing down to a deeper depth. However, when this was tried, the borehole
collapsed again and the raveled sand could not be dislodged. Following this procedure, the
bottom of the 16-inch diameter casing was at a depth of 89 feet below land surface. The casing
was grouted into position at this depth. Following grouting, the open hole section of the well
was extended to a depth of 218 feet below land surface. Drilling was stopped at that depth
because the production capacity appeared to be appropriate and no other difficulties had been
encountered to that depth.
Following completion of the well, an aquifer pumping test was initiated on August 30, 1996.
The piping from the well was connected to the discharge line which terminates at the water plant
and the test was begun. Immediately after starting the pumping, the in-line flow meter became
erratic and then inoperative. The flow meter transducer was removed and found to be clogged
with limestone silt and sand. The transducer was cleaned and reinstalled in an effort to continue
the test. However, the transducer became inoperative again within 2-5 minutes. At that time, a
small discharge spigot located near the flow transducer was opened to inspect for sand, etc. The
discharge was extremely milky in color and contained significant quantities of limestone sand
and silt and small limestone fragments from the drilling operation. Because of this, an accurate
test could not be performed so the test was aborted and the pump man was instructed to continue
pumping to clean out the well. The initial pumping rate was estimated to be approximately 1,200
"
3
gpm. The pumping rate was increased to approximately 2,000 gpm to better clear the well. A
short time afterward, the well began to pump silica sand and an additional small area subsided
approximately 4 feet northeast of the well. This feature is approximately 8 feet in diameter and
approximately 6-7 feet in depth. When the subsidence occurred, pumping was stopped. No
additional drilling or pumping has been performed at the site since.
Geophysical logging was recently performed on the well to provide additional borehole data and
confirm borehole characteristics. Based on logging results, the bottom of the open hole is at a
depth of 201 feet, indicating some additional ravelling and subsequent infilling of the well. Also,.
an enlarged cavity zone occurs from approximately 92-100 feet in depth.
Based on the small areas of subsidence and the problems associated with silica sand encountered
during drilling and grouting procedures, it is apparent that the zone from the top of limestone
(52 feet) down to a depth of at least 100 feet is unstable and continues to provide a connection
to land surface. The well has an unstable zone therefore, from the bottom of the casing (89 feet)
down to a depth of at least 100 feet.
Based on this problematic condition, several options were discussed at a meeting with City
personnel. Options discussed included:
Option 1 - Well Abandonment And New Well Construction
This option would propose the abandonment of the existing well and construct a new well,
hopefully at a new location. However, the City has already incurred most of the cost of the well
and a new location may have additional geologic difficulties. It should be noted that valuable
data has been collected during all phases of drilling and well construction at this site. This data
helps to build an understanding of subsurface geologic conditions, and how to overcome such
conditions. Starting a new well yields the highest level of risk (unknowns). By starting a new
well, the City would be starting the whole process over again. As such, well abandonment and
new well construction is not recommended at this time.
Option 2 - Well Capping
This option would propose the capping of the existing well and no additional work. The water
management district would need to be contacted to determine if capping would be acceptable.
This option does nothing to increase the City's water supply capacity. Additionally, the water
management district will most likely require abandonment at some time in the future if the well
is not put into service.
Option 3 - Well Modifications
This option would propose modifications to the eXIstmg production well in an attempt to
eliminate the pumping of silica sand. With this option, the openhole section of the well would
be backfilled with sand up to a depth of approximately 105 feet to temporarily plug off most of
! ,,,
.
4
the open hole section. Following backfilling, the zone around the bottom of the casing (89 feet)
down to 105 feet would be pressure grouted to force the grout out into the limestone to seal off
the connection to land surface. The water management district will likely be in favor of this, if
not actually requiring it. Following grouting, a borehole will be redrilled to a depth of 250 feet.
A lO-inch diameter well casing will be set at this depth and grouted into position through the
center of the existing 16-inch diameter casing. The lO-inch diameter casing will seal off the
unstable, problematic zone(s) encountered which are producing the silica sand. It is believed that
this option will provide the best solution for the problems encountered and be the most cost
effective solution as well. Accordingly, this option is recommended.
As discussed during the meeting with City personnel, the site is situated in the general vicinity
of the 51. Johns River system. Within this system, geologic faults have been documented. These
geologic faults can produce very complex and difficult conditions during the drilling of water
wells. Accordingly, rehabilitative modifications to water supply wells within this area should be
considered somewhat of a risk. It is possible that modifications to this well may not correct all
possible problems. Additionally, assumming that modifications are successful in eliminating the
silica sand, the well production flow capacity will remain unknown until well modifications have
been completed and the well tested. However, much information has been obtained at this site.
As each difficulty has been encountered, the situation has been evaluated by the engineer, the
geologist and the drilling contractor. Although it is difficult to assign a statistical probability of
success in this situation, the relative probability for the successful completion of this well is
believed to be very high, based on data obtained at the site. Given this, it is believed that this
well can be successfully modified to provide a seviceable well for the City.
Attachment No. 3
TEST WELL 4 INCH DIAMETER
1 Mobilization! Demobilization LS 1 7,420.00 7,420.00 1 7,420.00
2 F&I - 4" Well Casing FT 100 15.00 1,500.00 100 1,500.00
3 Drilling Open Borehole FT 400 8.00 3,200.00 30 240.00
4 Water Quality and Analysis Each 8 250.00 2,000.00 2 500.00
5 Geo h ical Well Surve LS 1 2000.00 2 000.00 0 0.00
WATER SUPPLY WELL NO.6
6 Mobilization! Demobilization LS 1 12,000.00 12,000.00 1 12,000.00
7 F & I - 24" Well Casing FT 100 83.00 8,300.00 52 4,316.00
8 Drilling Open Borehole - 23" FT 110 23.00 2,530.00 95 2,185.00
9 F & I - 16" Well Casing FT 210 28.00 5,880.00 89 2,492.00
10 Grout 16" well Casing Sack 270 12.00 3,240.00 120 1,440.00
11 Drilling Open Borehole - 15" FT 220 16.00 3,520.00 103 1,648.00
12 F & I and Remove Test Pump LS 1 2,500.00 2,500.00 1 2,500.00
13 Well Development Hour 24 90.00 2,160.00 24 2,160.00
14 Aquifer Performance Test LS 1 7,500.00 7,500.00 1 7,500.00
15 Physical/Chemical Sampling and Testing LS 1 4,000.00 4,000.00 1 4,000.00
16 Disinfection LS 1 1,000.00 1,000.00 2 2,000.00
17 Bacteriological Testing LS 1 2,000.00 2,000.00 1 2,000.00
18 Priority Pollutant Testing LS 1 3,000.00 3,000.00 1 3,000.00
19 Pump and Motor Each 1 6,000.00 6,000.00 1 6,000.00
20 Well Column LF 70 175.00 12,250.00 70 12,250.00
21 Concrete Pedestal, etc. LS 1 20,000.00 20,000.00 1 20,000.00
22 Electrical LS 1 18 000.00 18,000.00 1 18 000.00
Original Bid Amount $130,000.00
Revised Subtotal - Original Bid Items Only $113,151.00
CHANGE ORDER NUMBER 1 4" Test Well authorized 5/29/96
3 Delete 370 LF @ $8.00/LF LF -370 8.00 (2,960.00)
4 Delete 5 tests @ $250/test EA -5 250.00 (1,250.00)
5 Delete Geophysical well survey EA -1 2,000.00 (2,000.00)
A Mobilization of small drill rig for 3" hole LS 1 1,500.00 1,500.00
B 3" steel casing LF 250 3.55 887.50
C Cement Grout Sack 13 12.00 156.00
D Drilling Mud Sack 32 8.35 267.20
E Drilling rig hourly rate Hr 43.5 150.00 6,525.00
F Open borehole LF 180 6.00 1,080.00
G Sand ocket dred in Hr 24 150.00 3 600.00
Subtotal C.O. 1 $7,805.70
CHANGE ORDER NUMBER 2
H Steel Casing pipe 814.38
I Re-stockin for unused 16" casin 649.02
Subtotal C.O. 2 $1,463.40
CHANGE ORDER NUMBER 3
4 Delete 1 @ $ 250/EA. -1 250.00 (250.00)
7 Delete 48 LF @ $83.00/LF -48 83.00 (3,984.00)
8 Delete 15 LF @ $23.00/LF -15 23.00 (345.00)
9 Delete 121 LF @ $28.00/LF -121 28.00 (3,388.00)
10 Delete 150 sacks @ $12.00/Sacks -150 12.00 (1,800.00)
11 Delete 117 LF @ $16.00/LF -117 16.00 (1,872.00)
J Geophysical well log of 16" well 1 2,000.00 2,000.00
K R emobilization!demobilizatlon 1 9,000.00 9,000.00
L Mobilization of special Pressure Grout Equip. 1 5,000.00 5,000.00
M Backfill well for pressure grout 8 50.00 400.00
N Pressure grout 16" well per SJRWMD 120 12.00 1,440.00
0 Drill out sand backfill 129 10.00 1,290.00
P F & 110" casing 170 24.00 4,080.00
Q Cement 10" casing 286 12.00 3,432.00
R Drill 9-7/8 " open borehole 150 15.00 2,250.00
S Provide left hand coupling and nipple 1 1,500.00 1,500.00
T Geophysical well log of proposed 10" well 1 2,000.00 2,000.00
U F & I and Remove Test Pum 1 1,800.00 1,800.00
Subtotal C.O. 3 $22 553.00
REVISED PROJECT COST $161,822.10
Attachment No.4
CONTRACT CHANGE ORDER
Change Order No. 3
Engineer Project No.
W0446.01
Project Title:
Water Supply Well No.6
Contractor:
American Drilling, Inc.
Reason for Change: Additional items are required due to unforeseen below surface conditions.
Breakdown of Proposed Changes and Basis for Payment
(Includes pertinent drawings, specifications, and documentation where necessary)
Item No. and Description
Change in Contract
Cost + (-)
Deletions:
Item 4: Revise quantity to 2. Delete 1 @ $250.00
Item 7: Revise quantity to 52 ft. Delete 48 ft @ $83.00/ft.
Item 8: Revise to 95 ft. Delete 15 feet @ $23.00/ft.
Item 9: Revise quantity to 89 ft. Delete 121 ft @ $28.00/ft.
Item 10: Revise quantity to 120 sacks. Delete 150 sacks at $12.00/sack
Item 11: Revise quanity to 103 ft. Delete 117 ft @ $16.00/ft.
TOTAL DELETIONS:
($250.00)
(3,984.00)
($345.00)
($3,388.00)
($1,800.00)
($1,872.00)
($11,639.00)
Additions:
Item J. Geophysical Well Logging 16" Well
Item K. Remobilization/demobilization of drill rig
Item L. Mobilization of special grout equipment
Item M. Backfill well for pressure grout, 8cy @ $50.00/cy
Item N. Pressure grout well per SJRWMD. 120 sacks at $2.00/sack
Item O. Drill out sand backfill - 129 ft @$lO.OO/ft.
Item P. F & I 10" casing - 170 ft @ $24.00/ft.
Item Q. Cement 10" casing, 286 sacks @ $12.00/sack
Item R. Drill a 7/8" open bore hole - 150 ft @ $15.001ft.
Item S. Provide left hand coupling and nipple
Item T. Geophysical log of 10. well
Item U. F & I and remove test pump.
$ 1,000.00
2,000.00
9,000.00
5,000.00
400.00
1,440.00
1,290.00
4,080.00
3,432.00
2,250.00
1,500.00
2,000.00
1,800.00
TOTAL ADDITIONS:
$34,192.00
(1) Total Proposed Change in Contract Cost +(-)
$
$
22.553.00
(2) Original Contract Price
130.000.00
(3) Total All Previous Change Orders (Change Order No.1 thro 2)
$
9.269.10
(4) New Contract Price (Total of Item 1 & Item 4)
$
161.882.10
Recommended By Engineer:
Date:
Accepted By Contractor:
Date:
Accepted By Owner:
Date: